Uncovering the Work Sample Clauses

Uncovering the Work. Any Work that is covered by the Contractor before required inspections or tests are performed or approvals are given shall be uncovered by the Contractor to the extent directed by RMWD, and the Contractor shall bear all the expense for uncovering, exposure, inspection, testing, and of satisfactory reconstruction.
Uncovering the Work. 6.21.1 If the CM covers Work contrary to the requirements of the Contract Documents or contrary to the written request of the Contracting Authority or A/E, the CM shall, if the Contracting Authority or A/E requests in writing, uncover that Work for observation, correct it if not in conformity with the Contract Documents, and recover it at the CM’s expense without adjustment of the Contract Times. 6.21.2 If the CM covers Work in accordance with the Contract Documents and not contrary to a request from the A/E or Contracting Authority for an opportunity to observe the Work prior to covering, the CM shall, if the A/E requests in writing, uncover that Work. 6.21.2.1 If the uncovered Work is Defective Work, the CM shall pay the costs of uncovering, correcting, and recovering the Work and shall not be entitled to an adjustment of the Contract Times. 6.21.2.2 If the uncovered Work is not Defective Work and the CM believes that it is entitled to an adjustment of the Contract Sum or Contract Times, or both, on account of the uncovering and recovering of the Work, the CM may request a Change Order by giving written notice under Section 7.3.2 within seven days after the Contracting Authority or A/E observes the uncovered Work.
Uncovering the Work. 4.1.15.1 If any Work required to be inspected, tested or approved is covered contrary to the request of the Project Manager, the Work shall, if requested by the Project Manager, be uncovered for observation, inspection, testing or approval and replaced at the DESIGN-BUILDER’s expense. 4.1.15.2 If any Work has been covered in accordance with the Final Construction Documents which the Project Manager has not specifically requested to observe, and if the Project Manager considers it necessary or advisable that the covered Work be inspected or tested by others, the DESIGN-BUILDER, upon written request of the Project Manager, shall uncover, expose, or otherwise make available for observation, inspection, or testing that portion of the Work in question, furnishing all necessary labor, material, and equipment. If it is found that such Work is Defective, the DESIGN-BUILDER shall bear the expense of such uncovering, exposure, observation, inspection, testing, and satisfactory reconstruction. If, however, such Work is not found to be Defective, the DESIGN-BUILDER may be allowed an adjustment in the GMP or an extension of the Contract Time, or both, directly attributable to such uncovering, exposure, observation, inspection, testing, and reconstruction, if it makes a claim in accordance with the requirements of this Contract.
Uncovering the Work. 6.22.1 If the Contractor covers Work contrary to the requirements of the Contract Documents or contrary to the written request of the Contracting Authority or the A/E, or A/E, the Contractor shall, if the Contracting Authority or A/E requests in writing, uncover that Work for observation, correct it if not in conformity with the Contract Documents, and recover it at the Contractor'sContractor’s expense and without adjustment of the Contract Times. 6.22.2 If the Contractor covers Work in accordance with the Contract Documents and not contrary to a request from the A/E or the Contracting Authority for an opportunity to observe the Work prior to covering, the Contractor shall, if the A/E requests in writing, uncover that Work. 6.22.2.1 If the uncovered Work is Defective Work, the Contractor shall pay the costs of uncovering, correcting, and recovering the Work and shall not be entitled to an adjustment of the Contract Times. 6.22.2.2 If the uncovered Work is not Defective Work and the Contractor believes that it is entitled to an adjustment of the Contract Sum or Contract Times, or both, on account of the uncovering and recovering of the Work, the Contractor may request an adjustment to the Contracta Change Order by giving written notice under Section 7.3.2 within 7 days after the Contracting Authority or A/E observes the uncovered Work.
Uncovering the Work. 6.21.1 If the DB covers Work contrary to the requirements of the Contract Documents or contrary to the written request of the Contracting Authority, the DB shall, if the Contracting Authority requests in writing, uncover that Work for observation, correct it if not in conformity with the Contract Documents, and recover it at the DB’s expense without adjustment of the Contract Times. 6.21.2 If the DB covers Work in accordance with the Contract Documents and not contrary to a request from the Contracting Authority for an opportunity to observe the Work prior to covering, the DB shall, if the Contracting Authority requests in writing, uncover that Work. 6.21.2.1 If the uncovered Work is Defective Work, the DB shall pay the costs of uncovering, correcting, and recovering the Work and shall not be entitled to an adjustment of the Contract Times. 6.21.2.2 If the uncovered Work is not Defective Work and the DB believes that it is entitled to an adjustment of the Contract Sum or Contract Times, or both, on account of the uncovering and recovering of the Work, the DB may request a Change Order by giving written notice under Section 7.3.2 within 7 days after the Contracting Authority observes the uncovered Work.
Uncovering the Work. 11.1 If any portion of the Work should be covered contrary to the request of the City or contrary to requirements specifically expressed in the Contract Documents relative to inspection by the City, it must, if required in writing by the City, be uncovered for its observation and inspection and shall be replaced at the Contractor’s expense. 11.2 If any other portion of the Work has been covered, the City may request to see such Work and the Contractor shall uncover it. If such Work is found to be in accordance with the Contract Documents, the cost of uncovering and replacement shall be charged to the City by appropriate Change Order. If such Work is found not to be in accordance with the Contract Documents, the Contractor shall pay such costs unless it is found that the City caused this condition, in which event the City shall be responsible for the payment of such costs.
Uncovering the Work. 4.1.17.1 If any Work required to be inspected, tested or approved is covered contrary to the request of the Project Manager, the Work shall, if requested by the Project Manager, be uncovered for observation, inspection, testing or approval and replaced at the DESIGN‐BUILDER’S expense.
Uncovering the Work. If any Construction that is to be inspected, tested or approved is covered without written concurrence of CITY’S REPRESENTATIVE, it must, if requested by CITY or the CITY’S REPRESENTATIVE, be uncovered for observation. Such uncovering shall be at CONTRACTOR’S expense and will exclude the right to an increase in the Contract Price or Contract Time unless CONTRACTOR has given CITY or the CITY’S REPRESENTATIVE timely written notice of CONTRACTOR’S intention to cover such Construction and CITY or the CITY’S REPRESENTATIVE has not acted with reasonable promptness in response to such notice. 4.3.5.1 If CITY considers it necessary or advisable that covered Work be observed by CITY’S REPRESENTATIVE or the ARCHITECT or ENGINEER, or inspected or tested by others, CONTRACTOR, at CITY’S request, shall uncover, expose or otherwise make available for observation, inspection or testing as CITY may require, that portion of the Work in question, furnishing all necessary labor, material and equipment. If it is found that such Work is defective, CONTRACTOR shall bear all the expenses of such uncovering, exposure, observation, inspection and testing and of satisfactory reconstruction, including compensation for additional professional services and any additional expenses experienced by the CITY due to delays to others performing additional work, other contractual obligations, and CITY shall be entitled to issue an appropriate deductive Change Order. CONTRACTOR shall further bear the
Uncovering the Work. If any Work has been covered which the Owner, Engineer, or Resident Project Representative has not specifically requested to observe prior to its being covered, the Contractor, at the Owner’s request, will uncover, expose or otherwise make available for observation, inspection or testing, that portion of the Work in question. If the Owner or Engineer considers it necessary or advisable that covered Work be inspected or tested by others the Contractor, at the Owner’s request, will uncover, expose or otherwise make available for observation, inspection or testing, that portion of the Work in question. Uncovering of the Work shall be completed as the Owner or Engineer may require and the Contractor shall furnish all necessary labor, material, and equipment. If it is found that such Work is defective, the Contractor will bear all costs of such uncovering, exposure, observation, inspection, and testing, and reconstruction to the satisfaction o fthe Owner and Engineer.. If, however, such Work is not found to be defective, the Contractor will be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly attributable to such uncovering, exposure, observation, inspection, testing, and reconstruction, if he/she makes a Claim therefore.

