Common use of Rescheduling of Tests Clause in Contracts

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 104 contracts

Sources: Contract Agreement, Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 62 contracts

Sources: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 45 contracts

Sources: Engineering, Procurement and Construction Agreement, Draft Contract Agreement, Draft Contract Agreement (Dca)

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 26 contracts

Sources: Engineering Procurement and Construction (Epc) Agreement, Contract Agreement, Contract Agreement

Rescheduling of Tests. If the Authority’s Authority Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 17 contracts

Sources: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 16 contracts

Sources: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority MOR and the Contractor Concessionaire that it is unable to issue the Completion Certificate, as the case may be, Certificate because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 8 contracts

Sources: Construction Agreement, Construction Agreement, Construction Agreement

Rescheduling of Tests. If the Authority’s Authority‟s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 7 contracts

Sources: Engineering, Procurement and Construction Agreement, Construction Contract, Epc Agreement

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate, as the case may be, Certificate because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 6 contracts

Sources: Concession Agreement, Model Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 6 contracts

Sources: Draft Contract Agreement, Construction Contract, Construction Contract

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor theContractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 5 contracts

Sources: Construction Contract, Contract Agreement, Construction Contract

Rescheduling of Tests. If the AuthorityEmployer’s Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Sources: Epc Contract, Epc Agreement, Contract Agreement for Design and Construction

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion CertificateCertificate or Phased Completion Certificate(s), as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Sources: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Authority’s 's Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Sources: Construction Contract, Construction Contract, Construction Contract

Rescheduling of Tests. If the Authority’s Employer's Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Sources: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction Agreement

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority MPRDC and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Sources: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held beheld or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 2 contracts

Sources: Concession Agreement, Concession Agreement

Rescheduling of Tests. 12.5.1 If the Authority’s Authority Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule reschedule the Tests and hold the same as soon as reasonably practicable.

Appears in 2 contracts

Sources: Epc Agreement, Epc Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Concession Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. P a g e | 73

Appears in 1 contract

Sources: Engineering Procurement and Construction Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. 13.1 Change of Scope‌‌‌

Appears in 1 contract

Sources: Construction Contract

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Concession Agreement

Rescheduling of Tests. If the Authority’s Authority‟s Engineer certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Concession Agreement

Rescheduling of Tests. If the Authority’s Authority‟s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Engineering, Procurement and Construction Agreement

Rescheduling of Tests. If the Authority’s Engineer Engineer-in-charge certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Contract Agreement

Rescheduling of Tests. If the Authority’s Engineer designated Officer certifies to the Concessioning Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Concession Agreement

Rescheduling of Tests. If the Authority’s Employer‟s Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Epc Agreement

Rescheduling of Tests. If the Authority’s Engineer Engineer-in-Charge certifies to the Authority and the Contractor Concessionaire that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Concession Agreement

Rescheduling of Tests. If the Authority’s AUTHORITY’S/GMDAs Engineer certifies to the Authority Authority/GMDA and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Engineering Procurement and Construction Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances circumstanc- es on account of which the Tests could not be held or had to be suspended, the Contractor Contrac- tor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Construction Contract

Rescheduling of Tests. If the AuthorityEmployer’s Engineer certifies to the Authority Employer and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Demonstration Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Improvement and widening to two lane with paved shoulder of road from Km 21.100 to Km

Appears in 1 contract

Sources: Contract Agreement

Rescheduling of Tests. If the Authority’s Independent Engineer certifies to the Authority SH&DB and the Contractor DEVELOPER that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor DEVELOPER shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Sources: Development Agreement

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. 13.1 Change of Scope‌

Appears in 1 contract

Sources: Construction Contract