Change Order Requests Clause Samples
A Change Order Requests clause defines the process by which parties can propose modifications to the original scope, schedule, or cost of a contract. Typically, this clause outlines the steps for submitting a formal request, the required documentation, and the approval process before any changes are implemented. Its core function is to provide a structured and transparent method for managing changes, thereby minimizing disputes and ensuring that all parties agree to adjustments before they take effect.
POPULAR SAMPLE Copied 1 times
Change Order Requests. All change order requests by the City shall be made in writing by the City’s project manager. Within [insert number] days following its receipt of a change order request, Contractor will submit to City a written cost estimate, which shall include any adjustments to the project price, the Project Schedule, and the Acceptance criteria. Additional services by Contractor made necessary by the City’s change order request shall be billed at Contractor’s then current consulting rates. City will notify Contractor in writing if it wishes to proceed with the change order within [insert number] days.
Change Order Requests. Any party to the construction process may request changes to the Work, compensation or applicable schedules after execution of this Contract, and without invalidating this Contract. Unless otherwise specified herein, the Professional shall prepare the change orders and construction change directives. All Change Order requests shall be in writing and approved prior to the work which is the subject of the Change Order being completed, unless otherwise stated herein.
9.1.1 With respect to such requests for changes by the General Contractor, the General Contractor shall prepare and submit written change order requests to the designated Professional and Owner.
9.1.2 With respect to requests for changes by parties other than the General Contractor, the General Contractor shall promptly review and respond in writing to change order requests submitted by a Professional.
9.1.3 When requested to do so, the General Contractor shall prepare and submit to a Professional drawings, specifications or other data in support of a change order request.
9.1.4 Each change order shall include time and monetary impacts of the change, whether the change order is considered alone or with all other changes during the course of the Project.
Change Order Requests. If the Borrower requests additional improvements, changes in the Plans and Specifications must be submitted to Lender on the Change Order Request Form (Form 1200) or a similar form acceptable to Lender. Work on the requested changes shall not begin until Lender has approved such changes in writing and Borrower has deposited in the Rehabilitation Escrow Account additional funds in an amount sufficient to pay the cost of the approved changes, including a contingency reserve.
Change Order Requests. Any party to the construction process may request changes to the Work, compensation or applicable schedules.
9.1.1 With respect to such requests for changes by the CM, the CM shall prepare and submit change order requests to the Design Professional.
9.1.2 With respect to requests for changes by parties other than the CM, the CM shall promptly review and respond to change order requests submitted by the Design Professional.
9.1.3 When requested to do so, the CM shall prepare and submit to the Design Professional drawings, specifications or other data in support of a change order request.
9.1.4 Each change order shall include time and monetary impacts of the change, whether the change order is considered alone or with all other changes during the course of the Project.
Change Order Requests. Any party to the construction process may request changes to the Work, compensation or applicable schedules.
9.1.1 With respect to such requests for changes by the Builder, the Builder shall prepare and submit change order requests to the designated Professional.
9.1.2 With respect to requests for changes by parties other than the Builder, the Builder shall promptly review and respond to change order requests submitted by a Professional.
9.1.3 When requested to do so, the Builder shall prepare and submit to a Professional drawings, specifications or other data in support of a change order request.
9.1.4 Each change order shall include time and monetary impacts of the change, whether the change order is considered alone or with all other changes during the course of the Project.
Change Order Requests. Any party to the construction process may request changes to the Work, compensation or applicable schedules.
9.1.1 With respect to such requests for changes by the DB, the DB shall prepare and submit change order requests to the Owner.
9.1.2 With respect to requests for changes by parties other than the DB, the DB shall promptly review and respond to change order requests submitted by the Owner.
9.1.3 When requested to do so, the DB shall prepare and submit to the Owner drawings, specifications or other data in support of a change order request.
9.1.4 Each change order shall include time and monetary impacts of the change, whether the change order is considered alone or with all other changes during the course of the Project.
Change Order Requests. The Province may request a change to the Services (a “Change”) that are outside the scope of Ordinary Course Changes by delivering a written notice (the “Change Request”) to Supplier specifying the proposed change and the reason the Province is requesting the proposed change. Within ten Business Days after receipt of the Change Order Request (or such longer period of time requested by Supplier and agreed to by the Province, acting reasonably), Supplier will deliver to the Province a written response (the “Change Response”) that includes sufficient details to enable the Province to assess the anticipated impact of the change, including (a) a description of how and when the change would be implemented; (b) the effect of the Change on the Services and Service Levels; (c) an analysis of the risk (including privacy assessment if requested); (d) any increase or reduction in Fees (including any one time and ongoing Fees); (e) any other rights or obligations related to this Agreement that will be materially impacted (both positively and negatively); and (f) any other information reasonably requested by the Province. If the Province makes the Change Request on an emergency basis (including for privacy, confidentiality, security or legal compliance), Supplier will provide the Change Response as soon as possible and in any event no later than four Business Days after receipt. Supplier may request a Change by delivering to the Province a Change Request and a Change Response that contain the information required above. If a Change Request may result in an increase or decrease to the Fees, then the Parties will determine any increase or decrease to be made to the Fees in a manner consistent with the existing rates and margins under this Agreement.
Change Order Requests. Either SpeechWorks or AOL may initiate a Project Change Request ("PCR") as follows: a PCR may be requested for any reason, including without limitation, the following: a material modification, addition or deletion is required in the services or Deliverables; a material required task is not identified within one of the Specifications; a task identified in one of the Specifications has materially changed or is no longer required; AOL makes a material change to its operating environment; or material modifications are required to the project scope, schedule or implementation plan. All proposed PCRs shall be submitted in writing (including, without limitation, by email). Each proposed PCR will specify the nature of the proposed change requested, the reason for the proposed change, and any subsequent impact to schedules, Deliverables and cost. A PCR will not be implemented until all terms regarding such PCR are agreed upon in writing by SpeechWorks and AOL and executed by the authorized representatives of both parties.
Change Order Requests. No later than twenty (20) calendar days after CONSULTANT provides NOTICE of a request for a change order, CONSULTANT shall provide NOTICE to DISTRICT of the effect, if any, of the CHANGES on the payment, delivery timetable, and any right or obligation of the PARTIES under the AGREEMENT. As soon as reasonable after DISTRICT receives such NOTICE, DISTRICT and CONSULTANT shall meet and negotiate in good faith an equitable adjustment to the payment, delivery timetable, and any other rights and obligations of the PARTIES under the AGREEMENT.
Change Order Requests. Change Order Requests shall be submitted by the Contractor, using forms furnished by the provided by the District Representative or the Project Manager. The Change Order Request shall contain a coherent description of the circumstances justifying a change to the Contract. If the Change Order Request is based on a drawing or specification error, the Contractor shall identify the drawing or specification with particularity. Change Order Requests shall be submitted within fourteen (14) days after: (a) Receipt from the Project Manager of a Notice of Change; or