Baseline Progress Schedule definition

Baseline Progress Schedule means the time-scaled, Critical Path network schedule, updated from time to time in accordance with the Contract and depicting the subordinate activities and their durations, sequences, and interrelationships that represent the Design- Builder’s Work plans; the Design-Builder’s Work Breakdown Structure (WBS) for designing, constructing, and completing the Project.
Baseline Progress Schedule means the time-scaled, schedule, including revisions thereto, which has been provided by the Concessionaire in accordance with the Project Documents and which MDTA’s Authorized Representative has acknowledged in writing conforms to the Lease and Concession Agreement requirements, and updates thereto accepted by MDTA’s Authorized Representative. The Baseline Progress Schedule represents the Concessionaire’s plans for performing the Work and shows the Concessionaire’s Work Breakdown Structure (“WBS”) for designing, constructing, and completing the Project.
Baseline Progress Schedule means the time‐scaled, Critical Path network schedule, updated from time to time in accordance with the Contract and depicting the subordinate activities and their durations, sequences, and interrelationships that represent the Design‐Builder’s Work plans and the Design‐Builder’s Work Breakdown Structure WBS for designing, constructing, and completing the Project.

Examples of Baseline Progress Schedule in a sentence

  • Work shall not commence until the Contractor submits his Baseline Progress Schedule in accordance with the requirements of this section, unless otherwise approved in writing by the Engineer.

  • Contractor shall within twenty (20) days after the date of contract execution, prepare and submit to the County and Engineer for review and approval, a detailed and feasible Critical Path Method (CPM) Construction Schedule showing the method by which the Contractor will comply with Contract Milestones and Completion date requirements as set forth in the County-Contractor Agreement called the Baseline Progress Schedule.

  • Contractor shall within twenty (20) days after the date of contract execution, prepare and submit to the Owner and Engineer for review and approval, a detailed and feasible Critical Path Method (CPM) Construction Schedule showing the method by which the Contractor will comply with Contract Milestones and Completion date requirements as set forth in the Owner-Contractor Agreement called the Baseline Progress Schedule.

  • Contractor shall within thirty (30) days after the date of contract execution, prepare and submit to the Owner and Engineer for review and approval, a detailed and feasible Critical Path Method (CPM) Construction Schedule showing the method by which the Contractor will comply with Contract Milestones and Completion date requirements as set forth in the Owner-Contractor Agreement called the Baseline Progress Schedule.

  • The ▇▇▇▇ Contractor’s Baseline Progress Schedule shall meet the following requirements: Baseline Progress Schedule Format The ▇▇▇▇ Contractor shall use the precedence diagramming methods.

  • The Baseline Progress Schedule must show the order in which the ▇▇▇▇ Contractor proposes to perform the Work, the date on which it will start the major items of Work (including, but not limited to, excavation, drainage, paving, structures, mobilization, soil erosion, and sediment control) and the critical features (including, procurement of materials, plant, and Equipment) and the contemplated dates for completing the same.

  • Baseline Progress Schedule Within 30 Calendar Days following the Contract Award, the ▇▇▇▇ Contractor shall prepare and submit a Baseline Progress Schedule for the entire Project to CPRA’s Project Manager for review and Approval.

  • CPRA’s Project Manager will review the Baseline Progress Schedule and then hold a discussion meeting with the ▇▇▇▇ Contractor.

  • Birth, adoption, or ▇▇▇▇▇▇ care placement and leave must occur on or after March 12, 2023.

  • The Project shall be planned and documented using the Baseline Progress Schedule, a conventional CPM schedule in the form of an activity on node diagram based on the principles defined by the 2004 issue of the Construction Planning & Scheduling Manual published by the Associated General Contractors of America (AGC).

Related to Baseline Progress Schedule

  • Progress Schedule means a schedule of the Work, in a form satisfactory to Owner, as further set forth in Section 3.02.

  • Work Progress Schedule means the continually updated time schedule prepared and monitored by Contractor that accurately indicates all necessary appropriate revisions as required by the conditions of the Work and the Project while maintaining a concise comparison to the Baseline Schedule.

  • Development Schedule shall have the meaning set forth in Section 1.1.

  • Milestone Schedule means Seller’s milestone schedule, the form of which is attached to this Agreement as Exhibit Q.

  • Project Schedule means a document that, with respect to each Phase of the Project, identifies, coordinates and integrates the anticipated design and construction schedules, the Contracting Authority’s and Owner's responsibilities, government authority reviews and other activities as are necessary for the timely completion of the Work.