SAMPLES AND TESTS Sample Clauses
SAMPLES AND TESTS. OF MATERIALS AND WORK
1. Samples or test specimens of all materials to be used or offered for use in connection with the Work shall be prepared at the expense of Contractor and furnished to County in such quantities and sizes as may be required for proper examination, analysis and tests.
2. All samples shall be submitted in ample time to enable County to conduct any tests, analyses or examinations necessary before the time at which it is desired to incorporate the material into the Work.
3. County may refuse consideration of further samples of same brand or make of material or product previously determined as unsatisfactory for testing, analysis or examination.
SAMPLES AND TESTS. 24.1 The Contractor shall arrange for and furnish to the Architect, samples of any materials, goods or workmanship and perform any tests that may be called for by the Architect for his approval. Any samples and tests approved by the Architect shall be deemed to represent the minimum standard for the part of the Works to which they apply.
24.2 Where the Contractor fails to comply with the provisions of sub-clause 24.1, the Architect may arrange with other parties to provide the requisite samples or carry out the necessary tests. The Contractor shall be obliged to conform to the standards set by such samples or tests. All costs and expenses incurred in the procurement of such samples and tests shall be borne by the Contractor.
SAMPLES AND TESTS. The Contractor shall provide samples, materials, and equipment necessary or required for testing as outlined in the various sections of the Specifications or as directed by the Owner. The Contractor shall pay all costs for testing. Should materials, methods, or systems fail to meet specified standards, the Contractor shall pay all costs for additional testing as required by the Owner. All tests shall be made by a laboratory approved by the Owner. Based upon the site information provided by the Owner, the Contractor shall develop and make detailed surveys necessary for construction including slope stakes, batter boards, and other working points, lines and elevations. The Contractor shall report any errors, inconsistencies, or omissions to the Design Professional as a request for information. The Contractor shall preserve benchmarks, reference points and stakes, and in the case of destruction thereof by the Contractor, shall be responsible for damage or mistakes resulting from unnecessary loss or disturbance.
SAMPLES AND TESTS. The Concessionaire shall, as part of the Implementation Plan, submit to the Independent Engineer / PMC for his consent a detailed description of the arrangements for conducting the quality control programme during execution of the works, including details of his testing laboratory, equipment, staff and general procedures. If following submission, or at any time during the progress of works, it appears to the Independent Engineer / PMC that the Concessionaire‘s quality control programme is not adequate to ensure the quality of the works, the Concessionaire shall produce a programme, as desired by the Independent Engineer / PMC, who will be adequate to ensure satisfactory quality control. All costs of such sampling, testing and reporting of test results will be borne by the Concessionaire. The Concessionaire shall furnish certified copies of all test reports to the Independent Engineer / PMC within 3 days of completion of the specified tests. Where no specific testing procedure is mentioned, the tests shall be carried out as per the prevalent accepted Engineering practice to the directions of the Independent Engineer / PMC.
SAMPLES AND TESTS. No material shall be used in the work until it has been approved by District Engineer. All material and equipment are subject to test to determine their conformity with these specifications. Certified factory and mill tests normally shall be acceptable for standard manufactured items. Tests on other materials, including concrete mix designs and aggregate quality tests shall be made in a materials testing laboratory, approved by District Engineer. All tests shall be performed as specifically or otherwise designated by District Engineer, and shall be completed to District Engineer’s satisfaction. All tests shall be furnished by Contractor at Contractor’s expense. In areas where soil compaction must be repeated due to failure of the compacted material to pass the initial compaction tests, Contractor shall pay for any and all retesting required subsequent to the initial test.
SAMPLES AND TESTS. Article 1106.03 "Samples and Tests" is supplemented and modified as follows:
SAMPLES AND TESTS. OF MATERIALS AND WORK
1. Samples or test specimens of all materials to be used or offered for use in connection with this work shall be prepared at expense of Contractor and furnished to Project Manager and Architect/Engineer in such quantities and sizes as may be required for proper examination and tests.
2. All samples shall be submitted in ample time to enable Project Manager and Architect/Engineer to make any tests, analyses or examinations necessary before the time at which it is desired to incorporate the material into the work.
3. Project Manager and Architect/Engineer may refuse consideration of further samples of same brand or make of material or product previously determined as unsatisfactory for testing, analysis or examination.
4. Test samples or specimens of material for testing shall be taken by Architect/Engineer, his or her representative, Project Inspector or representative of the testing agency.
SAMPLES AND TESTS. Add the following to the end of the fourth paragraph of this Subsection of the Standard Specifications:
SAMPLES AND TESTS. Each consignment of materials required by the Engineer, shall be tested or inspected before being incorporated into the work and approved by the same Engineer before it is used.
SAMPLES AND TESTS. Representative preliminary samples of the character and quality prescribed shall be submitted by the Contractor or producer of all materials to be used in the Work, for testing or examination as desired by the Engineer. All tests of materials furnished by the Contractor shall be made in accordance with commonly recognized standards of national organizations and such special methods and tests as are prescribed in these specifications. The Contractor shall furnish such samples of materials as are requested by the Engineer, without charge. Samples will be secured and tested whenever necessary to determine the quality of material. Contractor shall notify City a sufficient time in advance of the manufacture or production of materials to be supplied by Contractor under this contract in order that City may arrange for mill or factory inspection and testing of same. Any materials shipped by Contractor from factory prior to having satisfactorily passed such testing and inspection by City's representatives, or prior to the receipt of notice from such representative that such testing and inspection will not be required, shall not be incorporated on the job of said improvements. Contractor shall also furnish City, in triplicate, certified copies of all required factory and mill test reports.