ENUMERATION OF THE CONTRACT DOCUMENTS Sample Clauses
The "Enumeration of the Contract Documents" clause defines and lists all the documents that collectively form the complete contract between the parties. This typically includes items such as the main agreement, general and special conditions, specifications, drawings, addenda, and any other referenced materials. By clearly identifying each document that is part of the contract, this clause ensures that there is no ambiguity about which documents are legally binding, thereby preventing disputes over missing or extraneous materials and ensuring all parties are aligned on the contract's scope and requirements.
POPULAR SAMPLE Copied 1 times
ENUMERATION OF THE CONTRACT DOCUMENTS. 2.01 The Contract Documents consisting of the Agreement Form, M/WBE Program Requirements, Documents contained in the Project Manual, General and Supplementary Conditions, Drawings, Specifications, and all Addenda and modifications issued after execution of the Contract thereto together form the Contract, and they are fully a part of the Contract as if written herein word for word. The following is an enumeration of the Drawings and Project Manual for this Project:
2.02 The Drawings:
ENUMERATION OF THE CONTRACT DOCUMENTS. 10.1 The Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated as follows:
10.1.1 This executed Agreement Between Owner and Contractor (i.e. the Agreement)
10.1.2 The General Conditions of the Contract for Construction Dated October 22, 2013
10.1.3 Other Documents, as follows:
ENUMERATION OF THE CONTRACT DOCUMENTS. 2.01 The Contract Documents consisting of the Agreement Form, M/WBE Program Requirements, Documents contained in the Project Manual, General and Supplementary Conditions, Drawings, Specifications, and all Addenda and modifications issued after execution of the Contract thereto together form the Contract, and they are fully a part of the Contract as if written herein word for word. The following is an enumeration of the Drawings and Project Manual for this Project:
2.02 The Drawings: SHEET NUMBER A0.0 SHEET NAME SITE PLAN CURRENT REV. DATE CURRENT REV. # BD1.6 B UILDING DEMOLITION “AS BUILT” DRAWINGS BD1.7 B UILDING DEMOLITION “AS BUILT” DRAWINGS BD1.8 B UILDING DEMOLITION “AS BUILT” DRAWINGS D1.1 OVERALL DEMOLITION KEY CEILING & PLAN D1.2 DEMOLITION FLOOR PLAN – ▇▇▇▇. ▇▇ D1.3 DEMOLITION FLOOR PLAN – ▇▇▇▇. ▇, ▇, ▇ ▇▇.▇ ▇▇▇▇▇▇▇▇▇▇ ▇▇▇▇▇ ▇▇▇▇ – ▇▇▇▇. ▇, 9 & 9 D2.0 DEMOLITION CEILING PLAN – ▇▇▇▇. ▇ & 16 A2.D1 DEMOLITION ROOF PLAN – BLDG. 2 A2.D2 DEMOLITION ROOF PLAN – BLDGS. 8 & 9 A2.D3 DEMOLITION ROOF PLAN – BLDGS. 1, 3, 4, 11 & 16 A2.D4 DEMOLITION ROOF PLAN – BLDGS. 5, 6, 7, 10, 12, 13, 14 & 15 A1.0 OVERALL KEY FLOOR PLAN A1.1 FLOOR PLANS – BLDGS. 