Final Completion Deadline Sample Clauses

Final Completion Deadline. Design-Builder shall achieve Final Completion on or before November 1, 2025 (the “Final Completion Deadline”). The date the Project has achieved Final Completion is the “Final Completion Date.”
Final Completion Deadline. Contractor shall achieve Final ------------------------- Completion by the Guaranteed Final Completion Date. If Final Completion is not achieved by such date, in addition to any other remedies Owner may have hereunder Owner may complete the Punch List items and draw upon the Letter of Credit in accordance with the provisions of Section 4.5 hereof in an amount equal to Owner's actual reasonable direct cost of performing such work
Final Completion Deadline. The Specifications may set forth a “Final Completion Deadline” by which the Developed Software must be implemented by Supplier and operational in order to meet a strategic business objective or Third Party deadline applicable to Customer, and thereby avoid a significant adverse impact on the Customer Business. In such case, if Supplier fails to perform its obligations under the applicable Specifications and implement the Developed Software before the Completion Deadline, Customer may terminate the Development Project upon ten (10) Business Daysnotice to Supplier.
Final Completion Deadline. Final Completion Deadline" is defined in the Energy Provider Agreement.
Final Completion Deadline. Design-Builder shall achieve Final

Related to Final Completion Deadline

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.

  • Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.