Scope Change Orders Clause Samples

Scope Change Orders. A “Scope Change” means a material addition to, deletion from, suspension of or other modification to, the quality, function or intent of the DB Project as delineated in the Scope Document, or a material change to the requirements of this Agreement, but shall not include refinement, correction or detailing of the DB Work by Concessionaire and Contractor from time to time. Concessionaire may order Scope Changes to the DB Work, in which event, as more specifically set forth in this Article 12, one or more of the Contract Sum, the Payment and Values Schedule, the Maximum Cumulative Drawdown Schedule, the Project Schedule, the Guaranteed Substantial Completion Date, the Guaranteed Final Acceptance Date, the Long Stop Date, the Scope Document and any other applicable terms and conditions of the Contract Documents shall be adjusted accordingly, if necessary, as agreed by Concessionaire and Contractor or determined pursuant to dispute resolution under Article 19; provided, that Contractor shall use reasonable efforts to mitigate the impacts of any Scope Change. If either Concessionaire or Contractor believes a Scope Change is necessary, it shall proceed as set forth in this Article 12. If Concessionaire believes that a particular item of DB Work is within the then-existing scope of DB Work but Contractor believes that such DB Work constitutes a Scope Change, the Contactor shall diligently proceed with such DB Work as directed in writing by Concessionaire; provided, that if the disputed item of DB Work is subsequently determined to constitute a Scope Change (whether by mutual agreement of the Parties or by operation of the dispute resolution provisions in Section 12.14), then such DB Work shall be deemed to have been the subject of a Work Order under Section 12.9 and Concessionaire shall issue a Scope Change Order with respect thereto as provided in Section 12.10 hereof; otherwise, Contractor shall not be entitled to a Scope Change Order with respect to such item of DB Work. All Scope Changes may be subject to the Department’s consent, as described in Section 24.8 hereof. In the event the Department requires modifications to the Contract Documents as a condition of its approval of any Scope Change, the Parties shall cooperate to effect such modifications. As a condition to Concessionaire’s obligation under this Article 12 to make payments to Contractor in respect to a Scope Change Order or Work Order, Contractor shall increase the amount of the Letter of Credit by ...
Scope Change Orders i. Following agreement on a final Project Plan at the completion of Stage 1 Work, the Parties may enter into a Scope Change Order for the purpose of (a) incorporating the final Project Plan in this Agreement, (b) adjusting the Project Plan Fixed Cost and the associated Discovery Labs Fixed Fee based on the results of Stage 1 Work, and (c) incorporating such other changes that the Parties agree are necessary and appropriate. ii. In addition, it may be necessary during the performance of the Project Plan, to enter into one or more additional Scope Change Orders to implement changes determined by Discovery Labs as being necessary or appropriate under the circumstances to meet its objectives. In that event, the Parties will negotiate in good faith to agree upon an appropriate cost and implementation plan for such Scope Change and enter into a Scope Change Order. To the extent that implementation of a Scope Change, as set forth in the related Scope Change Order, causes the date for completion of the Project Plan to be extended beyond the then current Milestone Date (as defined in Section 3.E(ii), below), then such Milestone Date shall be delayed for the period of such extension. By way of example, if implementation of a Scope Change Order would cause the Project Plan to be extended by one month, then the Milestone Date would be similarly extended to June 30, 2016. HAS BEEN OMITTED BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE REGISTRANT IF PUBLICLY DISCLOSED.
Scope Change Orders. Manager acknowledges that no change shall be made to the Construction Budget for any costs associated with the construction of the Project (a “Scope Change Order”) without the prior written consent of Owner, which consent will not be unreasonably withheld or delayed, and Owner agrees to approve or describe the reason for disapproval of all Scope Change Orders within 10 Business Days of the date of Manager’s written request, which written request shall include all information reasonably necessary for Owner to respond to Manager’s request; provided, however, Owner’s consent shall not be required for any single Scope Change Order that is less than $50,000, or for Scope Change Orders of $250,000 in the aggregate for the fiscal year. All Scope Change Orders must be accompanied by detailed information regarding the need for such Scope Change Order.
Scope Change Orders. A “Scope Change” means a material addition to, deletion from, suspension of or other modification to, the quality, function or intent of the Project as delineated in the Scope Document, or a material change to the requirements of this Agreement, but shall not include refinement, correction or detailing of the Work by Concessionaire and Contractor from time to time. Concessionaire may order Scope Changes to the Work, in which event, as more specifically set forth in Article 12, one or more of the Contract Sum, the Payment and Values Schedule, the Project Schedule and the Guaranteed Substantial Completion Date shall be adjusted accordingly, if necessary, as agreed by Concessionaire and Contractor. If either Concessionaire or Contractor believes a Scope Change is necessary, it shall proceed as set forth in this Article 12. If Concessionaire believes that a particular item of Work is within the then-existing scope of Work but Contractor believes that such Work constitutes a Scope Change, the Contactor shall diligently proceed with such Work as directed in writing by Concessionaire; provided, that if the disputed item of Work is subsequently determined to constitute a Scope Change (whether by mutual agreement of the Parties or by operation of the dispute resolution provisions in Section 12.14), then such Work shall be deemed to have been the subject of a Work Order under Section 12.9 and Concessionaire shall issue a Scope Change Order with respect thereto as provided in Section

