Unilateral Change Order Sample Clauses

POPULAR SAMPLE Copied 1 times
Unilateral Change Order. The term “Unilateral Change Order” means a Change Order that may be issued by Judicial Council, without Design Build Entity’s signature, pursuant to the terms of the Contract Documents.
Unilateral Change Order. (ULCO) means a Change Order issued by Owner without the complete agreement of Contractor, as to cost and/or time.
Unilateral Change Order. A written order prepared and issued by the District, the Construction Manager, and/or the Architect and signed by the District and the Architect, directing a change in the Work. A Unilateral Change Order is NOT a Construction Change Document (which is defined above as a Change Order that DSA must approve).
Unilateral Change Order. 100 In the event that agreement cannot be reached as to the cost or credit of the changed work, the Authority shall prepare a cost estimate, and the Contractor will be issued a unilateral change order to proceed with the changed work at a cost not-to-exceed the Authority's estimate. The Contractor shall proceed with the work and maintain accurate records of the actual cost of labor and material to perform the work.
Unilateral Change Order. When a change in the Work is required, and the Judicial Council and the CMR cannot agree as to the amount of the adjustment in the GMP and/or the extent of the adjustment in the Contract Time, the Judicial Council, at its sole discretion and without invalidating the Contract, may unilaterally issue a Change Order either under a lump-sum pricing option or a not-to-exceed time-and-materials pricing option, consistent with the “Lump-Sum Pricing Option” and “Time-and- Materials Pricing Option” provisions herein, for the change in the Work (“Unilateral Change Order”). A Unilateral Change Order shall not require CMR’s written acceptance. CMR shall diligently perform the work of a Unilateral Change Order regardless of any pending dispute thereof and CMR may maintain any rights available to it under the “Disputes and Claims” provisions herein.
Unilateral Change Order a. If the County proceeds under Article 5.6.B or Article 5.7.E, then no later than 30 days from the Satisfactory Completion of any additional Work, the County shall prepare and issue to the Contractor a Unilateral Change Order, including any adjustment in the Contract Price and Contract Time.
Unilateral Change Order. In case of failure on the part of Owner and the Design-Builder to arrive at an agreement on the amount of a credit or an extra cost for a proposed change to the Contract Documents, a unilateral Change Order will be processed in the amount believed by Owner to be reasonable and the Design-Builder shall proceed with the Work. If the Design-Builder believes that the amount set forth in the unilateral Change Order is not a reasonable payment for the Work required the Design-Builder may file a Claim and request for review in accordance with Article 10.
Unilateral Change Order. A Change Order issued by Engineer when agreement cannot be reached with Contractor on the price to be paid or other changes to the Task Order that are in dispute.
Unilateral Change Order. If agreement is not reached in response to a Request for Change Order or Change Proposal then no later than thirty (30) Days after the Satisfactory Completion of any additional Work not in dispute, the County shall execute a unilateral Change Order, including any adjustment in the Contract Price and Contract Time.
Unilateral Change Order. The District may issue a Unilateral Change Order in instances where the parties cannot agree to a price. The District's pricing of the change order shall be made in good faith. The District's issuance of Unilateral Change Order does not preclude the Contractor's right to challenge the amount, but the Contractor is obligated to continue its work while the dispute is considered. The District's price shall be based on a reasonable calculation of labor, labors, and shall be guided in part by such authoritative estimating guides as R.S.