CHANGE ORDER REQUIRED Clause Samples

The 'Change Order Required' clause mandates that any modifications to the original contract must be formally documented and approved through a change order process. In practice, this means that if the scope of work, project timeline, or costs need to be altered, both parties must agree to and sign a written change order before the changes take effect. This clause ensures that all adjustments are clearly recorded and mutually accepted, preventing misunderstandings and disputes over unauthorized or informal changes to the contract.
CHANGE ORDER REQUIRED. Any alteration, deviation or change in the work to be performed shall be reduced to a writing entitled “Change Order”, and signed by ▇▇▇▇▇ and ▇▇▇▇▇▇ in order to be effective. Whether the changes involve extra costs or not, they will only be executed upon such written order. Such writing shall specify the change or changes, any adjustments in price therefore, and shall be exe- cuted with the same formalities as this agreement, thereby becoming a part hereof.
CHANGE ORDER REQUIRED. No change in the Work shall be the basis of an addition to the Contract Sum or a change in the Contract Time unless and until such change has been specifically authorized by a Change Order executed and issued in accordance with the Contract Documents. Changes in the Work may be made without notice to Construction Manager's sureties, and absence of such notice shall not relieve such sureties of any of their obligations to Owner. 7.4.1 If a change in the Work is to be ordered, a preliminary request ("'Change Order Request"') shall be issued by Development Manager to Construction Manager describing the change and requesting the submission of a Change Order. Subject to the provisions of the Disbursement Agreement, when time does not permit the processing of a Change Order in advance of commencing the change in the Work, upon receipt of a written authorization from Development Manager, Construction Manager shall proceed with a change in the Work and Construction Manager shall concurrently proceed with submission of a Change Order. Such written authorization shall constitute a commitment by Owner and Development Manager to subsequently issue a Change Order providing for an addition to the Contract Time to complete the Work and/or an increase in the Contract Sum 7.4.2 Within three (3) days of its receipt of a Change Order Request, Construction Manager shall provide a preliminary estimate of any change in the Cost of the Work or Contract Time associated with the change described in the Change Order Request. Within ten (10) days following receipt of a Change Order Request, Construction Manager shall submit a Change Order Request to Development Manager together with the revised or new documents which, if approved by Owner, will become part of the Contract Documents setting forth any adjustment in the Cost of the Work or the Contract Time, and including an itemization of all costs of material and labor with extensions listing quantities and total costs, and a substantiation of any Claim for an extension of the Contract Time. If no Change Order request is submitted by Construction Manager within such period, it shall be conclusively presumed that the change described in the Change Order Request does not call for any Work that results in an increase in the Cost of the Work or the Contract Time, and such change shall be performed by Construction Manager without any such increase. If Construction Manager is unable to submit the above information within the time limit it ...

Related to CHANGE ORDER REQUIRED

  • Change Order The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

  • Purchase Order Requirements Customers shall use a Request for Quote per section 287.056(2), Florida Statutes, when making purchases off of this State Term Contract. Customers shall issue Request for Quotes to at least 25 vendors approved to provide IT Staff Augmentation services in accordance with section 287.0591(5), Florida Statutes. Customers shall order services from the Request for Quote via a Purchase Order with the Customers’ selected Contractor. The terms of the Purchase Order shall not conflict with the terms and conditions established by this Contract. In accepting a Purchase Order, the Contractor recognizes its responsibility for all tasks and deliverables contained therein, warrants that it has fully informed itself of all relevant factors affecting accomplishment of the tasks and deliverables and agrees to be fully accountable for the performance thereof.

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • Change Order Process 12.2.1 Contractor shall provide Notice to Owner as soon as practicable, but no later than five (5) Business Days, after the time when Contractor knows of the impact of any Force Majeure Event, Owner Caused Delay or any other basis for a Change Order that will impact the Work. Failure to provide such Notice within ten (10) Business Days after the time when Contractor knows of the impact of any Force Majeure Event shall be deemed to be a waiver of the Contractor’s right to receive a Change Order with respect thereto. Such Notice shall, to the extent practicable, specify the estimated impact on the Target Price and/or the Project Schedule, as applicable, the impact upon the various portions of the Work occasioned by reason of such Force Majeure Event, Owner Caused Delay or any other basis for a Change Order, and shall substantiate the foregoing to the satisfaction of Owner. In the event that Contractor does not know or is unable to specify with reasonable certainty the impact upon the Work at the time such Notice is to be delivered, Contractor shall instead provide Owner with a notice of a potential or anticipated impact of any Force Majeure Event, Owner Caused Delay or any other basis for a Change Order that could impact the Work, and shall thereafter provide Owner (and, if requested by Owner, the Independent Engineer) with periodic supplemental Notices during the period that the Force Majeure Event, Owner Caused Delay or any other basis for a Change Order, as applicable, continues, detailing any developments, progress or other relevant information of which Contractor is aware. To the extent Owner (in consultation with the Independent Engineer with respect to a Material Change) agrees with the Contractor’s determination of a Force Majeure Event or Owner Caused Delay or any other basis for a Change Order, as applicable, and the effects thereof, Owner shall notify Contractor of Owner’s acceptance. In the event Owner (in consultation with the Independent Engineer with respect to a Material Change) does not accept the Contractor’s findings, Owner or Contractor shall be permitted to dispute such Change Order in accordance with Article 36, and Contractor shall be paid for any Work performed in respect of such disputed Change Order as provided in Section 12.2.5. 12.2.2 As soon as practicable, and in any event within fifteen (15) Days (or such other period as is mutually agreed by Owner and Contractor) after receipt from Owner of a request for a change or Notice of Owner’s acceptance under Section 12.2.1, Contractor shall submit to Owner a proposal for implementing the change indicating the estimated change to the Target Price and/or the Project Schedule, as applicable. If Owner (having consulted with the Independent Engineer in the case of a Material Change) agrees that the Contractor’s proposal should be implemented, Owner (having consulted with the Independent Engineer in the case of a Material Change) shall issue a Change Order incorporating such proposal. Upon receiving such Change Order, Contractor shall diligently perform the change in accordance with the terms thereof. 12.2.3 Contractor’s proposal required pursuant to Section 12.2.2 shall consist of: (a) a detailed material take-off with supporting calculations in accordance with the pricing structure herein, for pricing the change, (b) revisions, if any, to the Drawings and Specifications, (c) a schedule for the work associated with the proposed change, (d) the effect, if any, to the Target Price and/or the Project Schedule, as applicable, (e) the effect, if any, of the change on the Work, including the Performance Tests and/or Demonstration Tests (or protocol therefor), (f) changes, if any, to any right, liability or obligation of a Party or any other provision hereof and (g) changes, if applicable, to any Applicable Deadline.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.