Quality control system. 11.2.1 The Contractor shall establish a Quality Control Mechanism, Quality Assurance Plan (the “Quality Assurance Plan” or “QAP”), Material Testing Plan (the “Material Testing Plan” or “MTP”) and Method Statements for execution of works (the “Method Statements” or “MS”) in consultation of Authority Engineer. 11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the Authority Engineer its Quality Control Mechanism, QAP, MTP and MS which shall include the following: (a) organisation, duties & responsibilities, procedures, inspections & documentation; (b) quality control mechanism including sampling and testing of Materials, tests required during the execution of works and frequencies by Contractor and Authority Engineer, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing & calibration in accordance with the Specifications & Standards and Good Industry Practice; and (c) internal quality audit system. The Contractor shall carry out internal audits of the Quality management System regularly, and at least once every 6 months. The Contractor shall submit to the Engineer a report listing the results of each internal audit within 7 days of completion. Each report shall include, where appropriate, theproposed measures to improve and/or rectify the Quality Management System and/or its implementation. 11.2.3 The Authority Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
Appears in 5 contracts
Sources: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement
Quality control system. 11.2.1 The Contractor shall establish a Quality Control MechanismControlMechanism, Quality Assurance Plan (the “Quality Assurance Plan” or “QAPPlan”or“QAP”), Material Testing Plan (the “Material Testing Plan” or “MTPPlan”or“MTP”) and Method Statements for execution of works (the “Method Statements” or “MSStatements ”or“MS”) in consultation of Authority Engineer.
11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the Authority Engineer its Quality Control Mechanism, QAP, MTP and MS which MSwhich shall include the following:
(a) organisation, duties & and responsibilities, procedures, inspections & and documentation;
(b) quality control mechanism including sampling and testing of Materials, tests required during the execution of works and frequencies by Contractor and Authority Engineer, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing & and calibration in accordance with the Specifications & Standards and Standardsand Good Industry Practice; and
(c) internal quality audit system. The Contractor shall carry out internal audits of the Quality management System regularlyregulary, and at least once every 6 months. The Contractor shall submit to the Engineer AuthorityEngineer a report listing the results of each internal audit within 7 days of completion. Each report shall include, where appropriate, theproposed the proposed measures to improve and/or rectify the Quality Management System and/or its implementation.
11.2.3 . The Authority Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets, Materials and workmanship in accordance with the Quality Assurance Plan.
11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.
Appears in 4 contracts
Sources: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement
Quality control system. 11.2.1 The Contractor shall establish a Quality Control Mechanism, Quality Assurance Plan (the “Quality Assurance Plan” or “QAPPlan”or“QAP”), Material Testing Plan (the “Material Testing Plan” or “MTPPlan”or“MTP”) and Method Statements for execution of works (the “Method Statements” or “MSStatements ”or“MS”) in consultation of Authority Engineer.
11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the Authority Engineer its Quality Control Mechanism, QAP, MTP and MS which MSwhich shall include the following:
(a) organisation, duties & and responsibilities, procedures, inspections & and documentation;
(b) quality control mechanism including sampling and testing of Materials, tests required during the execution of works and frequencies by Contractor and Authority Engineer, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing & and calibration in accordance with the Specifications & and Standards and Good Industry Practice; and
(c) internal quality audit system. The Contractor shall carry out internal audits of the Quality management System regularlyregulary, and at least once every 6 months. The Contractor shall submit to the Authority Engineer a report listing the results of each internal audit within 7 days of completion. Each report shall include, where appropriate, theproposed the proposed measures to improve and/or rectify the Quality theQuality Management System and/or its implementation.
11.2.3 . The Authority Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets, Materials and workmanship in accordance with the Quality Assurance Plan.
11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.
Appears in 3 contracts
Sources: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement
Quality control system. 11.2.1 The Contractor shall establish a Quality Control Mechanism, Quality Assurance Plan (the “Quality Assurance Plan” or “QAP”), Material Testing Plan (the “Material Testing Plan” or “MTP”) and Method Statements for execution of works (the “Method Statements” or “MS”) in consultation of Authority Engineer.
