Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. Draft Contract AgreementPage 84 of 261 S-D Tunnel 2022 (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
Appears in 1 contract
Sources: Construction Contract
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. Draft Contract AgreementPage 84 of 261 S-D Tunnel 2022 .
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.. Page 83 of 146