Application for Extension of Time Clause Samples

POPULAR SAMPLE Copied 1 times
Application for Extension of Time. 46.8.1. Before the Contractor’s time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying: 46.8.1.1. The Contractor; the registration number; and Project description; 46.8.1.2. Liquidated damage assessment rate, as specified in the Contract; 46.8.1.3. Original total Bid price; 46.8.1.4. The original Contract start date and completion date; 46.8.1.5. Any previous time extensions granted (number and duration); and 46.8.1.6. The extension of time requested. 46.8.2. In addition, the application for extension of time shall set forth in detail: 46.8.2.1. The nature of each alleged cause of delay in completing the Work; 46.8.2.2. The date upon which each such cause of delay began and ended and the number of Days attributable to each such cause; 46.8.2.3. A statement that the Contractor waives all claims except for those delineated in the application, and the particulars of any claims which the Contractor does not agree to waive. For time extensions for Substantial Completion and final completion payments, the application shall include a detailed statement of the dollar amounts of each element of claim item reserved; and 46.8.2.4. A statement indicating the Contractor’s understanding that the time extension is granted only for purposes of permitting continuation of Contract performance and payment for Work performed and that the City retains its right to conduct an investigation and assess liquidated damages as appropriate in the future.
Application for Extension of Time. 13.8.1 Before the Contractor's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying: (a) The Contractor; the registration number; and Project description; 13.8.1 (b) Liquidated damage assessment rate, as specified in the Contract; 13.8.1 (c) Original total bid price; (d) The original Contract start date and completion date; (e) Any previous time extensions granted (number and duration); and 13.8.1(f) The extension of time requested. 13.8.2 In addition, the application for extension of time shall set forth in detail: 13.8.2 (a) The nature of each alleged cause of delay in completing the Work; (b) The date upon which each such cause of delay began and ended and the number of Days attributable to each such cause; (c) A statement that the Contractor waives all claims except for those delineated in the application, and the particulars of any claims which the Contractor does not agree to waive. For time extensions for Substantial Completion and final completion payments, the application shall include a detailed statement of the dollar amounts of each element of claim item reserved; and (d) A statement indicating the Contractor's understanding that the time extension is granted only for purposes of permitting continuation of Contract performance and payment for Work performed and that the City retains its right to conduct an investigation and assess liquidated damages as appropriate in the future.
Application for Extension of Time. 46.8.1. Before the Contractor’s time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying: 46.8.1.1. The Contractor; the registration number; and Project description; 46.8.1.2. Liquidated damage assessment rate, as specified in the Contract;
Application for Extension of Time. 13.8.1. Before the Contractor's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying: (a) The Contractor; the registration number; and Project description; 13.8.1(b) Liquidated damage assessment rate, as specified in the Contract; 13.8.1(c) Original total bid price; 13.8.1 (d) The original Contract start date and completion date; 13.8.1 (e) Any previous time extensions granted (number and duration); and 13.8.1(f) The extension of time requested. 13.8.2. In addition, the application for extension of time shall set forth in detail: 13.8.2 (a) The nature of each alleged cause of delay in completing the Work;
Application for Extension of Time. Before the Construction Manager's request for a time extension for subcontracted work may be approved, the Construction Manager must within five (5) days after commencement of the condition which allegedly has caused or is causing the delay, submit a written application to the Director identifying: (a) the Construction Manager; the Subcontractor; the Agreement registration number; and Project description; (b) liquidated damage assessment rate, as specified in the subcontract; (c) original subcontract bid amount; (d) the original subcontract start date and completion date; (e) any previous time extensions granted (number and duration); and (f) the extension of time requested. In addition, the application for extension of time shall set forth in detail: (a) the nature of each alleged cause of delay in completing the work; (b) the date upon which each such cause of delay began and ended and the number of days attributable to each such cause; (c) a statement that the Construction Manager waives all claims except for those delineated in the application, and the particulars of any claims which the Construction Manager does not agree to waive. For time extensions for final completion payments, the application shall include a detailed statement of the dollar amounts of each element of claim item reserved; and (d) a statement indicating the Construction Manager's understanding that the time extension is granted only for the purpose of permitting continuation of performance and payment for work performed and that CUCF retains its right to conduct an investigation and assess liquidated damages as appropriate.
Application for Extension of Time. Any application by Tenant for an adjustment to the Schedules or for any other extension of time, must be in writing, must set forth in detail the reasons and causes of delay, and must be submitted to RDC within fifteen (15) days following the actual discovery of the cause of the delay. Tenant shall use due diligence to discover the occurrence of any delays. To the extent reasonably possible, the notice of the delay must describe the portion of the Design Services, the Development Services or the Work actually delayed, a description of the cause of the delay, and a description of how the cause of the delay affected the progress of the Design Services, the Development Services or the Work. To the extent reasonably possible, Tenant shall provide an estimate of the probable effect of such delay on the Schedules. RDC agrees to notify Tenant, within five (5) days after receipt of Tenant's notice, whether or not RDC concurs with Tenant's assessment of the delay.

Related to Application for Extension of Time

  • Extension of Time If the Executive shall be in violation of any provision of this Article 6, then each time limitation set forth in this Article 6 shall be extended for a period of time equal to the period of time during which such violation or violations occur. If the Company seeks injunctive relief from such violation in any court, then the covenants set forth in this Article 6 shall be extended for a period of time equal to the pendency of such proceeding including all appeals by the Executive.

  • Extension of Time, Waiver, Etc At any time prior to the Effective Time, any party may, subject to applicable Law, (a) waive any inaccuracies in the representations and warranties of any other party hereto, (b) extend the time for the performance of any of the obligations or acts of any other party hereto or (c) waive compliance by the other party with any of the agreements contained herein or, except as otherwise provided herein, waive any of such party’s conditions. Notwithstanding the foregoing, no failure or delay by the Company, Parent or Merger Sub in exercising any right hereunder shall operate as a waiver thereof nor shall any single or partial exercise thereof preclude any other or further exercise thereof or the exercise of any other right hereunder. Any agreement on the part of a party hereto to any such extension or waiver shall be valid only if set forth in an instrument in writing signed on behalf of such party.