WREGIS Metering. Seller shall cause the Facility to implement all necessary generation information communications in WREGIS, and report generation information to WREGIS pursuant to a WREGIS-approved meter that is dedicated to the Facility and only the Facility.
WREGIS Metering. If Utility owns Environmental Attributes pursuant to Section 4.6, Seller must cause the Facility to implement all necessary generation information communications in WREGIS, and report generation information to WREGIS pursuant to a WREGIS-approved meter dedicated to the Facility and only the Facility.
WREGIS Metering. PacifiCorp shall have the right upon notice to Seller to perform the Qualified Reporting Entity (as defined by WREGIS) functions for the Project to implement all necessary generation information communications in WREGIS, and report generation information to WREGIS pursuant to a WREGIS-approved meter that is dedicated to the Project and only the Project.
WREGIS Metering. If PacifiCorp owns the Environmental Attributes pursuant to Section 4.7, Seller must cause the Facility to implement all necessary generation information communications in WREGIS, and report generation information to WREGIS pursuant to a WREGIS-approved meter dedicated to the Facility and only the Facility.‌
WREGIS Metering. Seller will cause the Facility to implement all necessary generation information communications in WREGIS, and report generation information to WREGIS pursuant to a WREGIS-approved metering configuration, which metering configuration may reflect the operations of and meter data associated with the Generating Facility. PacifiCorp authorizes Seller to provide to WREGIS meter data with respect to Charging Energy, Grid Charging Energy and Discharging Energy and Generating Facility Metering Transformation Loss, all of which meter data will constitute Confidential Business Information and otherwise be subject to the requirements of Section 23.‌
WREGIS Metering. Seller will cause the Storage Facility to implement all necessary generation information communications in WREGIS, and report generation information to WREGIS pursuant to a WREGIS-approved metering configuration, which metering configuration may reflect the operations of and meter data associated with the Storage Facility. PacifiCorp authorizes Seller to provide to WREGIS meter data with respect to Charging Energy and Discharging Energy, which meter data will constitute Confidential Business Information and otherwise be subject to the requirements of Section 23.
WREGIS Metering. If the Seller desires PacifiCorp to be the WREGIS reporting entity for the Facility then Seller shall cause the Facility to implement all necessary generation information communications in WREGIS, and report generation information to WREGIS pursuant to a WREGIS-approved meter that is dedicated to the Facility and only the Facility.
WREGIS Metering. If Utility owns Environmental Attributes pursuant to Section 4.6, Seller must cause the Facility to implement all necessary generation information communications in WREGIS, and report generation information to WREGIS pursuant to a WREGIS-approved meter dedicated to the Facility and only the Facility. 31 SECTION 10 ▇▇▇▇▇▇▇▇, COMPUTATIONS AND PAYMENTS 31 10.1 Monthly Invoices. On or before the tenth (10th) day following the end of each calendar month, Seller must deliver to Utility an invoice showing Seller’s computation of Net Output delivered to the Point of Delivery during such month. When calculating the invoice, Seller must provide computations showing the portion of Net Output that was delivered during On-Peak Hours and the portion of Net Output that was delivered during Off-Peak Hours. If such invoice is delivered by Seller to Utility, then Utility must send to Seller, on or before the later of the twentieth (20th) day following receipt of such invoice or the thirtieth (30th) day following the end of each month, payment for Seller’s deliveries of Net Output to Utility. 31
WREGIS Metering. Seller shall cause the Renewable Energy Facility to implement all necessary generation information communications in WREGIS, and report generation information to WREGIS pursuant to a WREGIS-approved meter that is dedicated to the Renewable Energy Facility and only the Renewable Energy Facility.‌ SECTION 10‌

Related to WREGIS Metering

  • Metering The Interconnection Customer shall be responsible for the Connecting Transmission Owner’s reasonable and necessary cost for the purchase, installation, operation, maintenance, testing, repair, and replacement of metering and data acquisition equipment specified in Attachments 2 and 3 of this Agreement. The Interconnection Customer’s metering (and data acquisition, as required) equipment shall conform to applicable industry rules and Operating Requirements.