Related to Scope Change Orders

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • Change Order The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

  • SCOPE CHANGES The Commissioner reserves the right to require, by written order, changes to the scope of the Contract, by altering, adding to or deducting from the Bid Specifications, such changes to be within the general scope of the Contract. If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under the Contract, whether or not changed by the order, the Commissioner shall, upon notice from Contractor as hereafter stated, make an equitable adjustment in the Contract price, the delivery schedule or both and shall modify the Contract. The Contractor must assert its right to an adjustment under this clause within thirty days from the date of receipt of the written order. However, if the Commissioner decides that the facts justify it, the Commissioner may provide an adjustment without receipt of a proposal. Failure to agree to any adjustment shall be a dispute under the Disputes clause, provided, however, that nothing in this clause shall excuse the Contractor from proceeding with the Contract as changed.

  • Change Order Process 12.2.1 Contractor shall provide Notice to Owner as soon as practicable, but no later than five (5) Business Days, after the time when Contractor knows of the impact of any Force Majeure Event, Owner Caused Delay or any other basis for a Change Order that will impact the Work. Failure to provide such Notice within ten (10) Business Days after the time when Contractor knows of the impact of any Force Majeure Event shall be deemed to be a waiver of the Contractor’s right to receive a Change Order with respect thereto. Such Notice shall, to the extent practicable, specify the estimated impact on the Target Price and/or the Project Schedule, as applicable, the impact upon the various portions of the Work occasioned by reason of such Force Majeure Event, Owner Caused Delay or any other basis for a Change Order, and shall substantiate the foregoing to the satisfaction of Owner. In the event that Contractor does not know or is unable to specify with reasonable certainty the impact upon the Work at the time such Notice is to be delivered, Contractor shall instead provide Owner with a notice of a potential or anticipated impact of any Force Majeure Event, Owner Caused Delay or any other basis for a Change Order that could impact the Work, and shall thereafter provide Owner (and, if requested by Owner, the Independent Engineer) with periodic supplemental Notices during the period that the Force Majeure Event, Owner Caused Delay or any other basis for a Change Order, as applicable, continues, detailing any developments, progress or other relevant information of which Contractor is aware. To the extent Owner (in consultation with the Independent Engineer with respect to a Material Change) agrees with the Contractor’s determination of a Force Majeure Event or Owner Caused Delay or any other basis for a Change Order, as applicable, and the effects thereof, Owner shall notify Contractor of Owner’s acceptance. In the event Owner (in consultation with the Independent Engineer with respect to a Material Change) does not accept the Contractor’s findings, Owner or Contractor shall be permitted to dispute such Change Order in accordance with Article 36, and Contractor shall be paid for any Work performed in respect of such disputed Change Order as provided in Section 12.2.5. 12.2.2 As soon as practicable, and in any event within fifteen (15) Days (or such other period as is mutually agreed by Owner and Contractor) after receipt from Owner of a request for a change or Notice of Owner’s acceptance under Section 12.2.1, Contractor shall submit to Owner a proposal for implementing the change indicating the estimated change to the Target Price and/or the Project Schedule, as applicable. If Owner (having consulted with the Independent Engineer in the case of a Material Change) agrees that the Contractor’s proposal should be implemented, Owner (having consulted with the Independent Engineer in the case of a Material Change) shall issue a Change Order incorporating such proposal. Upon receiving such Change Order, Contractor shall diligently perform the change in accordance with the terms thereof. 12.2.3 Contractor’s proposal required pursuant to Section 12.2.2 shall consist of: (a) a detailed material take-off with supporting calculations in accordance with the pricing structure herein, for pricing the change, (b) revisions, if any, to the Drawings and Specifications, (c) a schedule for the work associated with the proposed change, (d) the effect, if any, to the Target Price and/or the Project Schedule, as applicable, (e) the effect, if any, of the change on the Work, including the Performance Tests and/or Demonstration Tests (or protocol therefor), (f) changes, if any, to any right, liability or obligation of a Party or any other provision hereof and (g) changes, if applicable, to any Applicable Deadline.

  • Change Orders and Contract Amendments 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following: a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity; b) the method of shipment or packing; c) the place of delivery; and d) the Related Services to be provided by the Supplier. 33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order. 33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.