Design Modifications Sample Clauses
The Design Modifications clause establishes the procedures and conditions under which changes to the original design may be made during a project. Typically, it outlines who has the authority to request or approve modifications, the process for documenting and communicating changes, and any requirements for adjusting costs or timelines as a result. This clause ensures that any alterations to the design are managed systematically, helping to prevent misunderstandings, scope creep, or disputes over project deliverables.
POPULAR SAMPLE Copied 3 times
Design Modifications. Clyvia reserves the right to carry out design modifications at any time; however, Clyvia is not obligated to carry out modifications of this type on products already delivered.
Design Modifications. EyeSys will have the right to make any design -------------------- modification to any of the Products at any time without incurring any obligation to make such modification to any of the Products previously sold; provided, however, that EyeSys will provide Nidek with sixty (60) days prior written notice of any such modifications that materially affect form, fit or function.
Design Modifications. 2.3.1 Address all non-conformance elements as directed by the Mobility Authority.
Design Modifications. Consultant shall prepare and submit engineering design revisions or additional design, as required or necessitated by unanticipated conditions encountered during construction. Consultant shall submit design revisions in the form of calculations, plans, specifications, and estimates as directed by the Project Manager. Consultant shall provide additional design services up to the level of effort included in the budget for this task, as directed. Additional services include utility coordination, illumination revisions, and pavement marking revisions. This task is limited to sixteen staff hours.
Design Modifications. If Consultant or City determines that design modifications may be necessary, Consultant shall discuss potential changes with City and POR prior to preparing the appropriate contract change order documents, depending upon the type of work (changed work, extra work, or force account work). Upon request of the APM, Consultant shall work with the POR to prepare detailed engineering design revisions necessitated by conditions encountered during construction. Up to ten (10) design modifications shall be prepared, limited to the budget and hours associated with this task.
Design Modifications. BUILDING C
(a) The south-western elevation is to be treated with vertical sun shading to reduce the impacts of the summer sun.
(b) Any full height screens to balconies required for wind mitigation must be amended to be partly open at the top in accordance with Section 4.2.3.13 of the SDCP 2012.
Design Modifications. 8.1. AUTONEUM retains the right to make modifications to drawings, specifications, and product descriptions etc. at any time.
8.2. The SUPPLIER will endeavor to ensure that no additional costs arise in the event of design modifications. If additional costs nevertheless arise, the SUPPLIER will immedi- ately inform AUTONEUM of this and of the probable amount involved. If AUTONEUM nevertheless insists upon the design modification, the PARTIES will agree upon an ap- propriate adjustment of the purchase price and if necessary on an extension of the de- livery periods. If the PARTIES are able to agree on the new terms and conditions, any ORDER already placed must be replaced by a new ORDER. If no agreement can be reached, AUTONEUM is entitled to cancel its relevant ORDERS.
Design Modifications. WASTE
(a) Allocated space and doors to be marked on plans for the designated ‘Commercial waste storage area”.
(b) Proposed doors to be marked up on residential ‘Bulky/organic waste room’. Doors should provide easy access for residents.
(c) A clear path of access should be provided to the lifts on the mezzanine waste level and any protruding obstacles to be deleted.
(d) A return and earn vending machine in accordance with the EPA design Guide for Container Recycling Equipment and Facilities must be incorporated within the basement level 1 or below ground supermarket lobby. Amended plans showing the location of the return and earn machine must be submitted to and approved by Council’s Area Planning Manager, prior to the issue of any Construction Certificate.
Design Modifications. ID reserves design and form modifications until delivery. This also applies to the Licensed Material.
Design Modifications. If Consultant or City determines that design modifications may be necessary, Consultant shall discuss potential changes with City and POR prior to preparing the appropriate contract change order documents, depending upon the type of work (changed work, extra work, or force account work). Upon request of the APM, Consultant shall work with the POR to prepare detailed engineering design revisions necessitated by conditions encountered during construction. Up to five (5) design modifications shall be prepared, limited to the budget and hours associated with this task for the ▇▇▇▇▇▇▇ Ave and 14th St roundabout project Up to ten (10) design modifications shall be prepared, limited to the budget and hours associated with this task for the 14th St: ▇▇▇▇▇▇▇ Ave to Commerce Ave project.