Common use of Procedure for Change of Scope Clause in Contracts

Procedure for Change of Scope. 13.2.1 In the event of the Employer determining that a Change of Scope is necessary, it may direct the Employer's Engineer to issue to the Contractor a notice specifying in reasonable detail the works and services contemplated thereunder (the "Change of Scope Notice") 13.2.2 Upon receipt of a Change of Scope Notice, the Contractor shall, with due diligence, provide to the Employer and the Employer's Engineer such information as is necessary, together with preliminary documentation in support of: (a) the impact, if any, which the Change of Scope is likely to have on the Project Completion Schedule if the works or services are required to be carried out during the Construction Period; and (b) the options for implementing the proposed Change of Scope and the effect, if any, each such option would have on the costs and time thereof, including the following details: (i) break down of the quantities, unit rates and cost for different items of work; (i) Proposed design for the Change of Scope; and

Appears in 1 contract

Sources: Epc Agreement

Procedure for Change of Scope. 13.2.1 In the event of the Employer determining that a Change of Scope is necessary, it may direct the Employer's Engineer to issue to the Contractor a notice specifying in reasonable detail the works and services contemplated thereunder (the "Change of Scope Notice") 13.2.2 Upon receipt of a Change of Scope Notice, the Contractor shall, with due diligence, provide to the Employer and the Employer's Engineer such information as is necessary, together with preliminary documentation in support of: (a) the impact, if any, which the Change of Scope is likely to have on the Project Completion Schedule if the works or services are required to be carried out during the Construction Period; and (b) the options for implementing the proposed Change of Scope and the effect, if any, each such option would have on the costs and time thereof, including the following details: (i) break down of the quantities, unit rates and cost for different items of work; (i) Proposed design for the Change of Scope; and

Appears in 1 contract

Sources: Epc Agreement

Procedure for Change of Scope. β€Œ 13.2.1 In the event of the Employer determining that a Change of Scope is necessary, it may direct the Employer's Engineer to issue to the Contractor a notice specifying in reasonable detail the works and services contemplated thereunder (the "Change of Scope Notice") 13.2.2 Upon receipt of a Change of Scope Notice, the Contractor shall, with due diligence, provide to the Employer and the Employer's Engineer such information as is necessary, together with preliminary documentation in support of: (a) the impact, if any, which the Change of Scope is likely to have on the Project Completion Schedule if the works or services are required to be carried out during the Construction Period; and (b) the options for implementing the proposed Change of Scope and the effect, if any, each such option would have on the costs and time thereof, including the following details: (i) break down of the quantities, unit rates and cost for different items of work; (i) Proposed design for the Change of Scope; and

Appears in 1 contract

Sources: Engineering, Procurement and Construction Agreement