Project Performance Monitoring System Sample Clauses
POPULAR SAMPLE Copied 1 times
Project Performance Monitoring System. The Borrower shall cause UCSA to ensure that implementation of the Project, operation of the Project facilities and the benefits derived from the Project are monitored and evaluated annually by the PPMU. This includes establishing a PPMS within 6 months of the Effective Date and providing results for incorporation in the Project progress and completion reports.
Project Performance Monitoring System. The Borrower shall cause MOTC to establish a PPMS within six (6) months of the Effective Date and collect baseline data for performance monitoring. The key indicators and assumptions outlined at the impact and outcome levels in the Project design and monitoring framework will be the primary data required for analysis.
Project Performance Monitoring System. Within 9 months after the Effective Date, BR with the support of consultants shall establish a project performance monitoring system in line with the targets, indicators set in the DMF. Within 12 months of the Effective Date, the baseline data corresponding to indicators and targets set out in the project status report shall be updated during the detailed design stage, disaggregated by income levels and sex as required. After the initial baseline survey, the PIU with support of the consultants shall conduct annual survey and quarterly monitoring of indicators and submit quarterly report to ADB throughout project implementation.
Project Performance Monitoring System. Within 6 months after the Effective Date, the EA shall develop a web-based project performance monitoring and reporting system, which shall include functions for accounting and expenditures the rehabilitation and reconstruction program implementation, concurrent evaluation of impacts, outcomes, outputs and activities in relation to targets and milestones established for the project and the overall rehabilitation and reconstruction program for the earthquake affected areas in Nepal. The EA will prepare monitoring reports in a pre-approved uniform format for all donors, covering key aspects of the rehabilitation and reconstruction program.
Project Performance Monitoring System. The State shall ensure that PMU establishes the a Project Performance Monitoring System (PPMS) acceptable to ADB to monitor indicators including (i) physical progress for infrastructure works, (ii) institutional development and capacity building, and (iii) impact assessment indicators. The State shall ensure that the PMU shall conduct initial baseline physical and socio-economic surveys and submit a detailed implementation plan for monitoring performance and for preparing benchmark information for ADB's review and concurrence within six months of the Effective Date. Thereafter, the PMU shall submit annual monitoring and evaluation reports to ADB throughout the Project implementation.
Project Performance Monitoring System. Within 9 months after the Effective Date, the EA and SPO with the support of the consultants shall establish a Project Performance Monitoring System in line with the targets, indicators set in the Project’s design monitoring framework. Within 12 months of the Effective Date, the baseline data corresponding to indicators and targets set out in the Project status report shall be updated during the detailed design stage, disaggregated by income levels and sex as required. After the initial baseline survey, the EA with support of the consultants, shall conduct annual survey and quarterly monitoring of indicators and submit quarterly report to ADB throughout Project implementation.
Project Performance Monitoring System. The Beneficiary shall ensure that progress monitoring, safeguard monitoring and benefit monitoring and evaluation shall be carried out during Project implementation by the Project Executing Agency and the IAs. Post-evaluation shall be carried out three (3) years after Project completion. A Project Performance Management System (PPMS) shall be developed on the basis of the Project design and monitoring framework to examine the Project’s technical performance, evaluate delivery of Project facilities, assess achievement of Project objectives and measure the Project’s social, economic, financial and institutional impacts. Baseline and periodic surveys shall be carried out to collect data disaggregated by income group, gender, types of vulnerability and other characteristics as appropriate. Consultant services shall be provided to assist the Project Executing Agency and IAs to jointly develop and implement the PPMS.
Project Performance Monitoring System. Within 3 months after the Effective Date, the MEE with the support of the PMU shall establish a PPMS in line with the targets and indicators set in the DMF. Within 12 months of the Effective Date, the baseline data corresponding to indicators and targets set out in the project status report shall be updated during the detailed design stage, disaggregated by income levels and gender as required.
Project Performance Monitoring System. Within twelve (12) months of the Effective Date, the Recipient shall cause MOF and MOFA to ensure the establishment of a Project performance monitoring system acceptable to ADB and the Recipient.
Project Performance Monitoring System. Within 6 months of the effectiveness of this Grant Agreement, the Recipient shall ensure that the Project Performance Monitoring System will have been established.