  • Revenue Metering The Connecting Transmission Owner’s revenue metering will be located on the generator side of the 115kV breaker at the ▇▇▇▇▇ Solar Collector Substation and will consist of: • three (3) combination current/voltage transformer (“CT/VT”) units (manufacturer and model ABB/▇▇▇▇▇▇▇ KXM-550, GE Grid Solutions KOTEF ▇▇▇.▇▇, or other equivalent specified by Connecting Transmission Owner); and • one (1) revenue meter. The ratios of the CTs and VTs will be provided by Connecting Transmission Owner upon its review of the Interconnection Customer’s design documents. (Note: Connecting Transmission Owner’s revenue metering CTs and VTs cannot be used to feed the Interconnection Customer’s check meter.) SERVICE AGREEMENT NO. 2556

  • One-Way Interconnection Trunks 2.3.1 Where the Parties use One-Way Interconnection Trunks for the delivery of traffic from Onvoy to Frontier, Onvoy, at ▇▇▇▇▇’s own expense, shall: 2.3.1.1 provide its own facilities for delivery of the traffic to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA; and/or 2.3.1.2 obtain transport for delivery of the traffic to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA (a) from a third party, or, (b) if Frontier offers such transport pursuant to a Frontier access Tariff, from Frontier. 2.3.2 For each Tandem or End Office One-Way Interconnection Trunk group for delivery of traffic from Onvoy to Frontier with a utilization level of less than sixty percent (60%) for final trunk groups and eighty-five percent (85%) for high usage trunk groups, unless the Parties agree otherwise, Onvoy will promptly submit ASRs to disconnect a sufficient number of Interconnection Trunks to attain a utilization level of approximately sixty percent (60%) for all final trunk groups and eighty-five percent (85%) for all high usage trunk groups. In the event Onvoy fails to submit an ASR to disconnect One-Way Interconnection Trunks as required by this Section, Frontier may disconnect the excess Interconnection Trunks or bill (and Onvoy shall pay) for the excess Interconnection Trunks at the rates set forth in the Pricing Attachment. 2.3.3 Where the Parties use One-Way Interconnection Trunks for the delivery of traffic from Frontier to Onvoy, Frontier, at Frontier’s own expense, shall provide its own facilities for delivery of the traffic to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA.

