Partial Substantial Completion Clause Samples

The Partial Substantial Completion clause defines the process by which specific portions of a project can be officially recognized as substantially complete before the entire project is finished. This typically allows the owner to take possession or begin using completed sections while work continues elsewhere, and may trigger the start of warranty periods or partial release of retainage for those areas. The core function of this clause is to provide flexibility in project delivery, enabling phased occupancy or use, and to clarify responsibilities and timelines for both parties as different parts of the project reach completion at different times.
POPULAR SAMPLE Copied 11 times
Partial Substantial Completion. The Authority may, in its sole discretion, agree that a portion or component of the Work, acceptable to the Authority, may be certified by the Architect as Substantially Complete provided that: The requirements provided herein for issuance of a Certificate of Substantial Completion are complied with for the portion of the Work for which a Certificate of Partial Substantial Completion is being sought; Such portion and any and all appurtenances, utilities, transportation arteries and any other items required under the Contract Documents and necessary to serve that portion of the Work are sufficiently complete so that the Authority can utilize and occupy that portion for its intended use in accordance with the Contract Documents without material interference from any incomplete or improperly completed items of Work; and The Authority is fully able to use and occupy the portion(s) of the Work for the purposes intended and the Contractor separates the portion(s) of the Work substantially complete from non-complete areas of the Work in order to prevent noise, dust and other construction disturbances which would materially interfere with the use of such portion(s) for its intended use in accordance with the Contract Documents and to assure the safety of those entering, exiting and occupying the completed portion(s).
Partial Substantial Completion. The Project Manager may, in his/her sole discretion, certify less than all of the Work as Substantially Complete. The Project Manager may require the Contractor to prepare and submit a List of Unfinished and Nonconforming Work for any designated portion of the Work. When the Contractor has performed all of the Work identified on such list, the Contractor shall submit to the Architect, if applicable, and the Project Manager an Application for Certification of Substantial Completion for the designated portion of the Work, containing a notarized statement that: (1) the governing codes administration authorities have approved each building, if applicable, for the designated portion of the Work; and, (2) the Contractor has obtained certificates of occupancy for each building on the designated portion of the Work. If the Architect and/or the Project Manager agree that the designated portion of the Work is complete, they may issue a Certificate of Substantial Completion that identifies the substantially completed portion of the Work. A Certificate of Final Completion shall not be issued for less than all of the Work.
Partial Substantial Completion. 2 Substantial Completion when it occurs prior to the expiration of the Construction Time.
Partial Substantial Completion. The time at which a designated Milestone or part of the Work has progressed to the point where all of the following conditions are met: (a) it is sufficiently complete in accordance with the Contract Documents such that the Port or its tenant has full, unrestricted and permanent occupancy and use of that part of the Work, (b) only minor or incidental physical construction Work (Punchlist) remains to be completed, (c) all systems and parts of the Work are commissioned and functional, (d) utilities are connected and operate normally, (e) Contractor has provided all occupancy permits and easement releases for that part of the Work so designated, (f) Contractor has submitted, and the Port has accepted (or accepted except as noted) draft OperationOperating and Maintenance Documentation, (g) Contractor has submitted and the EngineerPort has accepted (or accepted except as noted) Warranty Documentation in accordance with the requirements of the Contract and (h) all training required to be provided by Contractor has been satisfactorily completed.
Partial Substantial Completion. In the event that any portion of any floor(s) of the Premises is occupied by Tenant for the purpose of conducting business therein (as opposed to preparing the Premises for Tenant's use) prior to the applicable commencement date for such floor (i.e., the Phase I Commencement Date for any floor in the Phase I portion of the Premises and the Phase II Commencement Date for any floor in the Phase II portion of the Premises), then with respect to such floor(s), Tenant's tenancy thereof shall be deemed to be by the day and all of Tenant's obligations hereunder shall commence as of the first day of such occupancy; provided, however, that for each day prior to such applicable commencement date that Tenant occupies any floor(s) of the Premises, Tenant shall be responsible for paying Base Rent only for such floor(s) (such Base Rent to be calculated as the rentable square feet of such floor(s) times the per square foot rate payable hereunder during Lease Year 1 as set forth in ITEM 6 of the Schedule, pro rated for the number of days in such tenancy). The foregoing sentence shall not be deemed to imply a right of Tenant to occupy any floor of the Premises prior to the date that the Tenant Work for such floor is substantially complete and Landlord notifies Tenant thereof nor an obligation that Tenant occupy any portion of the Premises prior to the applicable commencement date for such portion of the Premises, nor shall it be deemed an obligation of Landlord to deliver any portion of the Premises prior to the applicable commencement date for such portion of the Premises.
Partial Substantial Completion. Partial Substantial Completion of the Work shall occur when the Village determines that a portion of the Work, as defined in the Contract Documents and/or otherwise by logical boundaries, is Substantially Complete in accordance with the Contract Documents. The Village may (but shall not be obligated to) agree that a portion or component of the Work, acceptable to the Village in its sole discretion, may be certified as Substantially Complete provided that: i. The requirements provided under Sections 6.10 and 6.1 1 above for issuance of a Certificate of Substantial Completion are complied with for the portion of the Work for which a Certificate of Partial Substantial Completion is being sought; ii. Such portion and any and all appurtenances, utilities, transportation arteries and any other items required under the Contract Documents and necessary to serve that portion of the Work are sufficiently completed, a temporary certificate of completion or Certificate of Occupancy, as applicable, is issued for the portion of the Work for which a Certificate of Partial Substantial Completion is being sought and/or all conditions or requirements of authorities having jurisdiction are complied with, to permit the Village to utilize and occupy that portion for its intended use in accordance with the Contract Documents without material interference from any incomplete or improperly completed items of Work; iii. The Village is fully able to use and occupy the portion of the Work for the purposes intended and the Design/Builder separates the portion of the Work which is Substantially Complete from non-complete areas of the Project in order to prevent noise, dust and other construction disturbances which would materially interfere with the use of such portion for its intended use in accordance with the Contract Documents and to assure the safety of those entering, exiting and occupying the Substantially Completed portion of the Work; and iv. Partial Substantial Completion shall not constitute Final Completion of the Work or Substantial Completion of the Project, nor shall it relieve the Design/Builder of any responsibility for the correction of Work (whether or not included in portion of Work Substantially Complete) or for the performance of Work not complete at the time of Partial Substantial Completion.

Related to Partial Substantial Completion

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.

  • Substantial Completion 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which has been accepted in writing to by the State, is substantially complete as defined in Subparagraph

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Certificate of Substantial Completion The certificate prepared by the Designer and approved by the Owner to the effect that the Work has reached Substantial Completion.