Pipework Sample Clauses

The Pipework clause defines the requirements and standards for the installation, maintenance, and quality of piping systems within a project. It typically outlines the types of materials to be used, installation methods, testing procedures, and compliance with relevant codes or regulations. For example, it may specify that all pipe joints must be leak-tested before commissioning or that only certain grades of metal piping are acceptable. The core function of this clause is to ensure that all pipework is safe, reliable, and fit for purpose, thereby minimizing the risk of leaks, failures, or non-compliance with legal standards.
Pipework. TS-777 Excavation of any section of the work shall not start until a complete set of the pipes and components for that section is available. TS-778 The trench shall be as narrow as practicable but not less than the pipe diameter plus 300 mm from each side to permit adequate compaction of side fill. Adequate working space shall be left for pipe jointers and joint holes shall be formed where necessary.
Pipework. The following supply items shall be supplied and installed by others: • The inlet under the floor and inside the inlet structure of the tank • The sludge draw-off pipe • The effluent pipe work The pipes shall be manufactured from 304 SS. The contractor under this Contract must, however, supply and install the scum discharge pipe up to the scum discharge manhole adjacent to the tank, which will be built by the Civil Contractor.
Pipework. 1. All the pipework supplied in one contract and complying with this specification shall be designed, manufactured, fabricated, erected and tested to comply with the contractually defined latest edition of a single national or international code and its associated standards. Mixing of codes from different countries of origin is not acceptable. 2. All pipes are to be sized to ensure that the process requirement is met with an economically viable and energy efficient solution. Pipe supports shall be provide if the pipe is not buried. 3. The pipeline shall conform to environmental regulation. Pipes are to follow best practices and shall adopt the same Pipework Standard/Code currently at the facility. 4. The design should incorporate the provision for meaningful in-service non-destructive testing during periodic overhauls of the pipeline. The provision and installation of the primary measuring elements for the control and instrumentation will all be required. The provision of all isolating valves and the necessary actuators will be required. 5. All pipes are required to be mild steel, the Contractor determines the required pressure rating of the pipe based on the equipment and pumping system selected. 6. All pipes are required to be compatible for use with the temperature unit. 7. Pipes are required to be sloped and include drain valves to cater for drainage during maintenance, and includes isolation valves. 8. The pipes are required to include all fittings (bends, expansion joints, etc.) and supports where needed. 9. Pipe supports are to be according manufacturer specifications when the pipe is above ground. 10. Pipe sizes are to be selected so that the following maximum permitted velocities or pressure differentials are not exceeded by design, or maximum upset conditions. a) Pump suction piping 1.5 5 to 25 b) Process water 2.5 5 to 50 11. The Contractor submits the pipe data sheets and complete design to Employer for acceptance. 12. The Contractor’s design verifies and ensures the integrity of all pipe work. The materials of construction for the pipework is suitable for the water and environment it is in contact with. 13. The contractor performs corrosion protection in accordance to 240-101712128: Standard for the Internal Corrosion Protection of Water Systems, Chemical Tanks and Vessels and Associated Piping with Linings. 14. All pipes are painted at minimum in accordance to SANS 10140: Identification Colour Marking. 15. The Contractor ensures that the Hydr...
Pipework. All pipe work shall be galvanized seamless steel to BS 1387 heavy grade. Pipework with screw fittings shall be supplied with screw and socket ends. Pipework for gas and arc welding, where permitted by the Engineer or his Representative, shall be supplied with plain ends, bevelled for butt welding. All pipework and fittings shall be to NFP A 14. For pipe work installation, hangers, welding, etc., details refer to Section 14-22 of these Specifications. Under tiles, steel pipe work shall be protected against corrosion by two layers of hessian and tar to the Engineer or his Representative IS approval. Valves, strainers, etc. shall be as specified in Section 3.11 of this Specification.
Pipework. PE100 PN12.5 delivery mains have been specified but may be substituted with stainless steel pipes. Stainless steel pipes, bends, tapers, flanges, brackets and associated butt-welded fittings shall be fabricated from 316 graded, schedule (SCH) 10S stainless steel and installed in accordance with the Contract Drawings, approved Contractor supplied drawings, WSA 04 Part 3 Clause 25.3 and AS 5200.053. Flanges shall be a minimum thickness of 13mm or 16mm, as nominated in the Contract Drawings and shall be drilled in accordance with Table D of AS 2129. All flanged fittings shall be provided with the appropriate flange gaskets, stainless steel bolts, nuts and washers. All bolts, nuts and washers shall have metric threads as per AS 1111, AS 1112 and AS 1237, respectively.
Pipework. Conformance testing associated with all pipework within the SPS facility shall be carried out in accordance with the requirements outlined in Clause 3 of this Technical Specification.
Pipework. All pipework, connections and delivery systems must conform to British Standard 6572. Pipes laid underground must be buried to a minimum depth of 750mm. Pipe laying may be done by trenching, mole plough or sub-soiler, depending on soil type and machinery available. The ground must be reinstated to original levels with the top soil returned to the surface. Where open ditches are crossed, the pipe must be covered by a tubular steel guard or sleeve pipe and laid 600 mm below the ditch bottom to allow for ditch cleaning. Where farm tracks are crossed, the water pipe must lay on a 75mm bed of sand and be covered by sand to a depth of 100mm before being overlain by backfill. The water supply must be controlled by isolating valves/stop cocks at the point of supply and at each trough. The isolating valves/stop cocks must be protected against frost, they must be easily accessible and protected from damage by livestock. Where they are buried, this must be at a minimum of 600mm and must be easily accessible through a covered inspection chamber. Underground pipework must not damage sites of archaeological or historic interest. Any spoil must not be used to fill and level adjacent wet areas or be put on any sites of archaeological or ecological importance. The water supply must be maintained in good condition for the duration of the agreement. The water trough should be placed in a free draining area to minimise damage by poaching. It should not be placed on or near sensitive habitats or species and the area should ideally be a sacrifice area. The trough should not be located near watercourses, on areas vulnerable to soil erosion or on or near a site of archaeological or historic interest. Troughs made of galvanised steel must comply with British Standard 3445. Other materials such as concrete or moulded polyethylene may be acceptable if agreed with your Natural England contact and if it complies with the appropriate British Standard. The water trough must be installed on a level base so it does not spill water. The trough must either be connected to a water supply or it must be supplied from a ▇▇▇▇▇▇ on a regular basis. The water trough must be maintained in good condition for the duration of the agreement.
Pipework. All suction and delivery pipes shall be connected to the pump casing by means of flexible connections. All flexible connections shall be installed as close to the pump’s casings as possible, and in any event, shall be between the suction valve and the pump casing and delivery non-return valve and the pump casing. In all cases the flexible connection shall be in the section of piping of smallest diameter. Double Victaulic joint are generally preferred for flexible connections, but approved re-enforced rubber bellow units are acceptable for low-pressure services. All valves and pipework external to the pump casing and separated there from by means of flexible connections shall be securely anchored to prevent movement.

