Performance Test Schedules Sample Clauses

Performance Test Schedules. Contractor shall start-up and commission the Facility in accordance with the procedures therefore adopted pursuant to Section 17.02. Subject to Contractor’s obligation to pay Delay Liquidated Damages to the extent set forth herein, Contractor shall have the period (the “Performance Testing Period”) through and including the ninetieth (90th) day following the Substantial Completion Guaranteed Date during which Contractor shall run, and, if necessary, re-run each of the Performance Tests necessary to demonstrate compliance with Performance Guarantees. Contractor shall agree with Owner on Performance Test schedules within such Performance Testing Period, such agreement not to be unreasonably withheld or delayed.
Performance Test Schedules. Seller shall give Notice to Purchaser and Independent Engineer at least five (5) Business Days prior to commencing a Performance Test, provided that re-performance of tests shall require only two (2) Business Days’ Notice. Seller shall keep Purchaser’s Representative and Independent Engineer continuously apprised of the schedule for all testing and changes in the schedule, as well as the commencement and performance of any tests. 35

Related to Performance Test Schedules

  • Performance Tests Contractor shall perform Performance Tests in accordance with Section 11.2 of the Agreement and Attachment S.

  • Performance Testing (a) All performance tests of the Project, including any Initial Performance Test required in Section 2 of Appendix VIII, will be performed in accordance with the test procedures set forth in Appendix VIII (“Performance Test”), including additional procedures and protocols related to Performance Testing as mutually agreed between Buyer and Seller (“Test Procedures”). Seller shall bear all costs and receive all revenues, if applicable, associated with all Performance Tests. (b) After the Initial Delivery Date and during the Delivery Term, Buyer will have the right to conduct a Performance Test (“Buyer Performance Test”) no more than once a calendar year to demonstrate whether the Project is capable of delivering the Distribution Services at the Contract Capacity. Within 30 calendar days following a Buyer Performance Test, Seller will have the right to retest the Project with a Performance Test (“Seller Retest”). For the avoidance of doubt, the results of any Seller Retest will supersede the results of the preceding Buyer Performance Test. (i) If a Buyer Performance Test or, if a corresponding Seller Retest has occurred, a Seller Retest demonstrates the Project is capable of delivering Distribution Services at or above ninety-nine percent (99%) of the Initial Contract Capacity, the Contract Capacity will remain the Initial Contract Capacity; (ii) If a Buyer Performance Test or, if a corresponding Seller Retest has occurred, a Seller Retest demonstrates the Project is capable of delivering Distribution Services at more than or equal to eighty-five (85%) of the Initial Contract Capacity, but less than ninety-nine percent (99%) of the Initial Contract Capacity (“Testing Band”), the Contract Capacity will be automatically adjusted (upwards or downwards) to the capacity commensurate with the amount of Distribution Services the Project delivered during the Performance Test within the Testing Band. (iii) If a Buyer Performance Test or, if a corresponding Seller Retest has occurred, a Seller Retest demonstrates the Project is not capable of delivering Distribution Services of at least eighty-five percent (85%) of the Initial Contract Capacity, an Event of Default shall occur in accordance with Section 7.1(a)(viii).

  • Performance Schedule The Parties will perform their respective responsibilities in accordance with the Performance Schedule. By executing this Agreement, Customer authorizes Motorola to proceed with contract performance.

  • Registry Performance Specifications Registry Performance Specifications for operation of the TLD will be as set forth in Specification 10 attached hereto (“Specification 10”). Registry Operator shall comply with such Performance Specifications and, for a period of at least one (1) year, shall keep technical and operational records sufficient to evidence compliance with such specifications for each calendar year during the Term.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.