  • Two-Way Interconnection Trunks 2.4.1 Where the Parties use Two-Way Interconnection Trunks for the exchange of traffic between Frontier and Onvoy, Onvoy, at its own expense, shall: 2.4.1.1 provide its own facilities to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA; and/or 2.4.1.2 obtain transport to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA (a) from a third party, or, (b) if Frontier offers such transport pursuant to a Frontier access Tariff, from Frontier. 2.4.2 Where the Parties use Two-Way Interconnection Trunks for the exchange of traffic between Frontier and Onvoy, Frontier, at its own expense, shall provide its own facilities to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA. 2.4.3 Prior to establishing any Two-Way Interconnection Trunks, Onvoy shall meet with Frontier to conduct a joint planning meeting (“Joint Planning Meeting”). At that Joint Planning Meeting, each Party shall provide to the other Party originating Centum Call Seconds (Hundred Call Seconds) information, and the Parties shall mutually agree on the appropriate initial number of End Office and Tandem Two-Way Interconnection Trunks and the interface specifications at the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA at which the Parties interconnect for the exchange of traffic. Where the Parties have agreed to convert existing One-Way Interconnection Trunks to Two-Way Interconnection Trunks, at the Joint Planning Meeting, the Parties shall also mutually agree on the conversion process and project intervals for conversion of such One-Way Interconnection Trunks to Two-Way Interconnection Trunks. 2.4.4 On a semi-annual basis, Onvoy shall submit a good faith forecast to Frontier of the number of End Office and Tandem Two-Way Interconnection Trunks that Onvoy anticipates Frontier will need to provide during the ensuing two (2) year period for the exchange of traffic between Onvoy and Frontier. Onvoy’s trunk forecasts shall conform to the Frontier CLEC trunk forecasting guidelines as in effect at that time. 2.4.5 The Parties shall meet (telephonically or in person) from time to time, as needed, to review data on End Office and Tandem Two-Way Interconnection Trunks to determine the need for new trunk groups and to plan any necessary changes in the number of Two-Way Interconnection Trunks. 2.4.6 Two-Way Interconnection Trunks shall have SS7 Common Channel Signaling. The Parties agree to utilize B8ZS and Extended Super Frame (ESF) DS1 facilities, where available. 2.4.7 With respect to End Office Two-Way Interconnection Trunks, both Parties shall use an economic Centum Call Seconds (Hundred Call Seconds) equal to five (5). Either Party may disconnect End Office Two-Way Interconnection Trunks that, based on reasonable engineering criteria and capacity constraints, are not warranted by the actual traffic volume experienced. 2.4.8 Two-Way Interconnection Trunk groups that connect to a Frontier access Tandem shall be engineered using a design blocking objective of ▇▇▇▇- ▇▇▇▇▇▇▇▇▇ ▇.005 during the average time consistent busy hour. Two-Way Interconnection Trunk groups that connect to a Frontier local Tandem shall be engineered using a design blocking objective of ▇▇▇▇-▇▇▇▇▇▇▇▇▇ B.01 during the average time consistent busy hour. Frontier and Onvoy shall engineer Two-Way Interconnection Trunks using Telcordia Notes on the Networks SR 2275 (formerly known as BOC Notes on the LEC Networks SR-TSV-002275). 2.4.9 The performance standard for final Two-Way Interconnection Trunk groups shall be that no such Interconnection Trunk group will exceed its design blocking objective (B.005 or B.01, as applicable) for three (3) consecutive calendar traffic study months. 2.4.10 Onvoy shall determine and order the number of Two-Way Interconnection Trunks that are required to meet the applicable design blocking objective for all traffic carried on each Two-Way Interconnection Trunk group. Onvoy shall order Two-Way Interconnection Trunks by submitting ASRs to Frontier setting forth the number of Two-Way Interconnection Trunks to be installed and the requested installation dates within Frontier’s effective standard intervals or negotiated intervals, as appropriate. Onvoy shall complete ASRs in accordance with OBF Guidelines as in effect from time to time. 2.4.11 Frontier may (but shall not be obligated to) monitor Two-Way Interconnection Trunk groups using service results for the applicable design blocking objective. If Frontier observes blocking in excess of the applicable design objective on any Tandem Two-Way Interconnection Trunk group and Onvoy has not notified Frontier that it has corrected such blocking, Frontier may submit to Onvoy a Trunk Group Service Request directing Onvoy to remedy the blocking. Upon receipt of a Trunk Group Service Request, Onvoy will complete an ASR to establish or augment the End Office Two-Way Interconnection Trunk group(s), or, if mutually agreed, to augment the Tandem Two-Way Interconnection Trunk group with excessive blocking and submit the ASR to Frontier within five (5) Business Days. 2.4.12 The Parties will review all Tandem Two-Way Interconnection Trunk groups that reach a utilization level of seventy percent (70%), or greater, to determine whether those groups should be augmented. Onvoy will promptly augment all Tandem Two-Way Interconnection Trunk groups that reach a utilization level of eighty percent (80%) by submitting ASRs for additional trunks sufficient to attain a utilization level of approximately seventy percent (70%), unless the Parties agree that additional trunking is not required. For each Tandem Two- Way Interconnection Trunk group with a utilization level of less than sixty percent (60%), unless the Parties agree otherwise, Onvoy will promptly submit ASRs to disconnect a sufficient number of Interconnection Trunks to attain a utilization level of approximately sixty percent (60%) for each respective group, unless the Parties agree that the Two-Way Interconnection Trunks should not be disconnected. In the event Onvoy fails to submit an ASR for Two-Way Interconnection Trunks in conformance with this Section, Frontier may disconnect the excess Interconnection Trunks or bill (and Onvoy shall pay) for the excess Interconnection Trunks at the applicable Frontier rates. 2.4.13 Because Frontier will not be in control of when and how many Two-Way Interconnection Trunks are established between its network and Onvoy’s network, Frontier’s performance in connection with these Two-Way Interconnection Trunk groups shall not be subject to any performance measurements and remedies under this Agreement, and, except as otherwise required by Applicable Law, under any FCC or Commission approved carrier- to-carrier performance assurance guidelines or plan. 2.4.14 Onvoy will route its traffic, or traffic belonging to its Interconnected VoIP Provider Customers, to Frontier over the End Office and Tandem Two-Way Interconnection Trunks in accordance with SR-TAP-000191, including but not limited to those standards requiring that a call from Onvoy to a Frontier End Office will first be routed to the End Office Interconnection Trunk group between Onvoy and the Frontier End Office.