2, 3 & 7 2-18-2019 1 A1.2 FLOOR PLAN – ▇▇▇▇. ▇ 2-18-2019 1 A1.3 FLOOR PLAN – ▇▇▇▇. ▇ 2-18-2019 1 A1.4 FLOOR PLAN – ▇▇▇▇. ▇ 2-18-2019 1 A1.5 FLOOR PLAN – ▇▇▇▇. ▇ 2-18-2019 1 A1.6 FLOOR PLAN – ▇▇▇▇. ▇ 2-18-2019 1 A1.7 FLOOR PLAN – ▇▇▇▇. ▇▇ 2-18-2019 1 A1.8 ENLARGED TLT. RM. FLOOR PLAN (BUILDING 16) 2-18-2019 1 A1.9 FLOOR PLAN – BUILDINGS 7 & 10 2-18-2019 1 LS1.3 L/S PLAN – ▇▇▇▇. ▇ 2-18-2019 1 LS1.4 L/S PLAN – ▇▇▇▇. ▇ 2-18-2019 1 LS1.5 L/S PLAN – ▇▇▇▇. ▇ 2-18-2019 1 LS1.6 L/S PLAN – ▇▇▇▇. ▇ 2-18-2019 1 LS1.7 L/S PLAN – ▇▇▇▇. ▇▇ 2-18-2019 1 LS1.9 L/S PLAN – ▇▇▇▇. ▇ & 10 2-18-2019 1 A2.0 OVERALL KEY ROOF PLAN 2-18-2019 1 A2.1 ROOF PLAN – BUILDINGS 1 & 16 2-18-2019 1 A2.2 ROOF PLAN – BUILDING 2 (PARTIAL) 3-21-2019 2 A2.3 ROOF PLAN – BUILDING 2 (PARTIAL) 3-21-2019 2 A2.4 ROOF PLAN – BUILDING 3, 12, 15, 17 & 18 2-18-2019 1 A2.5 ROOF PLAN – BUILDINGS 4 (PARTIAL) 2-18-2019 1 A2.6 ROOF PLAN – BUILDING 4 (PARTIAL) & 11 3-21-2019 2 A2.7 ROOF PLAN – BUILDING 5 2-18-2019 1 A2.8 ROOF PLAN – BUILDING 6 2-18-2019 1 A2.9 ROOF PLAN – BUILDINGS 7, 13 & 14 2-18-2019 1 A2.10 ROOF PLAN – BUILDING 8 2-18-2019 1 A2.11 ROOF PLAN – BUILDING 9 2-18-2019 1 A2.12 ROOF PLAN – BUILDING 10 2-18-2019 1 A2.13 NOT USED A2.14 NOT USED A2.15 NOT USED A2.16 ROOF DRAINAGE PLAN – BUILDING 2 2-18-2019 1 A2.17 ROOF DRAINAGE PLAN – BUILDINGS 8 &9 2-18-2019 1 ...
ENUMERATION OF THE CONTRACT DOCUMENTS. § 8.1 The Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated as follows:
§ 8.1.1 The Agreement is this executed edition of AIA Document A142-2004, Standard Form of Agreement Between Design- Builder and Contractor.
§ 8.1.2 The Supplementary and other Conditions of the Contract, if any, are as follows:
ENUMERATION OF THE CONTRACT DOCUMENTS. § 8.1 The Contract Documents, except for Modifications issued after the execution of this Agreement, are enumerated as follows:
§ 8.1.1 The Supplementary and other Conditions of the Contract, if any, are as follows:
§ 8.1.2 The Specifications are as follows: [Insert identification if existing as of time of execution]
§ 8.1.4 The Drawings are as follows: [Insert identification if existing as of time of execution]
§ 8.1.5 The Addenda, if any, are as follows:
§ 8.1.6 Exhibit A. Terms and Conditions
§ 8.1.7 Exhibit B. Process Equipment List
§ 8.1.8 Exhibit C. Designer-Builder’s Scope of Work.
§ 8.1.9 Exhibit D. Determination of the Cost of the Work (Schedule of Values)
§ 8.1.10 Exhibit E. Insurance, if applicable.
§ 8.1.11 Exhibit F. Project Master Schedule § 8.1.12 Exhibit G. Permits
ENUMERATION OF THE CONTRACT DOCUMENTS. The contract documents consist of each one of the following:
1. This agreement.
2. The ▇▇▇▇▇▇▇ Irrigation Proposal dated 10-29-23 and Cover Letter dated 10-28-23.
3. Plans provided by Aqua Turf International dated 9-20-22.
4. Wesco materials quote dated 12-1-23 and Pro Pump and Controls materials quote dated 11-28-23 reflecting the project materials to be purchased directly by the club. If there are any conflicts between any of the provisions of this Agreement and provisions contained in the other documents named above, this Agreement shall govern.
