No Damage for Delays Clause Samples

POPULAR SAMPLE Copied 1 times
No Damage for Delays. Specialty Laboratories shall have no claim for damages against BNPPLC or for an increase in the Construction Allowance by reason of any delay in the performance of any Work. Nor shall Specialty Laboratories have any claim for an extension of the deadline specified in subparagraph 2(A)(2)(a) for completing the Work because of any such period of delay, unless, however, such delay has been caused by BNPPLC's intentional interference with Work. In the event (and only to the extent) that any such intentional interference by BNPPLC continues after Specialty Laboratories provides written notice to cease, Specialty Laboratories shall be entitled to an extension of such deadline. BNPPLC's exercise of its rights and remedies permitted under this Agreement or the other Operative Documents will not be construed as intentional interference with Specialty Laboratories' performance of any Work.
No Damage for Delays. Except for delays due to the gross negligence of the Owner or active interference by the Owner, Design-Builder’s sole and exclusive remedy for delays shall be an increase to the Contract Time. Design-Builder shall not be entitled to an increase in the Contract Sum or to payment of any other additional monies from Owner for costs incurred as a result of such delay, including additional or extended General Conditions costs or General Requirements costs. Owner’s exercise of its rights under this Contract shall in no way be considered active interference.
No Damage for Delays. NAI will have no claim for damages against BNPPLC or for an increase in the Construction Allowance by reason of any delay in the performance of any Work. Nor will NAI have any claim for an extension of the deadline specified in subparagraph 2(A)(2)(a) for completing the Work because of any such period of delay, except that (i) in the case of any Pre-lease Force Majeure Delays, NAI will have certain rights as set forth in subparagraph 7(B) and other provisions of this Agreement, and (ii) in the event of intentional interference with the Work by BNPPLC itself for which NAI provides written notice to cease, NAI will be entitled to an extension of the deadline specified in subparagraph 2(A)(2)(a) as needed because of any delays resulting from such intentional interference. It is also understood that any such intentional interference by BNPPLC will constitute a Force Majeure Event. In no event, however, will BNPPLC’s exercise of its rights and remedies permitted under this Agreement or the other Operative Documents be construed as intentional interference with NAI’s performance of any Work; and thus neither BNPPLC’s exercise of its right to withhold Construction Advances at any time when NAI has failed to satisfy all conditions herein to such advances, nor BNPPLC’s exercise of its right to terminate Work by NAI as provided in subparagraph 7(C), be considered as intentional interference with the Work or a Pre-lease Force Majeure Event.
No Damage for Delays. Notwithstanding any provision in the UGCs, an extension of the Contract Time shall be the sole remedy of CMR for delays in performance of the Work, whether or not such delays are foreseeable, except for delays caused solely by acts of TFC that constitute intentional interference with CMR’s performance of the Work and then only to the extent such acts continue after CMR notifies TFC in writing of such interference. For delays caused by any act(s) other than the sole intentional interference of TFC, CMR shall not be entitled to any compensation or recovery of any damages including, without limitation, consequential damages, lost opportunity costs, impact damages, loss of productivity, or other similar damages as set forth in Section 13.1.3.1 below. TFC’s exercise of any of its rights or remedies under the Contract including, without limitation, ordering changes in the Work or directing suspension, rescheduling, or correction of the Work, shall not be construed as intentional interference with CMR’s performance of the Work regardless of the extent or frequency of TFC’s exercise of such rights or remedies. 13.1.3.1 The amount of any claim for damages asserted by CMR for a delay caused by TFC’s sole intentional interference shall not exceed the sum calculated as follows: (i) the per diem amount of CMR’s General Conditions Costs set forth in 8.2 x number of days of delay plus (ii) direct costs incurred during the period of delay based on allowable Costs of the Work set forth in Section 8.1. CMR shall not be entitled to (z) any indirect or consequential damages, (y) home office overhead, home office charges, or any damages based on Eichleay formula calculation;
No Damage for Delays. NAI shall have no claim for damages against BNPLC or for an increase in the Construction Allowance by reason of any delay in the performance of any Work.
No Damage for Delays. Ross shall have no claim for damages against BNPPLC or for an increase in the Construction Allowance by reason of any delay in the performance of any Work. Nor shall Ross have any claim for an extension of the deadline specified in subparagraph for completing the Work because of any such period of delay, unless, however, such delay has been caused by BNPPLC's intentional interference with Work. In the event (and only to the extent) that any such intentional interference by BNPPLC continues after Ross provides written notice to cease, Ross shall be entitled to an extension of such deadline. BNPPLC's exercise of its rights and remedies permitted under this Agreement or the other Operative Documents will not be construed as intentional interference with Ross's performance of any Work.
No Damage for Delays. Notwithstanding any provision in the UGCs, an extension of the Contract Time shall be the remedy of DB for delays in performance of the Work, whether or not such delays are foreseeable, except for delays to the extent caused by acts of TFC that constitute intentional interference with DB’s performance of the Work to the extent DB notifies TFC in writing of such interference. For delays caused by the intentional interference of TFC, DB shall be entitled to an equitable adjustment to the Contract Sum and Contract Time. TFC’s good faith exercise of its remedy under the Contract to order correction of the Work shall not be construed as intentional interference with DB’s performance of the Work. 13.1.3.1 The amount of any claim for damages asserted by DB for a delay caused by TFC’s sole intentional interference shall not exceed the sum calculated as follows: (i) the per diem amount of DB’s General Conditions Costs set forth in Section 7.2 x number of days of delay plus (ii) direct costs incurred during the period of delay based on allowable Costs of the Work set forth in Section 7.1. DB shall not be entitled to (a) any indirect or consequential damages,
No Damage for Delays. CONTRACTOR expressly agrees and acknowledges that its sole remedy for any delays referenced in Section (b), above, shall, if such Excusable Delay impacts the critical path of the Project, be an extension of time, plus all actual documented CONTRACTOR and subcontractor costs reasonably agreed to by the parties and CONTRACTOR fees (outlined in Section 4) to COMPANY, CONTRACTOR and COMPANY expressly waive any and all claims for damages for lost productivity, labor inefficiencies, acceleration of the Schedule of Completion , any lost profits, consequential damages and any other alleged impact damages not otherwise expressly part of the Contract Price (excluding any liquidated damages).