Related to Pipework

  • Shiftwork (A) Where the Employee would have received shift loadings had the Employee not been on leave during the relevant period and such loadings would have entitled the Employee to a greater amount than a loading of 17.5% of the payment under clause 23.1(c), then the shift loadings must be added to the payment under clause 23.1(c)(i) instead of the 17.5% loading. (B) Provided further that if the shift allowance would have entitled the Employee to a lesser amount than the loading of 17.5% then such loading of 17.5% shall be used for the purpose of calculating annual leave loading in lieu of the shift allowance.

  • Electrical Provide drawings for the following systems: .1 Lighting including circuiting and luminaire identification and switching. Also provide illuminance computer printout for all indoor typical indoor spaces and parking lots. .2 Convenience outlets and circuiting, special outlets and circuiting, television outlets, and power systems and equipment. Provide riser diagrams for all electrical systems including master clock, intercom, fire alarm, ITV, computer networking/telephone. Also, provide for emergency and normal power distribution. Provide luminaire schedule. .3 Panel schedule may be in preliminary form but circuitry must be included. .4 Applicable installation details. .5 General legend and list of abbreviations. .6 Voltage drop computation for all main feeders. .7 Short circuit analysis .8 Provide 1/2" scale floor plan and wall elevations for all electrical rooms.

  • Sprinkler System TWENTY-SIXTH.--If there now is or shall be installed in said building a "sprinkler system" the Tenant agrees to keep the appliances thereto in the demised premises in repair and good working condition, and if the New York Board of Fire Underwriters or the New York Fire Insurance Exchange or any bureau, department of official of the State or local government requires or recommends that any changes, modifications, alterations or additional sprinkler heads or other equipment be made or supplied by reason of the Tenant's business, or the location of partitions, trade fixtures, or other contents of the demised premises, or if such changes, modifications, alterations, additional sprinkler heads or other equipment in the demised premises are necessary to prevent the imposition of a penalty or charge against the full allowance for a sprinkler system in the fire insurance rate as fixed by said Exchange, or by any Fire Insurance Company, the Tenant will at the Tenant's own expense, promptly made and supply such changes, modifications, alterations, additional sprinkler heads or other equipment. As additional rent hereunder the Tenant will pay to the Landlord, annually in advance, throughout the term $ toward the contract price for sprinkler supervisory service.

  • Drainage Systems (1) Clear culvert inlets, outlets, and sediment catching basins. (2) Maintain waterbars, drainage dips, and other water diversion measures. (3) During active use, patrol and maintain functional drainage. (4) Repair damaged culvert ends.

  • Electrical appliance safety The Hirer shall ensure that any electrical appliances brought by them to the premises and used there shall be safe, in good working order, and used in a safe manner in accordance with the Electricity at Work Regulations 1989. Where a residual circuit breaker is provided the hirer must make use of it in the interests of public safety.