ENUMERATION OF THE CONTRACT DOCUMENTS. The Subcontract Documents, except for Modifications issued after execution of this Agreement, are enumerated as follows:
ENUMERATION OF THE CONTRACT DOCUMENTS. 2.01 The Contract Documents consisting of the Agreement Form, M/WBE Program Requirements, Documents contained in the Project Manual, General and Supplementary Conditions, Drawings, Specifications, and all Addenda and modifications issued after execution of the Contract thereto together form the Contract, and they are fully a part of the Contract as if written herein word for word. The following is an enumeration of the Drawings and Project Manual for this Project:
2.02 The Drawings: GN-000 COVER SHEET REV.5-pre-bid revision- Owner requested change 12.14.2021 GN-002 GENERAL NOTES REV.2-RESPONSE TO BCPS COMMENTS 05.10.2021 GN-003 ABBREVIATIONS AND SYMBOLS ORIGINAL DATE (Permit Submission) 01.24.2020 GN-004 FISH ROOM LIST ORIGINAL DATE (Permit Submission) 01.24.2020 GN-005 ROOF GENERAL NOTES REV.4- RESPONSE TO BCPS COMMENT 08.30.2021 SH-1 SURVEY ORIGINAL DATE (Permit Submission) 01.24.2020 C-1 WATER PLAN ORIGINAL DATE (Permit Submission) 01.24.2020 C-2 WATER DETAILS ORIGINAL DATE (Permit Submission) 01.24.2020 C-3 GENERAL NOTES AND SPECIFICATIONS ORIGINAL DATE (Permit Submission) 01.24.2020 S-000 STRUCTURAL NOTES ORIGINAL DATE (Permit Submission) 01.24.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇ ▇▇▇▇ PRESSURE DIAGRAM - A ORIGINAL DATE (Permit Submission) 01.24.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇ ▇▇▇▇ PRESSURE DIAGRAM - B ORIGINAL DATE (Permit Submission) 01.24.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇ ▇▇▇▇ PRESSURE DIAGRAM - C ORIGINAL DATE (Permit Submission) 01.24.2020 S-110-D BLDG #1 ROOF WIND PRESSURE DIAGRAM - D ORIGINAL DATE (Permit Submission) 01.24.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇▇ ▇▇▇▇ - ▇ ORIGINAL DATE (Permit Submission) 01.24.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇▇ ▇▇▇▇ - ▇ ORIGINAL DATE (Permit Submission) 01.24.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇ ▇▇▇▇ - A REV.1- RESPONSE TO BCPS COMMENT 05.06.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇ ▇▇▇▇ - ▇ REV.1- RESPONSE TO BCPS COMMENT 05.06.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇ ▇▇▇▇ - ▇ REV.1- RESPONSE TO BCPS COMMENT 05.06.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇ ▇▇▇▇ - ▇ REV.1- RESPONSE TO BCPS COMMENT 05.06.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇ ▇▇▇▇ PRESSURE DIAGRAM - A ORIGINAL DATE (Permit Submission) 01.24.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇ ▇▇▇▇ PRESSURE DIAGRAM - B ORIGINAL DATE (Permit Submission) 01.24.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇ ▇▇▇▇ PRESSURE DIAGRAM - C ORIGINAL DATE (Permit Submission) 01.24.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇▇ ▇▇▇▇ - ▇ ORIGINAL DATE (Permit Submission) 01.24.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇▇ ▇▇▇▇ - ▇ ORIGINAL DATE (Permit Submission) 01.24.2020 ▇-▇▇▇-▇ ▇▇▇▇ #▇ ▇▇▇▇ ▇▇▇▇ - A REV.1- RESPONSE TO BCPS COMMENT 05.06.2020 ▇-▇▇▇-▇ ▇▇▇▇ #...