Related to No Damage for Delays

  • No Damages for Delay The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.

  • Damages for delay Subject to the provisions of Clause 12.4, if COD does not occur prior to the 91st day after the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Concessionaire shall pay Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the amount of Performance Security for delay of each day until COD is achieved.

  • No Damage Any loss, damage or destruction, whether covered by insurance or not, affecting Company's business or properties;

  • Force Majeure, Notice of Delay, and No Damages for Delay The Contractor will not be responsible for delay resulting from its failure to perform if neither the fault nor the negligence of the Contractor or its employees, subcontractors, or agents contributed to the delay and the delay is due directly to acts of God, wars, acts of public enemies, strikes, fires, floods, or other similar cause wholly beyond the Contractor’s control, or for any of the foregoing that affect suppliers if no alternate source of supply is available to the Contractor. In case of any delay the Contractor believes is excusable, the Contractor shall notify the Department in writing of the delay or potential delay and describe the cause of the delay either (i) within ten (10) calendar days after the cause that creates or will create the delay first arose, if the Contractor could reasonably foresee that a delay could occur as a result; or (ii) if a delay is not reasonably foreseeable, within five (5) calendar days after the date the Contractor first had reason to believe that a delay could result. THE FOREGOING WILL CONSTITUTE THE CONTRACTOR’S SOLE REMEDY OR EXCUSE WITH RESPECT TO ANY DELAY except if such delay is caused by the fraud, bad faith, or active interference of the Department. Providing notice in strict accordance with this paragraph is a condition precedent to such remedy, and a rebuttable presumption of prejudice will exist based on Contractor’s untimely notice. The Contractor shall not assert any claim for damages related to such delay. The Contractor will not be entitled to an increase in the Term Contract price or payment of any kind from the Department for direct, indirect, consequential, impact, or other costs, expenses, or damages, including costs of acceleration or inefficiency, arising because of delay, disruption, interference, or hindrance from any cause whatsoever. If performance is suspended or delayed, in whole or in part, due to any of the causes described in this subsection, the Department may unilaterally (and with no recourse on the part of the Contractor) identify and use an alternate source to complete any work under the Term Contract as the Department deems necessary, in its sole discretion. After the causes have ceased to exist, the Contractor shall perform at no increased cost, unless the Department determines, in its sole discretion, that the delay will significantly impair the value of the Contract to the Department or State, in which case the Department may (i) accept allocated performance or deliveries from the Contractor, provided that the Contractor grants preferential treatment to the Department with respect to Products subjected to allocation; or (ii) terminate the Term Contract in whole or in part.

  • Liability for Damage Each party shall be liable to the other for all damage to the property of the other negligently, recklessly or intentionally caused by that party (or their agents, employees or invitees), except to the extent the loss is insured and subrogation is waived under the owner's policy.