Claims for Extension of Time Clause Samples

The "Claims for Extension of Time" clause defines the process by which a party, typically a contractor, can formally request additional time to complete contractual obligations due to delays beyond their control. This clause outlines the circumstances under which such claims are valid, such as unforeseen events, changes in project scope, or delays caused by the client, and usually requires the affected party to submit a written notice with supporting evidence within a specified timeframe. Its core practical function is to provide a fair mechanism for adjusting project timelines, thereby protecting parties from penalties or breach of contract when delays are justified and outside their responsibility.
POPULAR SAMPLE Copied 1 times
Claims for Extension of Time. A. The parties agree that no extension beyond any required date of completion, whether Substantial Completion or Final Completion, fixed by the terms of the Contract shall be effective unless granted in writing, and signed by the Owner’s Procurement Agent or his designee. All time requirements set forth herein shall be of the essence. It shall be a condition precedent to any claim for extension of time that the Contractor comply strictly with the following requirements: 1. Give Notice of delay in writing to the Owner’s Project Manager, and to the Procurement Agent within two (2) days of the occurrence which gives rise to the alleged delay, or within seven (7) days of the beginning of the delay if the resulting delay was not reasonably foreseeable at its commencement. Delays based on weather occurrences shall be submitted in accordance with, and are subject to the limitations of, Section 37, Weather Delays, of these Terms and Conditions. The Notice of claim for delay shall identify itself as a notice of claim, shall state the circumstances of the occurrence, shall state the justification for the delay and for the extension of time, and shall state the estimated duration of the delay and of the extension requested. In case of a continuing cause of delay, only one Notice shall be required so long as the delay asserted is continuous, but an additional Notice shall be given at least every fourteen (14) days providing a statement of what the Contractor has done to mitigate or overcome the cause of the delay, how long the delay is anticipated to continue, and the justification for such projection. Strict compliance with all of these submission requirements shall be a condition precedent to consideration of any claim for delay related to weather, but compliance of itself shall not establish the validity of any claim. 2. The Contractor shall submit to the Owner’s Project Manager, and to the Procurement Agent a statement of the actual time extension requested as a result of the claimed delay, which shall include all documentation and supporting information for such claimed delay required by this Section and by any applicable Contract Specifications, within twenty-one (21) days after the delay has ceased. 3. The Contractor shall comply with all directions and decisions of the Owner’s Project Manager or the Procurement Agent and shall proceed diligently with the performance of the Contract and with any disputed work pending final resolution of any claim or dispute. “F...
Claims for Extension of Time. Notwithstanding the provisions of Section 12.05 and 12.06 above, none of the causes of delay described therein shall be deemed a valid excuse for Contractor's failure to start, perform, or complete the work, or any portion thereof, on time unless Contractor has notified the Project Manager, in writing, of the alleged cause of delay within ten
Claims for Extension of Time. The Developer may only claim an extension of time to the Project Proceed Date, the Date for Substantial Commencement and the Date for Practical Completion if the Developer is or is likely to be delayed in achieving a Major Milestone as a result of one of the following: (a) Force Majeure occurs; (b) an act or omission of WSPT resulting in a breach of this deed by WSPT, or because of the negligent act or omission of WSPT; (c) a delay in WSPT giving access to the Premises in accordance with clause 3.1(c) or clause 21.3 ("Terms of Developer access to the Premises"); (d) the Developer suspending or ceasing to perform the Works (in compliance with the provisions of this deed) by reason of a Native Title Application or Threatened Species Claim; (e) delays due to the discovery of Relics; (f) a delay to the Developer effecting the Satisfactory Project Proceed Arrangements by the Project Proceed Date due to a failure by WSPT to procure vacant possession of that part of the land occupied by the Lessees of the Agistment Leases; (g) subject to clause 11.2 ("Mitigation"), a delay to WSPT procuring vacant possession of any part of the Land; (h) a Discriminatory Law comes into effect, a delay in the Developer obtaining the Project Approval by the date specified in the Development Program, so long as the Developer has used all reasonable endeavours to submit the Project Application to the Consent Authority by the date specified in the Development Program; (i) the presence in or on the Land of Contamination that was not referred to or contemplated in the Environmental Investigation Report; (j) the time taken to resolve in accordance with clause 32 ("Dispute Resolution") any dispute regarding the Environmental Guidelines under clause 13.2 ("Environmental Guidelines"); and (k) the Independent Certifier unreasonably withholds or delays the granting of a Certificate of Practical Completion.

Related to Claims for Extension of Time

  • Requests for Extension The Borrower may, by notice to the Administrative Agent (who shall promptly notify the Lenders) not earlier than 90 days and not later than 35 days prior to an anniversary of the Closing Date (each, an “Applicable Anniversary Date”), request that each Lender extend such Lender’s Maturity Date for an additional year from the Maturity Date then in effect for such Lender hereunder (such Lender’s “Existing Maturity Date”). The Borrower may request such an extension no more than two times.

  • Request for Extension Upon request, the Department may extend the time allowed for both a response to the Letter of Concern and a Corrective Action Plan depending upon the nature of the deficiency. The Provider shall request an extension of time in writing from the Department’s designated representative. The written request shall contain a justification and proposed extension period.

  • Contract Negotiation Meetings When operational requirements permit, the Employer will grant leave without pay to an employee for the purpose of attending contract negotiation meetings on behalf of the Alliance. Preparatory Contract Negotiation Meetings

  • Certification of Meeting or Exceeding Tobacco-Free Workplace Policy Minimum Standards A. Grantee certifies that it has adopted and enforces a Tobacco-Free Workplace Policy that meets or exceeds all of the following minimum standards of: i. Prohibiting the use of all forms of tobacco products, including but not limited to cigarettes, cigars, pipes, water pipes (hookah), bidis, kreteks, electronic cigarettes, smokeless tobacco, snuff and chewing tobacco; ii. Designating the property to which this Policy applies as a "designated area,” which must at least comprise all buildings and structures where activities funded under this Grant Agreement are taking place, as well as Grantee owned, leased, or controlled sidewalks, parking lots, walkways, and attached parking structures immediately adjacent to this designated area; iii. Applying to all employees and visitors in this designated area; and iv. Providing for or referring its employees to tobacco use cessation services. B. If Grantee cannot meet these minimum standards, it must obtain a waiver from the System Agency.

  • Procedures for Exercise The manner of exercising the Stock Option herein granted shall be by written notice to the Secretary of the Company at the time the Stock Option, or part thereof, is to be exercised, and in any event prior to the expiration of the Stock Option. Such notice shall state the election to exercise the Stock Option, the number of shares of Stock to be purchased upon exercise, the form of payment to be used, and shall be signed by the person so exercising the Stock Option.