ENUMERATION OF THE CONTRACT DOCUMENTS. 2.01 The Contract Documents consisting of the Agreement Form, M/WBE Program Requirements, Documents contained in the Project Manual, General and Supplementary Conditions, Drawings, Specifications, and all Addenda and modifications issued after execution of the Contract thereto together form the Contract, and they are fully a part of the Contract as if written herein word for word. The following is an enumeration of the Drawings and Project Manual for this Project:
2.02 The Drawings: Number Title No. Date G0.01 Cover Sheet 3 5-24-19 G0.02 General Info, Sheet index, & Code info 3 5-24-19 G0.03 Product Approval Sheet 3 5-24-19 A0.01 Architectural Site Plan 1 6-21-18 AD1.01A Partial First Floor Demo Plan Area “A” 3 5-24-19 AD1.01B Partial First Floor Demo Plan Area “B” 3 5-24-19 AD1.02 Overall Second Floor Demo Plan 3 5-24-19 AD1.03A Partial Roof Demo Plan Area “A” 3 5-24-19 AD1.03B Partial Roof Demo Plan Area “B” 3 5-24-19 AD1.04 Existing Roof Photos 1 6-21-18 AD1.05 Existing Roof Photos 1 6-21-18 AD1.06 Existing Roof Photos 1 6-21-18 A1.00 Overall Roof Plan & Drainage Calculations 1 6-21-18 A1.01A Partial First Floor Plan Area “A” 1 6-21-18 A1.01B Partial First Floor Plan Area “B” 1 6-21-18 A1.02 Overall Second Floor Plan 1 6-21-18 A1.03 Overall Roof Plan 3 5-24-19 A1.03A Partial Roof Plan Area “A” 3 5-24-19 A1.03B Partial Roof Plan Area “B” 3 5-24-19 A2.01 Elevations 1 6-21-18 A2.02 Existing Elevations 1 6-21-18 A3.01 Roof Details 3 5-24-19 A3.02 Roof Details 3 5-24-19 A7.01 Door Schedule 3 5-24-19 A7.02 Window Schedule 4 9-11-19 A7.03 Door Details 1 6-21-18 S1.01 S2.01 S2.02 S3.01 Wind Pressures Elevations – ▇▇▇▇▇. #▇, #▇, #▇ & #▇ ▇▇▇▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇ Elevations Typical Details M0.00 Legend and Abbreviations 1 3-30-18 M0.01 General Notes 1 3-30-18 M1.01 Site Plan Mechanical 1 3-30-18 MD1.01 Overall First Floor Plan Mechanical Demolition 1 3-30-18 MD1.01A1 Partial ▇▇▇▇▇ ▇▇▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇ Mechanical Demolition 1 3-30-18 MD1.01A2 Partial ▇▇▇▇▇ ▇▇▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇ Mechanical Demolition 1 3-30-18 MD1.01B1 Partial ▇▇▇▇▇ ▇▇▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇ Mechanical Demolition 1 3-30-18 MD1.01B2 Partial ▇▇▇▇▇ ▇▇▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇ Mechanical Demolition 1 3-30-18 M1.01 Overall First Floor Plan Mechanical 1 3-30-18 M1.01A1 Partial First Floor Plan Area A1 Mechanical 1 3-30-18 M1.01A2 Partial First Floor Plan Area A2 Mechanical 1 3-30-18 M1.01B1 Partial ▇▇▇▇▇ ▇▇▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇ Mechanical 1 3-30-18 M1.01B2 Partial ▇▇▇▇▇ ▇▇▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇ Mechanical 1 3-30-18 MD1.02 Overall Second Floor...
ENUMERATION OF THE CONTRACT DOCUMENTS. The Contract Documents, except for Modifications issued after execution of this Contract, are enumerated as follows:
(a) the Contract
(b) Supplementary or other Conditions of the Contract as follows: Job Special Provisions
(c) Construction Schedule
(d) State Wage Order (order number)
(e) The Addenda, if any, are as follows:
(f) Owner’s Invitation for Bids for the Festus Well #8 and Well #10 Pump Replacement and Refurbishment project
(g) Contractor’s Response
(h) Insurance Certificates
(i) E-verify Affidavit
(j) Non-Collusion Affidavit
(k) Performance and Payment Bond