Target Substantial Completion Date definition

Target Substantial Completion Date means each of the Target Substantial Completion Date for Subproject 1 and the Target Substantial Completion Date for Subproject 2 and “Target Substantial Completion Dates” means collectively the Target Substantial Completion Date for Subproject 1 and Target Substantial Completion Date for Subproject 2.
Target Substantial Completion Date means the date specified in Attachment E, which represents the target date for achieving Substantial Completion of Subproject 5.
Target Substantial Completion Date has the meaning set out in Section 3.1;

Examples of Target Substantial Completion Date in a sentence

  • The Target Substantial Completion Date shall only be adjusted by Change Order as provided under this Agreement.

  • The liquidated damages will be the Owner’s sole claim for damages against the Design-Builder for failure to achieve Substantial Completion by the Target Substantial Completion Date.

  • Owner’s review and comments regarding the Recovery Schedule shall not relieve Contractor of any obligations for performance of the Work, change the Target Substantial Completion Date or Guaranteed Substantial Completion Date or be construed to establish the reasonableness of the Recovery Schedule.

  • Contractor shall be entitled to an adjustment to the Contract Price for reasonable, additional costs incurred by Contractor for delay or in mitigation or avoidance of a delay which would otherwise meet such requirements of this Section 6.9. For the avoidance of doubt, this Section 6.9 shall govern the determination of any right of Contractor to an adjustment to the Target Substantial Completion Date and Guaranteed Substantial Completion Date for delay unless such delay is caused by Force Majeure.

  • Even if the Work is otherwise in compliance with the CPM Schedule, Owner may, at any time, direct Contractor in writing to advance one or both of the Target Substantial Completion Date and the Guaranteed Substantial Completion Date; provided, however, such directive shall be reasonable and Contractor shall have agreed in writing that such acceleration is commercially and technically feasible.


More Definitions of Target Substantial Completion Date

Target Substantial Completion Date means the Target Substantial Completion Date for Subproject 6(a) and, if elected by Owner under the LNG Berth 3 Option pursuant to Section 4.10A herein, the Target Substantial Completion Date for Subproject 6(b), and “Target Substantial Completion Dates” means collectively the Target Substantial Completion Date for Subproject 6(a) and Target Substantial Completion Date for Subproject 6(b).
Target Substantial Completion Date means the date set forth on the Project Schedule, by which the Plant shall have achieved Substantial Completion in accordance with the terms of the Construction Contract.
Target Substantial Completion Date means the date specified in Attachment 5, which represents the target date for achieving Substantial Completion of Project 5.
Target Substantial Completion Date shall have the meaning set forth in Section 4.S(a). “Taxes” shall have the meaning set forth in Section 6.7 of this Contract.
Target Substantial Completion Date means [ ] by which the ESCO shall successfully achieve Substantial Completion which may only be extended in accordance with the provisions of this Agreement;
Target Substantial Completion Date means the date that is * calendar days from the date of Full Notice to Proceed, as such date may be adjusted by mutual agreement of the Parties.
Target Substantial Completion Date means with respect to each Stage, the date on which Contractor is scheduled to achieve Substantial Completion of such Stage, as shown on the CPM Schedule as the “Target Substantial Completion Date”. [***].