Related to Uncovering the Work

  • Continuing the Work The Contractor shall carry on the Work and adhere to the progress schedule during all disputes, disagreements or alternative resolution processes with the Owner. The Contractor shall not delay or postpone any Work because of the pending resolution of any disputes, disagreements or processes, except as the Owner and the Contractor may agree in writing.

  • Completion of the Work The Contractor must obtain Material Completion as defined in Section 6.1.2 below prior to any occupancy of the Project.

  • UNCOVERING OF WORK 13.1.1 If any portion of the Work should be covered contrary to the request of the Architect or to requirements specifically expressed in the Contract Documents, it must, if required in writing by the Architect, be uncovered for his or her observation and shall be replaced at the Contractor's expense. 13.1.2 If any other portion of the Work has been covered which the Architect has not specifically requested to observe prior to being covered, the Architect may request to see such Work and it shall be uncovered by the Contractor. If such Work is found in accordance with the Contract Documents, the cost of uncovering and replacement shall, by appropriate Change Order, be charged to the State. If such Work is found not to be in accordance with the Contract Documents, the Contractor shall pay such costs unless it is found that this condition was caused by the State or a separate contractor as provided in Article 6 of these General Conditions, in which event the State shall be responsible for the payment of such costs.

  • Uncovering and Correction of Work 12.1 The Contractor shall promptly correct Work rejected by the Owner or failing to conform to the requirements of the Contract Documents, whether observed before or after Substantial Completion and whether or not fabricated, installed or completed, and shall correct any Work found to be not in accordance with the requirements of the Contract Documents within a period of two years from the date of Substantial Completion, or by terms of an applicable special warranty required by the Contract Documents. The provisions of this Article apply to work done by Subcontractors as well as to Work done by direct employees of the Contractor. 12.2 At any time during the progress of the work, or in any case where the nature of the defects shall be such that it is not expedient to have them corrected, the Owner, at their option, shall have the right to deduct such sum, or sums, of money from the amount of the contract as they consider justified to adjust the difference in value between the defective work and that required under contract including any damage to the structure.

  • Examination of work before covering up In respect of the work which the Authority’s Engineer is entitled to examine, inspect, measure and/or test before it is covered up or put out of view or any part of the work is placed thereon, the Contractor shall give notice to the Authority’s Engineer whenever any such work is ready and before it is covered up. The Authority’s Engineer shall then either carry out the examination, inspection or testing without unreasonable delay, or promptly give notice to the Contractor that the Authority’s Engineer does not require to do so. Provided, however, that if any work is of a continuous nature where it is not possible or prudent to keep it uncovered or incomplete, the Contractor shall notify the schedule of carrying out such work to give sufficient opportunity, not being less than 3 (three) business days’ notice, to the Authority’s Engineer to conduct its inspection, measurement or test while the work is continuing. Provided further that in the event the Contractor receives no response from the Authority’s Engineer within a period of 3 (three) business days from the date on which the Contractor’s notice hereunder is delivered to the Authority’s Engineer, the Contractor shall be entitled to assume that the Authority’s Engineer would not undertake the said inspection.