Contractor Requested Change Order Clause Samples

A Contractor Requested Change Order clause allows the contractor to formally propose modifications to the original scope, schedule, or cost of a project. Typically, the contractor submits a written request detailing the desired changes and justifying the need, such as unforeseen site conditions or design clarifications. This clause ensures that any alterations initiated by the contractor are reviewed, approved, and documented by the owner or project manager, thereby maintaining control over project changes and preventing unauthorized work or disputes over compensation.
Contractor Requested Change Order. Contractor may propose a Change Order to Owner if the proposed changes improve the Facility or are otherwise advisable for the Work. Any such proposed Change Order shall not affect the obligation of Contractor to perform the Work and to deliver the Facility in accordance with this Agreement unless and until Owner executes a Change Order pursuant to Section 10.6. If the Parties do not agree on the adjustment to the Contract Price in respect of this Section 10.2, then the adjustment to the Contract Price may be determined in accordance with Exhibit 18 but only if the Parties so agree. If the Parties do not agree either (a) to a fixed price Change Order or (b) that an adjustment to the Contract Price shall be determined in accordance with Exhibit 18, then no Change Order shall be executed. If Contractor proceeds with a proposed change in the Work pursuant to this Section 10.2 without receiving the consent of Owner, Contractor shall be responsible for the removal of any such work if a Change Order request is not subsequently approved by Owner; provided, however, that in the event of any Emergency affecting the safety of persons or property, Contractor shall act, at its discretion, to prevent threatened damage, injury or loss.
Contractor Requested Change Order. 4.4.1 Contractor shall be entitled to submit a request for a Change Order with respect to: (a) the failure of, or inability to run, a Process Test or remedial work in connection with a failure of a Process Test, in each case other than solely due to a Defect, unless covered by an Owner-initiated Change Order; (b) a delay caused by a failure of Owner to provide Front End Feedstock for purposes of Performance Tests in accordance with the requirements of Exhibit M; (c) a Force Majeure Event; (d) any Change of Law, unless such Change of Law is due to an act or omission of Contractor; (e) Owner's failure to comply with Section 2.7 regarding Hazardous Wastes or Materials or any delay arising as a result of the handling, removal, transportation or disposal of any Hazardous Waste or Materials by the Owner in accordance with and to the extent required by Section 2.7; (f) a delay caused by a failure of Owner to furnish the Site and to provide rights of ingress and egress to and from the Site for Contractor and its Subcontractors to the extent specified in the Site Access Plan; (g) a delay caused by Owner's failure to assist Contractor to the extent provided in Section 2.2 in obtaining Governmental Approvals to be obtained by Contractor or a delay caused by Owner's delay in obtaining Governmental Approvals to be obtained by Owner in accordance with Section 2.2 (other than as a result of a failure of Contractor to assist Owner in accordance with Section 3.4); (h) Owner's failure to provide, or failure to cause Operator to provide, operations personnel in accordance with Section 2.3; (i) Owner's failure to make arrangements for the supply of utilities as provided in Section 2.6; (j) the suspension of the Work or any portion thereof pursuant to Article 14; (k) an unreasonable exercise by any of Owner's Parties of inspection or observation rights pursuant to Section 6.2 which results in delay or adverse cost impact; (l) a rejection of Work by Owner in accordance with Section 6.4, following which it is determined that no Defect occurred; (m) a delay caused by a claim as a result of which Contractor is required to change the scope of Work (provided that so long as Contractor is indemnified for such claim by Owner, Contractor shall not change the scope of Work without Owner's consent) or by an injunction issued by a court of competent jurisdiction, in each case relating to an intellectual property infringement arising out of the Pro Terra(TM) Process; (n) written instructio...

Related to Contractor Requested Change Order

  • Change Order The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • Contract Task Order A- E shall be assigned work via a task order by COUNTY which shall subsequently be referred to as the “Contract Task Order” (hereinafter “CTO”). A CTO for each project shall be developed by A-E in conjunction with COUNTY Project Management staff. The County Project Manager shall manage all A-E’s work including monitoring the CTO work schedule, quality of deliverables, review of invoiced amounts, adherence to set budget, and internal review of submittal packages. A-E shall follow all requirements as outlined in the CTO; this general Scope of Work, the project specific Scope Statement, and the Architect-Engineer Guide (Rev July 2018). The CTO shall include a detailed Scope Statement, describing tasks to be performed with a specific list of deliverables for each task, schedule of work and cost to complete the work. The schedule of work shall allow enough time for meetings with County Management staff to review the work progress, provide technical and policy direction, resolve problems and ensure adherence to the work completion schedule. The CTO shall include a cover sheet provided by County Project Management staff with the appropriate signature blocks and contract information. Once both Parties agree, and all Parties have signed the CTO, County Management staff shall provide A-E with a Notice to Proceed (NTP) to begin work. A-E shall submit all plans, reports and other documents produced under the CTO to the assigned County Project Manager within the timeframe indicated in the CTO or as directed by County Project Management staff.

