Construction Timelines Sample Clauses

Construction Timelines. (a) The Concessionaire shall comply with the DPR, the Construction Plan, the Designs and Drawings and the Technical Specifications and complete the construction of the Project Facilities so as to ensure that the WtC Facility achieves COD on or before the Scheduled COD. (b) Subject to Clause 14.7(c) below, the Concessionaire shall be entitled to a day-for-day extension of [the relevant Scheduled Project Milestone Completion Date or, as the case may be,]50 the Scheduled COD, if the completion of construction, Trial Operations, and testing of the Project Facilities is delayed due to any of the following reasons (each such event, a Delay Event): (i) occurrence of a Force Majeure Event, provided that the requirements of Article 26 have been complied with; (ii) a Change in Law; (iii) undue delay by the relevant Government Authority in granting or renewing any Applicable Permit, despite the Concessionaire having applied for such grant or renewal expeditiously and having complied with the requirements of Applicable Laws in making such application; (iv) undue delay by the relevant Government Authority in providing any utility connection, despite the Concessionaire having applied for such utility connection expeditiously and having complied with the requirements of Applicable Laws in making such application; (v) any delay attributable to unforeseen site conditions in accordance with Clause 10.4; (vi) delay by the Authority in approving the EMP and OHS Plan in accordance with Clause 14.4; (vii) delay by the Authority in approving the O&M Plan in accordance with Clause 18.2; (viii) delay by the Authority in approving the Waste Acceptance, Segregation and Rejection
Construction Timelines. The SRC Producer will have 18 months to bring the PV System to commercial operation. If the PV System has not achieved this status within 18 months, the deposit associated with the PV System will be forfeited to the Renewable Energy Standard Account. If, after 24 months the PV System has not been brought to commercial operation, the SRC Producer will be fined at a rate of $1,000 per day beginning with the first day of the 25th month and continuing until the final day of the 30th month. Any fines accrued during this time period must be paid in advance of the setting of any meter by Public Service. If, the PV System has not been brought into commercial operation after 30 months, Public Service will consider the PV System incomplete and remove it from the program with any associated capacity forfeited and any outstanding fines or other costs due immediately to Public Service from the SRC Producer.
Construction Timelines. The SRC Producer will have 30 months to bring the PV System to Substantial Completion from the date of notice that the SRC Bid was a winning bid (the “Target Completion Date”). If the PV System has not achieved Substantial Completion by the Target Completion Date, the Deposit will be forfeited to the Renewable Energy Standard Adjustment account in an amount equal to 1/180th of the Deposit per day for each day following the Target Completion Date that the PV System has not been brought to Substantial Completion, not to exceed the Deposit. If the PV System has not been brought to Substantial Completion after 36 months, Public Service will consider the PV System incomplete and have the right to remove it from the Solar*Rewards Community program with any associated capacity forfeited and terminate this Agreement which will be effective upon written notice to SRC Producer of such termination.
Construction Timelines a. The Concessionaire shall comply with the Construction Plan, the Designs and Drawings and the Technical Specifications and complete the construction/renovation for (i) Tolly Nallah STP 1 by Scheduled Tolly Nallah STP 1 Construction Completion Date; (ii) Tolly Nallah STP 2 by Scheduled Tolly Nallah STP 2 Construction Completion Date; (iii) Tolly Nallah STP 3 by Scheduled Tolly Nallah STP 3 Construction Completion Date; (iv) Existing Tolly Nallah Infrastructure 1 by Scheduled Existing Tolly Nallah Infrastructure 1 Construction Completion Date; (v) Existing Tolly Nallah Infrastructure 2 by Scheduled Existing Tolly Nallah Infrastructure 2 Construction Completion Date; and (vi) Garden Reach STP by Scheduled Garden Reach Construction Completion Date. b. Subject to Article 7.11(c) below, the Concessionaire shall be entitled to a day-for-day extension of the relevant Scheduled Payment Milestone Completion Date or the relevant Scheduled Tolly Nallah Construction Completion Date or Scheduled Garden Reach Construction Completion Date, as the case may be, if the completion of construction/renovation of any location‟s facilities is delayed due to any of the following reasons (each such event, a Delay Event): i. occurrence of a Force Majeure Event, provided that the requirements of Article 14 have been complied with;
Construction Timelines. (a) The Concessionaire shall comply with the DPR, the Construction Plan, the Designs and Drawings and the Technical Specifications and complete the construction of the Project Facilities so as to ensure that the MRF achieves COD on or before the Scheduled COD. (b) Subject to Clause 14.7(c) below, the Concessionaire shall be entitled to a day-for-day extension of [the relevant Scheduled Project Milestone Completion Date or, as the case may be,]54 the Scheduled COD, if the completion of construction, Trial Operations, and testing of the Project Facilities is delayed due to any of the following reasons (each such event, a Delay Event): (i) occurrence of a Force Majeure Event, provided that the requirements of Article 26 have been complied with; (ii) a Change in Law; (iii) undue delay by the relevant Government Authority in granting or renewing any Applicable Permit, despite the Concessionaire having applied for such grant or renewal expeditiously and having complied with the requirements of Applicable Laws in making such application;
Construction Timelines. Provided that all conditions precedent under this Agreement have been satisfied, construction of the Project shall commence on or before February 28, 2025 (“Commencement Date”), and shall be completed no later than August 31, 2026 (“Completion Date”); and further provided that if the Oklahoma Housing Finance Agency (“OHFA”) does not approve either or both of the Funding Period One applications submitted by or on behalf of Developer, but subsequently approves application(s) for OFHA’s Funding Period Two 2024 Tax Credit Allocation, the Commencement Date will be extended to June 1, 2025 and the Completion Date will be extended to October 31, 2026.
Construction Timelines. In regard to the timelines for construction of the various components of the Project, the first two sentences of Section 2(C)(i), and the entirety of Sections 2(C)(ii), (iii), and (iv) of the Agreement are hereby deleted and replaced with the following:
Construction Timelines. (a) The SRC Producer will have 18 months to bring the PV System to Substantial Completion from the date Interconnection Agreement and payment (the “Target Completion Date”). If the PV System has not achieved Substantial Completion by the Target Completion Date, the Deposit will be forfeited to the Renewable Energy Standard Adjustment account in an amount equal to 1/180th of the Deposit per day for each day following the Target Completion Date that the PV System has not been brought to Substantial Completion, with forfeiture not to exceed the Deposit amount. If the PV System has not been brought to Substantial Completion after 24 months (following the exhaustion of the 6-month extension period), Public Service will consider the PV System incomplete and have the right to remove it from the Solar*Rewards Community program with any associated capacity forfeited and terminate this Agreement which will be effective upon written notice to SRC Producer of such termination. Extensions will also be granted to SRC Producers with an extension length that corresponds to delays attributable to Public Service or substation upgrades (but not to the extent caused by SRC Producer’s mismanagement, negligence, or other breach of this Agreement); such extensions shall not require a forfeiture of deposit or otherwise toll the other extension eligibilities and policies described in this Section 5.1. (b) The SRC Producer may prevent termination of this Agreement under Section 5.1(a) by (1) providing Public Service notice its intent to achieve Substantial Completion beyond six months and no later than 12 months from the Target Completion Date; and (2) delivering a second Deposit to Public Service. Such notice and delivery of a second Deposit must be made no later than six months prior to the Target Completion Date. The second Deposit will be forfeited to the Renewable Energy Standard Adjustment account in an amount equal to 1/180th of the Deposit per day for each day following 24 months from the Target Completion Date that the PV System has not been brought to Substantial Completion, not to exceed the second Deposit.
Construction Timelines 

