Other Network Upgrades Sample Clauses

The "Other Network Upgrades" clause defines the responsibilities and procedures related to upgrades or enhancements to a network that are not otherwise specifically addressed in the main agreement. This clause typically outlines how such additional upgrades are identified, who is responsible for their costs, and the process for approval and implementation. For example, if a utility or service provider needs to make improvements to accommodate new users or technologies, this clause would govern those actions. Its core practical function is to ensure that any unforeseen or supplemental network improvements are managed transparently and fairly, preventing disputes over responsibility and cost allocation.
Other Network Upgrades. (i) Reliability Network Upgrades. None. (ii) Delivery Network Upgrades. None.
Other Network Upgrades. (i) Reliability Network Upgrades. None identified in the Phase II Interconnection Study. (ii) Delivery Network Upgrades.
Other Network Upgrades. Participating TO’s Reliability Network Upgrades. The Participating TO shall:
Other Network Upgrades. Interconnecting Transmission Owner’s Network Upgrades shall include an extended grounding mat and rewired and upgraded control and protection for the Interconnection Facilities, all at its Medway Station #65, and all at Interconnection Customer’s expense.
Other Network Upgrades. Description of Project Facility Owner Estimated Cost
Other Network Upgrades. ▇. ▇▇▇▇▇▇▇ Substation: four +/- 4 MVAR dynamic reactive sources; a dedicated 115/34.5 kV transformer for the dynamic reactive sources, including High-side and Low-side breakers (see Appendix A-1). ii. ▇▇▇▇▇ Hydro Substation: equipment needed to automate the high-voltage switching controls for both 18 MVAR shunt capacitor banks (see Appendix A-3). iii. ▇▇▇▇▇▇ Substation: an additional 5.4 MVAR of shunt capacitance (see Appendix A-4).
Other Network Upgrades. [insert Other Network Upgrades associated with the second terminal position if it is internal to New England Control Area, list all Network Upgrades for terminal locations external to New England Control Area as Affected System Upgrades].
Other Network Upgrades. (i) Participating TO’s Reliability Network Upgrades
Other Network Upgrades. (i) Participating TO’s Reliability Network Upgrades: The Participating TO shall install: A. Ivanpah Substation Plan of Service: Install the following equipment at a dedicated 220 kV double-breaker line position on a breaker-and-a-half configuration to terminate the Ivanpah- Stateline 220 kV Transmission Line as follows: (1) Two (2) 220 kV 3000 A, 50 kA circuit breakers. (2) Four (4) 220 kV 3000 A, 80 kA horizontal-mounted group-operated disconnect switches. (3) One (1) grounding switch attachment (for line grounding). (4) Eighteen (18) bus supports with associated steel pedestals.
Other Network Upgrades. Comment [ED1]: Estimates are needed for Appendix C, Exhibit 1 New protective relaying for the S-171 and S-171S lines is needed between the new 115 kV ring bus switchyard installed for the Interconnection Customer’s Generating Facility and the Interconnecting Transmission Owner’s Drumrock / Hartford Avenue Substations.