OPERATIONS AND STORAGE AREAS Sample Clauses
OPERATIONS AND STORAGE AREAS. A. All operations of the Contractor (including storage of Materials, and Equipment) shall be confined to areas authorized by the Owner. The Contractor shall be liable for any and all damages caused by him to such premises.
B. The Contractor shall hold and save the Owner free and harmless from liability of any nature or kind arising from any use, trespass, or damage occasioned by his operations on the premises of third persons.
C. The Contractor shall be wholly responsible for the care, compliance with law, and storage of Materials, or Equipment delivered on the Work site or purchased for use thereon. Stored Materials, or Equipment shall be carefully and continuously protected from damage or deterioration and so located so as to facilitate inspection by the Owner. The responsibility for the care and storage of Materials, or Equipment shall be with the Contractor whether such Materials, or Equipment are furnished by the Contractor or by the Owner. Storage of Materials, or Equipment shall not unduly interfere with the progress of the Contractor's Work or the Work of any other Contractor.
OPERATIONS AND STORAGE AREAS. Confinement to Authorized Areas. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer.
OPERATIONS AND STORAGE AREAS. A. The Contractor shall confine all operations (including storage of materials) to areas authorized or approved by the HISD Issuing Authority.
B. Temporary buildings (e.g., storage sheds, shops, offices) may be erected by the Contractor only with the prior written approval of the HISD Issuing Authority and shall be built with labor and materials furnished by the Contractor without expense to HISD. The temporary buildings shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon the completion of the Work. With the written consent of the HISD Issuing Authority, the buildings and utilities may be abandoned and need not be removed. Asbest such written consent, Contractor shall reimburse HISD for any costs incurred by HISD to remove abandoned temporary buildings. Unless stated otherwise herein, any facilities or utilities required by Contractor shall be furnished by Contractor at Contractor’s expense.
C. The Contractor shall, under regulations prescribed by the HISD Issuing Authority, use only established roadways or temporary roadways constructed by the Contractor when and as authorized by the HISD Issuing Authority. The Contractor shall comply with all federal, state, and local laws and regulations when transporting materials. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks or roads.
OPERATIONS AND STORAGE AREAS. 18.1 Job Order Contractor shall confine all operations (including storage of materials) to areas authorized or approved by Owner.
18.2 Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by Job Order Contractor only with the approval of Owner and shall be built with labor and materials furnished by Job Order Contractor without expense to Owner. The temporary buildings and utilities shall remain the property of Job Order Contractor and shall be removed by Job Order Contractor at its expense upon the completion of the Work. With the written consent of Owner, the buildings and utilities may be abandoned and need not be removed.
18.3 Job Order Contractor shall use only established roadways or temporary roadways constructed by Job Order Contractor when and as authorized by Owner. Job Order Contractor shall comply with all Federal, state and local laws and regulations when transporting materials.
OPERATIONS AND STORAGE AREAS. In accordance with FAR Clause 52.236-10 “Operations and Storage Areas” (APR 1984), temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Subcontractor only with the approval of the project engineer and shall be built with labor and materials furnished by the Subcontractor without expense to Chemonics. The temporary buildings and utilities shall remain the property of the Subcontractor and shall be removed by the Subcontractor at its own expense upon completion of the work. The Subcontractor shall use only established roadways and bridges or use temporary roadways. When materials are transported in executing the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or applicable laws. When it is necessary to cross curbs or sidewalks, the Subcontractor shall protect the property from damage. The Subcontractor shall repair or pay for the repair of any damaged curbs, sidewalks, bridges, and roads.
OPERATIONS AND STORAGE AREAS. 15.1 The CONTRACTOR shall confine all operations (including storage of materials) to areas authorized or approved by the OWNER. The CONTRACTOR shall hold and save the OWNER and its representatives, free and harmless from liability of any nature occasioned by the CONTRACTOR'S performance.
15.2 Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the CONTRACTOR only with the approval of the OWNER and shall be built with labor and materials furnished by the CONTRACTOR without expense to the OWNER. The temporary buildings and utilities shall remain the property of the CONTRACTOR and shall be removed by the CONTRACTOR at its expense upon completion of the work. Only with the written consent of the OWNER may the buildings and utilities be abandoned and not removed.
15.3 The CONTRACTOR shall use only established roadways, or use temporary roadways constructed by the CONTRACTOR when and as authorized by the OWNER. In such case, the CONTRACTOR shall minimize disruption and delays to traffic in the affected areas. When materials are transported in prosecuting the work vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the CONTRACTOR shall protect them from damage. The CONTRACTOR shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
OPERATIONS AND STORAGE AREAS. 18.1 Job Order Contractor shall confine all operations (including storage of materials) to areas authorized or approved by ▇▇▇▇▇▇▇’▇ Authorized Representative. Placement of materials and equipment shall be made with a minimum of interference to ▇▇▇▇▇▇▇ operations and personnel.
18.2 Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by Job Order Contractor only with the approval of ▇▇▇▇▇▇▇’▇ Authorized Representative and shall be built with labor and materials furnished by Job Order Contractor without expense to ▇▇▇▇▇▇▇’▇ Authorized Representative. The temporary buildings and utilities shall remain the property of Job Order Contractor and shall be removed by Job Order Contractor at its expense upon the completion of the Work. With the written consent of ▇▇▇▇▇▇▇’▇ Authorized Representative, the buildings and utilities may be abandoned and need not be removed.
18.3 Job Order Contractor shall use only established roadways or temporary roadways constructed by Job Order Contractor when and as authorized by ▇▇▇▇▇▇▇’▇ Authorized Representative. Job Order Contractor shall comply with all Federal, state and local laws and regulations when transporting materials.
OPERATIONS AND STORAGE AREAS. A. Contractor shall confine all operations (including storage of materials) to areas authorized or approved by Owner.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by Contractor only with the approval of Owner and shall be built with labor and materials furnished by Contractor without expense to Owner. The temporary buildings and utilities shall remain the property of Contractor and shall be removed by Contractor at its expense upon the completion of the Work. With the written consent of Owner, the buildings and utilities may be abandoned and need not be removed.
C. Contractor shall, under regulations prescribed by Owner, use only established roadways or temporary roadways constructed by Contractor when and as authorized by Owner. Contractor shall comply with all Federal, state and local laws and regulations when transporting materials.
OPERATIONS AND STORAGE AREAS. (a) The Contractor shall confine all operations (including storage of materials) on ANTHC premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the ANTHC, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
(b) Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the ANTHC. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
(c) The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
OPERATIONS AND STORAGE AREAS. The Contractor shall confine all operations (including storage of materials) to areas authorized or approved by the Project Manager. If the City makes offsite areas available to the Contractor for its operations or storage, the Contractor shall indemnify the City to the same extent as required under the Contract Documents for Work performed at the site, and such indemnification shall also apply to the owner of such offsite area(s) and its heirs, successors and assigns.