Relief for Differing Site Conditions Clause Samples

Relief for Differing Site Conditions. If the DBOM Contractor establishes that the actual conditions encountered during performance of the Design-Build Work meet the criteria for a Differing Site Condition in accordance with this Section and Article 19 (Uncontrollable Circumstances) and materially and directly impact the DBOM Contractor’s cost or time of performance, then the DBOM Contractor shall be entitled to Uncontrollable Circumstance relief as and to the extent provided in Article 19 (Uncontrollable Circumstances). Notwithstanding anything set forth in this Section or in Article 19 (Uncontrollable Circumstances), no Uncontrollable Circumstance relief shall be allowed for any alleged Differing Site Condition unless the DBOM Contractor provides the BWS with notice in accordance with this Section.
Relief for Differing Site Conditions. If the Project Company establishes that the actual conditions encountered during Project Implementation Work meet the criteria for a Differing Site Condition then the Project Company shall be entitled to Uncontrollable Circumstance relief as and to the extent provided in Section 14.1 (Uncontrollable Circumstances Generally).
Relief for Differing Site Conditions. If the Design-Builder establishes that the actual conditions encountered during Construction: (1) meet the criteria for a Differing Site Condition, and (2) directly and materially impact the Design-Builder’s cost or time of performance, then the Design-Builder shall be entitled to Uncontrollable Circumstance relief as and to the extent provided in Section 39.1.. The Design-Builder shall not be provided relief for any conditions of which it should have been aware.
Relief for Differing Site Conditions. If the actual conditions encountered during construction: (1) meet the criteria for a Differing Site Condition, and (2) meet the criteria for a Compensation Event, then the Developer shall be entitled to relief based on the occurrence of a Compensation Event as and to the extent provided in Article 15 (Compensation Events and Changes in Law).

Related to Relief for Differing Site Conditions

  • Differing Site Conditions ‌ 3.19.1 This provision is applicable if the Project involves digging trenches or other excavations that extend deeper than four (4) feet below the surface. Contractor shall promptly, and before the following conditions are disturbed, provide written notice to City if the Contractor finds any of the following conditions: .1 Material that Contractor believes may be a hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with the provisions of existing law. .2 Subsurface or latent physical conditions at the site differing from those indicated by information about the site made available to bidders prior to the deadline for submitting bids. .3 Unknown physical conditions at the site of any unusual nature, differing materially different from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents. .4 Except as otherwise provided in this Section 3.19, and as specified under law, including Public Contract Code Section 7104, Contractor is responsible for performing the Work subject to existing site conditions, without adjustment to the Contract Sum or Contract Time. 3.19.2 City shall promptly investigate any of the above the conditions and if City finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in Contractor’s cost of, or the time required for, performance of any part of the Work, shall issue a Change Order under the procedures described in the Contract Documents. The City may, acting in its sole discretion, extend the applicable deadline for submitting a Change Order Request when it is based upon differing conditions subject to Public Contract Code Section 7104. 3.19.3 In the event that a dispute arises between the City and the Contractor regarding any of the matters specified in subsection 3.19.1, above, Contractor shall not be excused from any scheduled completion date provided for in the Contract Documents, but shall proceed with all Work to be performed under the Contract. Contractor shall retain any and all rights provided either by the Contract or by law which pertain to the resolution of disputes between Contractor and City.

  • Site Conditions A. Existing Site Conditions: Information with respect to the site of the Work given in drawings or specifications has been obtained by County's representatives and is believed to be reasonably correct, but the County does not warrant either the completeness or accuracy of such information, and it is the responsibility of the Contractor to verify all such information.

  • Available Relief for a Force Majeure Event 11.7.1 Subject to this Article 11: (a) no Party shall be in breach of its obligations pursuant to this Agreement except to the extent that the performance of its obligations was prevented, hindered or delayed due to a Force Majeure Event; (b) every Party shall be entitled to claim relief in relation to a Force Majeure Event in regard to its obligations, including but not limited to those specified under Article 4.5; (c) For avoidance of doubt, neither Party’s obligation to make payments of money due and payable prior to occurrence of Force Majeure events under this Agreement shall be suspended or excused due to the occurrence of a Force Majeure Event in respect of such Party. (d) Provided that no payments shall be made by either Party affected by a Force Majeure Event for the period of such event on account of its inability to perform its obligations due to such Force Majeure Event.

  • SUSPENSIVE CONDITIONS 2.1 This entire AGREEMENT is subject to the registration of transfer of ownership of the PROPERTY to the EMPLOYER. In the event that the PROPERTY is not transferred within 6 (six) months from date of signing of this Agreement by the CONTRACTOR, the CONTRACTOR reserves the right to: 2.1.1 increase the CONTRACT SUM, based on the current prices for the building materials, and the CONTRACTOR shall notify the EMPLOYER in writing of such increased cost and the EMPLOYER may then, at his/her option, cancel this agreement by providing written notice of cancellation to the CONTRACTOR within 5 (five) DAYS of receiving written notice from the CONTRACTOR in respect of the increased cost. Should written notice of cancellation not be forthcoming within the aforesaid period, the CONTRACTOR and the EMPLOYER shall proceed with the AGREEMENT at the increased CONTRACT SUM and the EMPLOYER shall be obliged to pay the increase in the CONTRACT SUM to the CONTRACTOR within 21 (twenty one) DAYS of receiving written notice from the CONTRACTOR in respect of the increased cost; or 2.1.2 cancel this AGREEMENT and the parties shall have no claim of whatsoever nature against each other. 2.2 This AGREEMENT is subject further to the EMPLOYER being offered a loan to be secured by a mortgage bond over the PROPERTY and improvements in the amount reflected in Schedule B or such lesser amount as the EMPLOYER may accept, within 30 (thirty) DAYS of the date of the CONTRACTOR’s signature of this AGREEMENT, which period may be extended in the CONTRACTOR’s sole discretion. Should no amount be inserted in the relevant field in the Schedule B, then the suspensive condition contained in this clause will not apply. In the event that the suspensive condition contained in this clause is not fulfilled, this AGREEMENT will lapse and the parties shall have no claim of whatsoever nature against each other.

  • Additional Disruption Events Change in Law: Applicable; provided that Section 12.9(a)(ii) of the Equity Definitions is hereby amended by adding the words “(including, for the avoidance of doubt and without limitation, adoption or promulgation of new regulations authorized or mandated by existing statute)” after the word “regulation” in the second line thereof.