The 'Provisional Items' clause defines how certain items or works in a contract are included on a provisional basis, meaning their necessity or scope is not yet fully determined at the time of agreement. In practice, this clause allows the contract to list specific tasks, materials, or services with estimated quantities or costs, which may be adjusted or omitted as the project progresses and actual needs become clear. Its core function is to provide flexibility in project planning and budgeting, ensuring that unforeseen or variable elements can be addressed without requiring a formal contract amendment.
Provisional Items. The full amount of provisional lumpsums and the value annexed to each provisional item inserted in the tender documents shall be deducted from the contract sum and the value of work ordered and executed thereunder shall be ascertained by measurement or valuation as for deviations. No work under these items is to be begun without instructions in writing from the Engineer-in-charge. The extent of quantities or items described as “Provisional” shall not be held to guarantee or limit the amount and description of the work to be executed by the contractor either in respect of the items concerned or the work as a whole. No addition or deduction shall be made by the Contractor to the amount of the provisional lumpsums as included in the tender documents.
Provisional Items. After the tender closing, the Items in the Form of Tender noted as being “Provisional” may have quantities modified or may be deleted from the Contract at the sole discretion of the Owner without negotiating with the bidders regardless of the percentage of the Tender the individual or combined “Provisional Items” represent. No consideration for loss of overhead costs or loss of profit on work not performed will be considered should these Items be deleted from the Contract.
Provisional Items. Items of work that may be required during the course of construction, but the exact requirements of which will depend on ground conditions or other uncertain factors encountered, are shown as "Provisional Items". These quantities are anticipated to vary significantly, or may not be used at all. The Contractor shall price these items accordingly and shall not claim any anticipated loss of profit or increased overhead if any or all of these items is deleted altogether.
Provisional Items. E21.1 The Provisional Items listed on Form B: Prices are part of the Contract.
Provisional Items. E15.1 The Provisional Items listed on Form B: Prices are part of the Contract. E15.2 The Contractor shall not perform Work included in the Provisional Items without prior authorization from the Contract Administrator. All Work included in the Provisional Items will be carried out within the construction areas shown on the Drawings.
Provisional Items. E25.1 The Provisional Items listed on Form B: Prices are part of the Contract. E25.2 The Contractor shall not perform Work included in the Provisional Items without prior authorization from the Contract Administrator. All Work included in the Provisional Items will be carried out within the construction areas shown on the Drawings. E25.3 Notwithstanding GC:7, the City reserves the right to diminish all or any portion of the items of work listed in the Provisional Items and no claim shall be made for damages on the grounds of loss of anticipated profit or for any other reason.
Provisional Items. Items of work that may be required during the course of construction, but the exact requirements of which will depend on ground conditions or other uncertain factors encountered, are shown as "Provisional Items". These quantities are anticipated to vary significantly, or may not be used at all. The Contractor shall price these items accordingly and shall not claim any anticipated loss of profit or increased overhead if any or all of these items is deleted altogether. The main item under provisional will be the application of a stabilizer within the granular course. This item is to be calculated on a distribution rate of 3 l/m2 using products such as Calcium, Magnesium or Entac (or equivalent). The Contractors in using equivalent products shall provide technical information to the Municipality as to the equivalency rate to support their proposal. This item is further discussedin the supplemental provision.

Related to Provisional Items

  • Additional Items The Insurer shall have received such other documents, instruments, approvals or opinions requested by the Insurer or its counsel as may be reasonably necessary to effect the Transaction, including, but not limited to, evidence satisfactory to the Insurer and its counsel that the conditions precedent, if any, in the Transaction Documents have been satisfied.

  • Provisional Application Upon signature of this Compact, and until this Compact has entered into force in accordance with Section 7.3, the Parties will provisionally apply the terms of this Compact; provided that, no MCC Funding, other than Compact Implementation Funding, will be made available or disbursed before this Compact enters into force.

  • Provisional Measures 1. The judicial authorities shall have the authority to order prompt and effective provisional measures: (a) to prevent an infringement of any intellectual property right from occurring, and in particular to prevent the entry into the channels of commerce in their jurisdiction of goods, including imported goods immediately after customs clearance; (b) to preserve relevant evidence in regard to the alleged infringement. 2. The judicial authorities shall have the authority to adopt provisional measures inaudita altera parte where appropriate, in particular where any delay is likely to cause irreparable harm to the right holder, or where there is a demonstrable risk of evidence being destroyed. 3. The judicial authorities shall have the authority to require the applicant to provide any reasonably available evidence in order to satisfy themselves with a sufficient degree of certainty that the applicant is the right holder and that the applicant’s right is being infringed or that such infringement is imminent, and to order the applicant to provide a security or equivalent assurance sufficient to protect the defendant and to prevent abuse. 4. Where provisional measures have been adopted inaudita altera parte, the parties affected shall be given notice, without delay after the execution of the measures at the latest. A review, including a right to be heard, shall take place upon request of the defendant with a view to deciding, within a reasonable period after the notification of the measures, whether these measures shall be modified, revoked or confirmed. 5. The applicant may be required to supply other information necessary for the identification of the goods concerned by the authority that will execute the provisional measures. 6. Without prejudice to paragraph 4, provisional measures taken on the basis of paragraphs 1 and 2 shall, upon request by the defendant, be revoked or otherwise cease to have effect, if proceedings leading to a decision on the merits of the case are not initiated within a reasonable period, to be determined by the judicial authority ordering the measures where a Member's law so permits or, in the absence of such a determination, not to exceed 20 working days or 31 calendar days, whichever is the longer. 7. Where the provisional measures are revoked or where they lapse due to any act or omission by the applicant, or where it is subsequently found that there has been no infringement or threat of infringement of an intellectual property right, the judicial authorities shall have the authority to order the applicant, upon request of the defendant, to provide the defendant appropriate compensation for any injury caused by these measures. 8. To the extent that any provisional measure can be ordered as a result of administrative procedures, such procedures shall conform to principles equivalent in substance to those set forth in this Section. SECTION 4: SPECIAL REQUIREMENTS RELATED TO BORDER MEASURES12

  • Personal Items 15.6.1 We shall not be responsible in any way for your personal furniture, jewellery, other valuables, cash, credit cards, cheques, documents or other personal possessions unless we have been fraudulent or breached this Agreement in respect of your belongings. 15.6.2 If you wish to bring in large personal items (for example, furniture), into the Residence, you must ask the General Manager in writing before you move in. Any decision to allow personal items to be brought into, and used in, the Residence is at the discretion of the General Manager. 15.6.3 Your personal items must not constitute a fire hazard or a health and safety risk, or disturb the peaceful enjoyment of the Residence by other residents and employees.

  • Adding agenda items Any agenda item requiring a decision by the Members must be identified as such on the agenda. Any Member may add an item to the original agenda by written notification to all of the other Members no later than 7 calendar days preceding the meeting.