Distribution Piping System Sample Clauses

The Distribution Piping System clause defines the requirements and standards for the network of pipes used to transport fluids, such as water, gas, or steam, within a facility or project. It typically outlines specifications for materials, installation methods, testing procedures, and safety measures that must be followed during construction or maintenance. By establishing clear guidelines, this clause ensures the safe, efficient, and reliable delivery of fluids throughout the system, minimizing risks of leaks, failures, or non-compliance with regulatory standards.
Distribution Piping System. The DPS routing and sizing for the base case long term servicing plan is show in Drawing G05 in Appendix One. 4 FINANCIAL MODELLING GENERAL ASSUMPTIONS The project plan outlines the full build-out of the UBC NDES project, all relevant capital costs, operating costs, and other facts and assumptions for the full 30-year project term. There are a number of assumptions regarding future prices and rates that have a global bearing on the results of the financial model. Table 5 below shows the commodity price and other cost escalation rates used in the model. Base year 2014 Forecast CPI (for O&M) 2.0% Capital costs 2.0% Natural gas ▇▇▇▇▇▇▇ Electricity (2014 to 2023) Hydro Electricity (2024 onwards) 2.0% Heat purchased from ADES ▇▇▇▇▇▇▇ Waste heat from TRIUMF 0.0% Further information regarding the items in Table 5 above: • The base year for the model is 2014, although construction is not expected to commence until early 2015. The model also indicates a project year, with 2014 being year 0. No adjustment to the NPV calculations has been made for the short initial year because the costs incurred are proportionately small and no customer connections are made until the second quarter of 2015. • Operating costs (non-fuel) and capital costs have been escalated at 2% per annum as an estimate of inflation. A sensitivity comparison for +/– 1% on this amount has been prepared and is shown in Section 2.10.3. • The commodity cost of natural gas is assumed to escalate in proportion to the ▇▇▇▇▇▇▇ forecast for domestic natural gas at Huntington/Sumas. The commodity forecast used is as of June 30, 2014, and after two years of mild decline, followed by two years of increase moderately in excess of CPI, the forecast assumes 1.5% per annum escalation until 2024, which is the limit of the ▇▇▇▇▇▇▇ forecast. Thereafter, the financial model assumes that commodity cost of natural gas will escalate at 2% per annum, in line with the estimated CPI. Gas delivery and demand charges are assumed to escalate at CPI. • The cost of electricity is assumed to escalate according to BC Hydro’s most recent 10 year rate plan. The escalation factor used is moderately in excess of CPI until 2018, and thereafter is assumed to be 2% per annum, in line with the estimated CPI.
Distribution Piping System. Class C KWL has extensive experience with the design and installation of pre-insulated piping for hot water district energy systems in the Lower Mainland, particularly at UBC. The per-linear-meter cost factors for individual pipe diameters are based on actual installed costs of DPS in the Lower Mainland. The quantities and sizing of pipe in the cost estimate are based on the DPS layout shown in drawing G-002, which was developed using a WaterCAD model to optimize the pipe sizing and the pipe lengths were determined using GIS. DPS alignments and locations have not been finalized. General routing has been identified, however major utility conflicts have not been identified or included in the cost estimates. DPS service connection allowances are included for all building and energy centre connections. General conditions were estimated at 7% of capital cost, engineering at 15%, and a contingency of 20% of capital has been added.
Distribution Piping System. Thermal energy is delivered to customers with a closed loop four-pipe hot water distribution network. The same water is heated in the CEP, distributed to the buildings, transferred at the ETS and returned back to the CEP to be reheated and distributed again. No water is drained or lost in the system, and no additional water is required during normal operation.
Distribution Piping System. District heating piping to be prefabricated, pre-insulated steel piping system meeting EN253 or prefabricated, pre- insulated flexible piping system meeting EN15632. District cooling piping to be welded standard schedule steel with epoxy coating or HDPE, with no insulation. Piping shall meet system design temperature and pressure. District heating and cooling piping to be designed to ASME B31.1 Power Piping Code and meet piping manufacturer design and installation requirements. Energy transfer stations shall use a single brazed plate or plate and frame heat exchanger to isolate the district energy system from each building system, i.e. one for space heating, one for domestic hot water (DHW), and one for space cooling. DHW heat exchangers shall be double-wall gasketed plate and frame. Direct connection of district cooling system may be considered. Each energy transfer station shall include a commercial grade control system consisting of thermal energy metering systems meeting EN1434, two-way control valves to modulate flow through each heat exchanger, and temperature and pressure sensors. The control system will control the building supply temperature based on an agreed reset schedule. The central heating energy plant will employ sewer heat recovery as the base load energy source, consisting of heat pumps to provide the temperature lift and a sewage treatment and filtration system to meet heat pump requirements. Natural gas boilers will be used in series to the sewer heat recovery system to provide peaking and backup capability. The central heating plant will be sized to meet peak demand, with the sewer heat recovery system being sized to meet the base load, and natural gas boilers sized for full plant capacity with “N-1 redundancy” (i.e. can serve approximately 75% of peak demand with largest single production unit unavailable). The central cooling plant will employ chillers and cooling towers to serve the cooling load, with high efficiency chillers to serve the base load and standard efficiency chillers to provide peaking capability. The central cooling plant will be sized to meet the peak demand, with no redundancy or backup. Chilled water storage utilizing an existing tank on site may be employed. Regards, ▇▇▇▇▇ ▇▇▇▇▇, P.Eng. FVB Energy Inc. Page 33 of 35 Table of Contents 1 Document Purpose 3 2 Burnaby Mountain District Energy Utility 3 3 Responsibilities of the Customer and ▇▇▇▇▇ ▇ ▇ ▇▇▇▇▇▇▇▇▇▇▇▇ ▇▇▇ ▇▇▇▇▇▇▇▇ ▇▇▇▇ and DHW Systems 12 Definitions BAS Bu...