11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the Authority Engineer its Quality Control Mechanism, QAP, MTP and MS which shall include the following:
(a) organisation, duties & and responsibilities, procedures, inspections & and documentation;
(b) quality control mechanism including sampling and testing of Materials, tests required during the execution of works and frequencies by Contractor and Authority Engineer, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list checklist for site activities, and proforma for testing & and calibration in accordance with the Specifications & and Standards and Good Industry Practice; and
(c) internal quality audit system. The Contractor shall carry out internal audits of the Quality management Management System regularly, and at least once every 6 months. The Contractor shall submit to the Engineer a report listing the results of each internal audit within 7 days of completion. Each report shall include, where appropriate, theproposed the proposed measures to improve and/or and / or rectify the Quality Management System and/or and / or its implementation.
11.2.3 . The Authority Engineer shall convey its comments to the Contractor within a period of 21 (twenty-twenty- one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets, Materials and workmanship in accordance with the Quality Assurance Plan.
11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.
Appears in 2 contracts
Sources: Epc Agreement, Epc Agreement
Quality control system. 11.2.1 The Contractor shall establish a Quality Control Mechanism, Quality Assurance Plan (the “Quality Assurance Plan” or “QAPPlan”or“QAP”), Material Testing Plan (the “Material Testing Plan” or “MTPPlan”or“MTP”) and Method Statements for execution of works (the “Method Statements” or “MSStatements ”or“MS”) in consultation of Authority EngineerSPV’s Engineer .
11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the Authority SPV’s Engineer its Quality Control Mechanism, QAP, MTP and MS which shall include the following:
(a) organisation, duties & and responsibilities, procedures, inspections & and documentation;
(b) quality control mechanism including sampling and testing of Materials, tests required during the execution of works and frequencies by Contractor and Authority EngineerSPV’s Engineer , standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing & and calibration in accordance with the Specifications & and Standards and Good Industry Practice; and
(c) internal quality audit system. The Contractor shall carry out internal audits of the Quality management System regularlyregulary, and at least once every 6 months. The Contractor shall submit to the Engineer a report listing the results of each internal audit within 7 days of completion. Each report shall include, where appropriate, theproposed the proposed measures to improve and/or rectify the Quality Management System and/or its implementation.
11.2.3 . The Authority SPV’s Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets, Materials and workmanship in accordance with the Quality Assurance Plan.
11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.
Appears in 1 contract
Sources: Epc Agreement
Quality control system. 11.2.1 The Contractor shall establish a Quality Control MechanismControlMechanism, Quality Assurance Plan (the “Quality Assurance Plan” or “QAPPlan”or“QAP”), Material Testing Plan (the “Material Testing Plan” or “MTPPlan”or“MTP”) and Method Statements for execution of works (the “Method Statements” or “MSStatements ”or“MS”) in consultation of Authority Engineer.
11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the Authority Engineer its Quality Control Mechanism, QAP, MTP and MS which shall include the following:
(a) organisationOrganization, duties & and responsibilities, procedures, inspections & and documentation;
(b) quality control mechanism including sampling and testing of Materials, tests required during the execution of works and frequencies by Contractor and Authority Engineer, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing & and calibration in accordance with the Specifications & and Standards and Good Industry Practice; and
(c) internal quality audit system. The Contractor shall carry out internal audits of the Quality management System regularlyregulary, and at least once every 6 months. The Contractor shall submit to the Engineer a report listing the results of each internal audit within 7 days of completion. Each report shall include, where appropriate, theproposed the proposed measures to improve and/or rectify the Quality Management System and/or its implementation.
11.2.3 . The Authority Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets, Materials and workmanship in accordance with the Quality Assurance Plan.
11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.
Appears in 1 contract
Sources: Engineering, Procurement and Construction (Epc) Agreement
Quality control system. 11.2.1 The Contractor shall establish a Quality Control Mechanism, Quality Assurance Plan (the “Quality Assurance Plan” or “QAP”), Material Testing Plan (the “Material Testing Plan” or “MTP”) and Method Statements for execution of works (the “Method Statements” or “MS”) in consultation of Authority Engineer.
11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the Authority Engineer its Quality Control Mechanism, QAP, MTP and MS which shall include the following:
(a) organisation, duties & and responsibilities, procedures, inspections & and documentation;
(b) quality control mechanism including sampling and testing of Materials, tests required during the execution of works and frequencies by Contractor and Authority Engineer, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing & and calibration in accordance with the Specifications & and Standards and Good Industry Practice; and
(c) internal quality audit system. The Contractor shall carry out internal audits of the Quality management System regularly, and at least once every 6 months. The Contractor shall submit to the Engineer a report listing the results of each internal audit within 7 days of completion. Each report shall include, where appropriate, theproposed the proposed measures to improve and/or rectify the Quality Management System and/or its implementation.
