Procedure for Relief and Compensation Sample Clauses
The "Procedure for Relief and Compensation" clause outlines the steps that must be followed when a party seeks remedy or financial compensation due to a breach or other specified event under the agreement. Typically, this clause details how a claim should be submitted, the required documentation or evidence, and the timeline for responding to or resolving such claims. By establishing a clear process, the clause ensures that both parties understand their rights and obligations in the event of a dispute, thereby reducing ambiguity and facilitating fair and efficient resolution of claims.
Procedure for Relief and Compensation. Subject to Section 12.2.4 (Late Provision of Notice or Information), any claim made by Developer pursuant to Section 12.2.1 must:
Procedure for Relief and Compensation. Developer shall not be entitled to any extension of time, compensation or relief from its obligations under this Agreement with respect to the relevant Compensation Event.
Procedure for Relief and Compensation then the Contractor shall not be entitled to any extension of time, compensation, or relief from its obligations under the Contract in respect of the period for which the information is delayed.
Procedure for Relief and Compensation. Subject to Clause 15.8 (Late Provision of Information) to obtain relief and/or claim compensation the Contractor must:-
15.6.1 as soon as practicable, and in any event within fifteen (15) Working Days after it became aware that the Compensation Event has caused or is likely to cause delay, breach of an obligation under this Contract and/or the Contractor to incur costs or lose revenue, give to the Authority a notice of its claim for an extension of time to the Relevant Date, payment of compensation and/or relief from its obligations under the Contract;
15.6.2 within ten (10) Working Days of receipt by the Authority of the notice referred to in Clause 15.6.1 above, give full details of the Compensation Event and the extension of time to the Relevant Date and/or any Estimated Change in Project Costs and/or loss of revenue claimed;
Procedure for Relief and Compensation give full details of the Compensation Event and the extension of time and/or relief from its obligations under this Contract and/or any Change in Costs claimed; and
Procedure for Relief and Compensation. Subject to Section 12.2(d) (Late Provision of Notice or Information), any claim made by the Development Entity pursuant to Section 12.2(a) must:
(i) be submitted to the Department as soon as practicable, and in any event within twenty
Procedure for Relief and Compensation. Subject to Section 12.2(d) (Late Provision of Notice or Information), any claim made by the Development Entity pursuant to Section 12.2(a) must:
(i) be submitted to the Department as soon as practicable, and in any event within twenty (20) Business Days of the Development Entity first becoming aware that the relevant Compensation Event would have the effect that is the subject of the Development Entity’s claim;
(ii) as soon as is reasonably practicable following receipt by the Department of the claim referred to in Section 12.2(b)(i), give full details of the relevant Compensation Event (as available to it having made due enquiry) and the extension of time and/or relief from its obligations under this PPA and/or any Change in Costs claimed or reasonably likely to be claimed, including:
(A) to the extent the Development Entity believes that the relevant Compensation Event would result in a delay to the achievement of CNG Readiness or Site Completion (as relevant) at the applicable Project Site, a Time Impact Analysis (based on the Project Working Schedule most recently agreed pursuant to Section 2 (Project Management Plan) of the Technical Provisions) demonstrating that the relevant Compensation Event will result in an identifiable and measurable disruption to CNG Readiness or Site Completion (as relevant), which will impact a Critical Path activity (i.e., would consume all available float and would extend the time required to achieve CNG Readiness or Site Completion (as relevant));
(B) evidence demonstrating that no other concurrent unrelated delay to a Critical Path activity that is the Development Entity’s responsibility has occurred that has contributed to the delay for which relief is being sought; and
(C) evidence demonstrating that such event could not reasonably be avoided by the Development Entity without material cost or delay, including by re-sequencing, reallocating or redeploying its forces to other Project Sites; and
(iii) provide evidence to the Department demonstrating that:
(A) the Compensation Event was the direct cause or is reasonably likely to be the direct cause of:
I. Change in Costs; and/or II. a delay in achieving CNG Readiness at the applicable Project Site by the applicable CNG Readiness Deadline or (following the applicable CNG Readiness Deadline) further delay in the achievement of CNG Readiness; and/or
Procedure for Relief and Compensation. Subject to clause 15.4 (Late Provision of Notice or Information), to obtain relief, extension and/or claim compensation, the Contractor must:
15.2.1 as soon as practicable, and in any event within twenty (20) Business Days, after it became aware that the Compensation Event has caused or is likely to cause delay, breach of an obligation under this Contract and/or the Contractor to incur costs, (or if earlier after it has received written notice from the Authority's Representative that a Compensation Event has occurred and that expressly requires the Contractor to claim relief, extension and/or compensation pursuant to this clause 15.2) give to the Authority a notice of its claim for:
15.2.1.1 an extension of time to (as appropriate):
(a) the Services Commencement Date;
(b) any date specified in a RRAPP Band Deactivation Notice for an increase in the number of Available Prisoner Places;
(c) any date specified in a RRAPP Band Activation Notice for the reduction in the number of Available Prisoner Places; and/or
(d) the period specified in paragraph (i) of the definition of Contractor Default; and/or
15.2.1. 2 payment of compensation; and/or
Procedure for Relief and Compensation. Subject to clause 16.8 (Late Provision of Information) below, to obtain relief, extension and/or claim compensation the Contractor must:
16.6.1 as soon as practicable, and in any event within fifteen (15) Business Days after it became aware that the Compensation Event has caused or is likely to cause delay, breach of an obligation under this Agreement and/or the Contractor to incur costs or lose revenue (including loss of Rents and/or Service Charges payable to the Landlord), give to the Authority a notice of its claim for an extension of time to the relevant Start on Site Date, Planned Services Commencement Date and/or the relevant Long Stop Date, payment of compensation and/or relief from its obligations under this Agreement;
16.6.2 within ten (10) Business Days of receipt by the Authority of the notice referred to in clause 16.6.1 (Procedure for Relief and Compensation), give full details of the Compensation Event and the extension of time and/or any Estimated Change in Project Costs and/or loss of revenue (including loss of Rents and/or Service Charges payable to the Landlord) claimed; and
16.6.3 demonstrate to the reasonable satisfaction of the Authority that:
(a) the Compensation Event was the direct cause of the Estimated Change in Project Costs and/or loss of revenue (including loss of Rents and/or Service Charges payable to the Landlord) and/or any delay in the achievement of the Start on Site Date or the Planned Services Commencement Date and/or breach of the Contractor's obligations under this Agreement; or following the Planned Services Commencement Date, delay in achieving Services Commencement before the relevant Long Stop Date; and
(b) the Estimated Change in Project Costs and/or loss of revenue (including loss of Rents and Service Charges payable to the Landlord), time lost and/or relief from the obligations under this Agreement claimed could not reasonably be expected to be mitigated or recovered by the Contractor acting in accordance with Good Industry Practice.
Procedure for Relief and Compensation give full details of the Compensation Event and the extension of time amendment to the relevant Milestone(s) and/or any Estimated Change in Project Costs and/or loss of revenue claimed; and