Related to Construction Timelines

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • Construction Work The regulation at 41 C.F.R. § 60-1.3 defines “construction work” as the construction, rehabilitation, alteration, conversion, extension, demolition or repair of buildings, highways, or other changes or improvements to real property, including facilities providing utility services. The term also includes the supervision, inspection, and other onsite functions incidental to the actual construction.

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Construction Completion The related Construction shall have been completed substantially in accordance with the related Plans and Specifications, the related Deed and all Applicable Laws, and such Leased Property shall be ready for occupancy and operation. All fixtures, equipment and other property contemplated under the Plans and Specifications to be incorporated into or installed in such Leased Property shall have been substantially incorporated or installed, free and clear of all Liens except for Permitted Liens.

  • Construction Plans Tenant shall prepare final plans and specifications for the Tenant Improvements that (a) are consistent with and are logical evolutions of the Approved Schematic Plans and (b) incorporate any other Tenant-requested (and Landlord-approved) Changes (as defined below). As soon as such final plans and specifications ("Construction Plans") are completed, Tenant shall deliver the same to Landlord for Landlord's approval, which approval shall not be unreasonably withheld, conditioned or delayed. All such Construction Plans shall be submitted by Tenant to Landlord in electronic .pdf, CADD and full-size hard copy formats, and shall be approved or disapproved by Landlord within ten (10) business days after delivery to Landlord. Landlord's failure to respond within such ten (10) business day period shall be deemed approval by Landlord. If the Construction Plans are disapproved by Landlord, then Landlord shall notify Tenant in writing of its objections to such Construction Plans, and the parties shall confer and negotiate in good faith to reach agreement on the Construction Plans. Promptly after the Construction Plans are approved by Landlord and Tenant, two (2) copies of such Construction Plans shall be initialed and dated by Landlord and Tenant, and Tenant shall promptly submit such Construction Plans to all appropriate Governmental Authorities for approval. The Construction Plans so approved, and all change orders approved (to the extent required) by Landlord, are referred to herein as the "Approved Plans."