11.2.3 . The Authority Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets, Materials and workmanship in accordance with the Quality Assurance Plan.
11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.
Appears in 1 contract
Sources: Engineering, Procurement and Construction (Epc) Agreement
Quality control system. 11.2.1 The Contractor shall establish a Quality Control Mechanism, Quality Assurance Plan (the “Quality Assurance Plan” or “QAP”), Material Testing Plan (the “Material Testing Plan” or “MTP”) and Method Statements for execution of works (the “Method Statements” Statements ”or “MS”) in consultation of Authority Engineer.
11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the Authority Engineer its Quality Control Mechanism, QAP, MTP and MS which shall include the following:
(a) organisation, duties & and responsibilities, procedures, inspections & and documentation;
(b) quality control mechanism including sampling and testing of Materials, tests required during the execution of works and frequencies by Contractor and Authority Engineer, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing & and calibration in accordance with the Specifications & and Standards and Good Industry Practice; and
(c) internal quality audit system. The Contractor shall carry out internal audits of the Quality management System regularlyregulary, and at least once every 6 months. The Contractor shall submit to the Authority Engineer a report listing the results of each internal audit within 7 days of completion. Each report shall include, where appropriate, theproposed the proposed measures to improve and/or rectify the Quality theQuality Management System and/or its implementation.
11.2.3 . The Authority Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets, Materials and workmanship in accordance with the Quality Assurance Plan.
11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.
Appears in 1 contract
Sources: Standard Engineering, Procurement and Construction (Epc) Agreement
Quality control system. 11.2.1 The Contractor shall establish a Quality Control MechanismControlMechanism, Quality Assurance Plan (the “Quality Assurance Plan” or “QAPPlan”or“QAP”), Material Testing Plan (the “Material Testing Plan” or “MTPPlan”or“MTP”) and Method Statements for execution of works (the “Method Statements” or “MSStatements ”or“MS”) in consultation of Authority Engineer.
11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the Authority Engineer its Quality Control Mechanism, QAP, MTP and MS which shall include the following:
(a) organisation, duties & and responsibilities, procedures, inspections & and documentation;
(b) quality control mechanism including sampling and testing of Materials, tests required during the execution of works and frequencies by Contractor and Authority Engineer, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing & and calibration in accordance with the Specifications & and Standards and Good Industry Practice; and
(c) internal quality audit system. The Contractor shall carry out internal audits of the Quality management System regularlyregulary, and at least once every 6 months. The Contractor shall submit to the Engineer a report listing the results of each internal audit within 7 days of completion. Each report shall include, where appropriate, theproposed the proposed measures to improve and/or rectify the Quality Management System and/or its implementation.
11.2.3 . The Authority Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets, Materials and workmanship in accordance with the Quality Assurance Plan.
11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.
Appears in 1 contract
Sources: Engineering, Procurement and Construction (Epc) Agreement
Quality control system. 11.2.1 The Contractor shall establish a Quality Control Mechanism, Quality Assurance Plan (the “Quality Assurance Plan” or “QAP”), Material Testing Plan (the “Material Testing Plan” or “MTP”) and Method Statements for execution of works (the “Method Statements” or “MS”) in consultation of Authority Engineer.
11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the Authority Engineer its Quality Control Mechanism, QAP, MTP and MS which shall include the following:
(a) organisation, duties & and responsibilities, procedures, inspections & and documentation;
(b) quality control mechanism including sampling and testing of Materials, tests required during the execution of works and frequencies by Contractor and Authority Engineer, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing & and calibration in accordance with the Specifications & and Standards and Good Industry Practice; and
(c) internal quality audit system. The Contractor shall carry out internal audits of the Quality management Management System regularly, and at least once every 6 months. The Contractor shall submit to the Engineer a report listing the results of each internal audit within 7 days of completion. Each report shall include, where appropriate, theproposed the proposed measures to improve and/or and / or rectify the Quality Management System and/or and / or its implementation.
11.2.3 . The Authority Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets, Materials and workmanship in accordance with the Quality Assurance Plan.
11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.