  • Contractor Changes The Contractor shall notify DAS in writing no later than ten (10) Days from the effective date of any change in: a. its certificate of incorporation or other organizational document; b. more than a controlling interest in the ownership of the Contractor; or c. the individual(s) in charge of the Performance. This change shall not relieve the Contractor of any responsibility for the accuracy and completeness of the Performance. DAS, after receiving written notice by the Contractor of any such change, may require such agreements, releases and other instruments evidencing, to DAS’s satisfaction, that any individuals retiring or otherwise separating from the Contractor have been compensated in full or that provision has been made for compensation in full, for all work performed under terms of the Contract. The Contractor shall deliver such documents to DAS in accordance with the terms of DAS’s written request. DAS may also require, and the Contractor shall deliver, a financial statement showing that solvency of the Contractor is maintained. The death of any Contractor Party, as applicable, shall not release the Contractor from the obligation to Perform under the Contract; the surviving Contractor Parties, as appropriate, must continue to Perform under the Contract until Performance is fully completed.

  • Change Order Process 12.2.1 Contractor shall provide Notice to Owner as soon as practicable, but no later than five (5) Business Days, after the time when Contractor knows of the impact of any Force Majeure Event, Owner Caused Delay or any other basis for a Change Order that will impact the Work. Failure to provide such Notice within ten (10) Business Days after the time when Contractor knows of the impact of any Force Majeure Event shall be deemed to be a waiver of the Contractor’s right to receive a Change Order with respect thereto. Such Notice shall, to the extent practicable, specify the estimated impact on the Target Price and/or the Project Schedule, as applicable, the impact upon the various portions of the Work occasioned by reason of such Force Majeure Event, Owner Caused Delay or any other basis for a Change Order, and shall substantiate the foregoing to the satisfaction of Owner. In the event that Contractor does not know or is unable to specify with reasonable certainty the impact upon the Work at the time such Notice is to be delivered, Contractor shall instead provide Owner with a notice of a potential or anticipated impact of any Force Majeure Event, Owner Caused Delay or any other basis for a Change Order that could impact the Work, and shall thereafter provide Owner (and, if requested by Owner, the Independent Engineer) with periodic supplemental Notices during the period that the Force Majeure Event, Owner Caused Delay or any other basis for a Change Order, as applicable, continues, detailing any developments, progress or other relevant information of which Contractor is aware. To the extent Owner (in consultation with the Independent Engineer with respect to a Material Change) agrees with the Contractor’s determination of a Force Majeure Event or Owner Caused Delay or any other basis for a Change Order, as applicable, and the effects thereof, Owner shall notify Contractor of Owner’s acceptance. In the event Owner (in consultation with the Independent Engineer with respect to a Material Change) does not accept the Contractor’s findings, Owner or Contractor shall be permitted to dispute such Change Order in accordance with Article 36, and Contractor shall be paid for any Work performed in respect of such disputed Change Order as provided in Section 12.2.5. 12.2.2 As soon as practicable, and in any event within fifteen (15) Days (or such other period as is mutually agreed by Owner and Contractor) after receipt from Owner of a request for a change or Notice of Owner’s acceptance under Section 12.2.1, Contractor shall submit to Owner a proposal for implementing the change indicating the estimated change to the Target Price and/or the Project Schedule, as applicable. If Owner (having consulted with the Independent Engineer in the case of a Material Change) agrees that the Contractor’s proposal should be implemented, Owner (having consulted with the Independent Engineer in the case of a Material Change) shall issue a Change Order incorporating such proposal. Upon receiving such Change Order, Contractor shall diligently perform the change in accordance with the terms thereof. 12.2.3 Contractor’s proposal required pursuant to Section 12.2.2 shall consist of: (a) a detailed material take-off with supporting calculations in accordance with the pricing structure herein, for pricing the change, (b) revisions, if any, to the Drawings and Specifications, (c) a schedule for the work associated with the proposed change, (d) the effect, if any, to the Target Price and/or the Project Schedule, as applicable, (e) the effect, if any, of the change on the Work, including the Performance Tests and/or Demonstration Tests (or protocol therefor), (f) changes, if any, to any right, liability or obligation of a Party or any other provision hereof and (g) changes, if applicable, to any Applicable Deadline.