First Component definition
Examples of First Component in a sentence
Within thirty (30) days of the Notice to Proceed for the First Component of the Project, the CM shall complete the labor/materials marketplace survey and provide the Owner’s Representatives with a written evaluation of the extent of available and suitable labor/materials and whether the CM anticipates that the extent of available and suitable labor/materials will impact the costs/time for completion of Project construction.
The CM shall submit its written recommended bidding/construction strategy to the Owner’s Representatives for their acceptance within thirty (30) days of the date of the Notice to Proceed for the First Component of the Project (“the Preliminary Bidding/Construction Strategy”).
No later than sixty (60) days of the Notice to Proceed for the First Component of the Project, the Bid Packages developed by the CM shall be submitted to the Owner’s Representatives for review and acceptance by the Owner.
The CM’s fee for the First Component shall be paid to the CM via monthly payments based on the fixed fee divided by the duration of services.
In addition, the First Component work shall include any activities necessary for coordination with the environmental/site mitigation work described in Article 4.8. The First Component work may commence immediately upon execution of this Agreement and the Owner’s issuance of the first written Notice to Proceed.
The prequalification process shall commence within thirty (30) days of Owner’s issuance of the Notice to Proceed on the First Component.
The CM shall submit written Constructability Review comments to the Owner's Representatives within thirty (30) days of the Notice to Proceed and throughout the different phases of design and milestones for the First Component of the Project Owner shall have the sole and exclusive discretion to accept some, all or none of the CM’s Constructability Review Comments.
The CM shall assist in the review and closeout of all environmental mitigation work completed as part of the First Component.
The CM shall submit the Value Engineering Recommendations to the Owner’s Representatives within thirty (30) days of the Notice to Proceed for the First Component of the Project.
The CM shall be entitled to a fixed, not to exceed fee of $393,093 for the First Component and Pre-Construction Services of the Basic Services.