Target times Clause Samples

Target times. Each Party shall use its best endeavors to respond to and rectify faults of a type listed in the following table in accordance with the relevant response and restoration timeframes shown in the table below: Priority Level Fault Types (Key examples) ResponseTime * RestorationTime Level 1 Major switch outage Transmission bearer total outage Route blocking in excess of 50% of utilised capacity Major signalling faults Major routing issues Fraudulent calls Every 1 hour 4 hours Level 2 Minor switch outage Minor routing faults Minor signalling problemsRoute blocking of 10% to 50% of utilised capacity Crossed lines and silent calls Every 4 hours 24 hours Level 3 Faults affecting single or a small number of Customers Route blocking of less than10% of utilised capacity Every 24 hours 72 hours ▇▇▇▇▇ ▇ Remote CongestionExternal Technical Irregularities Other performance related issues Every 48 hours 14 days Any Customer Delays shall be added to the above table.
Target times. Each Party shall respond to, rectify and restore faults of a type listed in the following table in accordance with the target times set out below. Priority Level Fault Types (examples) Response Time Restoration Time Level 1 (Service Affecting (SA)) 1. Power Failure 2. Fibre Optic Cable 3. Inside Plant 4. Fault due to Cable Maintenance 5. Fault due to Equipment Maintenance 6. Fault due to Circuit Maintenance 7. Customer 8. Others Within 1 hour within 60 km from SACOFA base (additional 1 hour is added for every additional 60 km). 4 hours ▇▇▇▇▇ ▇ (▇▇▇- ▇▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇▇ (▇▇▇)) 1. Power Failure 2. Fibre Optic Cable 3. Inside Plant 4. Fault due to Cable Maintenance 5. Fault due to Equipment Maintenance 6. Fault due to Circuit Within 4 hours 24 hours Maintenance 7. Customer Others  Note: The above is not applicable to SACOFA’s submarine cable system, refer to Fault Escalation for Submarine Cable System (Annexure A) Explanatory Notes to Condition 2.12: (a) All faults reported shall be ascribed with a “Priority Level” as set out in the above table for response, progress update frequency and restoration purposes and the Parties involved shall cooperate with one another to achieve the given time targets based on the severity of the fault reported. (b) Some of the common “Fault Types” are listed as example in the above table.
Target times. Each Party shall use its best endeavours to respond to and rectify faults of a type listed in the following table in accordance with the relevant response and restoration timeframes shown in the table below: Level 1 Major switch outage Transmission bearer total outage Route blocking in excess of 50% of utilised capacityMajor signalling faults Major routing issues Fraudulent calls Every 1 hour 4 hours Level 2 Minor switch outage Minor routing faults Minor signalling problemsRoute blocking of 10% to 50% of utilised capacity Crossed lines and silent calls Every 4 hours 24 hours Level 3 Faults affecting single or a small number of Customers Route blocking of less than10% of utilised capacity Every 24 hours 72 hours ▇▇▇▇▇ ▇ Remote CongestionExternal Technical Irregularities Other performance related issues Every 48 hours 14 days Any Customer Delays shall be added to the above table.
Target times. Each Party shall respond to, rectify and restore faults of a type listed in the following table in accordance with the target times set out below.

Related to Target times

  • Contract Times The number of days or the dates stated in the Agreement to: (i) achieve Substantial Completion; and (ii) complete the Work so that it is ready for final payment as evidenced by Architect's or Owner’s representative’s written recommendation of final payment.

  • Project Timeline The Project Timeline establishes a start and end date for each Phase of the Project. Developed during the Initiate & Plan Stage and revised as mutually agreed to, if needed, the timeline accounts for resource availability, business goals, size and complexity of the Project, and task duration requirements.

  • Lead Times Lead times for delivery of the Products are set forth in Schedule B to this Agreement (the “Lead Times”). Supplier shall deliver Products ordered by S&W by the applicable Delivery Date set forth in S&W’s Order, so long as the Delivery Date is consistent with the Lead Times. If applicable Lead Times are not set forth in Schedule B, the Delivery Date shall be such date as reasonably agreed to by the parties.

  • Target 3.1 The target is set out in Schedule 6 to this Agreement, as varied from time to time. 3.2 Whether the target has been met must be determined in accordance with Rule 6. 3.3 The Secretary of State may carry out a review of the sector commitment during 2016 for the target periods 1st January 2017 to 31st December 2018 and 1st January 2019 to 31st December 2020. The target may be varied to take account of the review in accordance with the procedure set out in Rule 12. 3.4 The target may also be varied in accordance with Rules 6, 9, 10 and 11.

  • Contract Time The period of time established for completion of the Project by the Contract Documents. Contract Time commences upon the date specified in the Proceed Order and ends upon the Material Completion and Occupancy Date, as it may be amended.