Related to Distribution Piping System

  • Distribution System The Transmission Owner’s facilities and equipment used to transmit electricity to ultimate usage points such as homes and industries directly from nearby generators or from interchanges with higher voltage transmission networks which transport bulk power over longer distances. The voltage levels at which Distribution Systems operate differ among areas. Distribution Upgrades – The additions, modifications, and upgrades to the Transmission Owner’s Distribution System at or beyond the Point of Interconnection to facilitate interconnection of the Small Generating Facility and render the transmission service necessary to effect the Interconnection Customer’s wholesale sale of electricity in interstate commerce.

  • Distribution Upgrades The Connecting Transmission Owner shall design, procure, construct, install, and own the Distribution Upgrades described in Attachment 6 of this Agreement. If the Connecting Transmission Owner and the Interconnection Customer agree, the Interconnection Customer may construct Distribution Upgrades. The actual cost of the Distribution Upgrades, including overheads, shall be directly assigned to the Interconnection Customer. The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with owning, operating, maintaining, repairing, and replacing the Distribution Upgrades, as set forth in Attachment 6 to this Agreement.

  • Distribution of UDP and TCP queries DNS probes will send UDP or TCP “DNS test” approximating the distribution of these queries.

  • Unbundled Sub-Loop Distribution Voice Grade (USLD-VG) is a copper sub- loop facility from the cross-box in the field up to and including the point of demarcation at the End User’s premises and may have load coils.

  • Distribution Services 3.1. Distributor will have the right, as agent for the Fund, to enter into dealer agreements with responsible investment dealers, and to sell Shares to such investment dealers against orders therefor at the public offering price (as defined below) stated in the Fund’s effective Registration Statement on Form N-2 under the 1940 Act and the Securities Act of 1933, as amended (the “Securities Act”), including the then-current prospectus and statement of additional information (the “Registration Statement”). Upon receipt of an order to purchase Shares from a dealer with whom Distributor has a dealer agreement, Distributor will promptly cause such order to be filled by the Fund. 3.2. Distributor will also have the right, as agent for the Fund, to sell such Shares to the public against orders therefor at the public offering price (as defined below) and in accordance with the Registration Statement. 3.3. Distributor will also have the right to take, as agent for the Fund, all actions which, in Distributor’s reasonable judgment, are necessary to carry into effect the distribution of the Shares. 3.4. The “public offering price” for the Shares of the Fund shall be the net asset value (“NAV”) of the Shares then in effect, plus any applicable sales charge determined in the manner set forth in the Registration Statement or as permitted by the 1940 Act and the rules and regulations promulgated by the SEC or other applicable regulatory agency or self-regulatory organization under the oversight of the SEC. In no event shall any applicable sales charge exceed the maximum sales charge permitted by the Rules of FINRA. 3.5. The NAV of the Shares of the Fund shall be determined in the manner provided in the Registration Statement, and when determined shall be applicable to transactions as provided for in the Registration Statement. The NAV of the Shares shall be calculated by the Fund or by another entity on behalf of the Fund. Distributor shall have no duty to inquire into or liability for the accuracy of the NAV per Share as calculated. 3.6. On every sale, the Fund shall receive the applicable NAV of the Shares promptly, but in no event later than the third business day following the date on which Distributor shall have received an order for the purchase of the Shares. 3.7. Upon receipt of purchase instructions, Distributor will transmit such instructions to the Fund or its transfer agent for the issuance and registration of the Shares purchased. 3.8. Distributor, as agent of and for the account of the Fund, may repurchase the Shares at such prices and upon such terms and conditions as shall be specified in the Registration Statement. 3.9. Distributor shall maintain membership with the National Securities Clearing Corporation (“NSCC”) and any other similar successor organization to sponsor a participant number for the Fund so as to enable the Shares to be traded through FundSERV. The Distributor shall not be responsible for any operational matters associated with FundSERV or networking transactions. 3.10. Distributor will review all proposed advertising materials and sales literature for compliance with Applicable Law and shall file such materials with appropriate regulators as required by current laws and regulations. Distributor agrees to furnish the Fund with any comments provided by regulators with respect to such materials. 3.11. Distributor shall prepare or cause to be prepared reports for the Board of Trustees (the “Board”) of the Fund regarding its activities under this Agreement as reasonably requested by the Board.