Final Completion and Acceptance of the Work Clause Samples

The "Final Completion and Acceptance of the Work" clause defines the process by which a project owner formally acknowledges that all contractual work has been completed to the required standards. Typically, this involves a final inspection, submission of necessary documentation, and resolution of any outstanding issues or punch list items before the owner issues a certificate of final completion. This clause ensures that both parties agree the work is finished and satisfactory, thereby triggering final payment obligations and marking the end of the contractor’s responsibilities, which helps prevent disputes over incomplete or defective work.
POPULAR SAMPLE Copied 1 times
Final Completion and Acceptance of the Work. (1) When the Contractor deems the Work, including all Punch List Work, to be complete, the Contractor must notify the Commission Representative in writing that the Work will be ready for an inspection and/or test on a date specified by the Contractor. Such notice is to be given at least five (5) days in advance of said date. If the Commission Representative concurs that the Work will be ready for inspection or testing on the date given, the Commission will make such inspection within a reasonable period of time. The scheduling of the inspection to determine whether the Work is complete does not relieve the Contractor of its responsibilities under the Contract Documents. The Contractor must cooperate in all respects in the scheduling and performance of the inspection. Upon inspection, the Commission will determine if Final Completion and Acceptance of the Work has been achieved and will issue a written notice to the Contractor confirming the Final Completion and Acceptance of the Work. (2) No action of the Commission, the Commission Representative, the Architect, or their respective Executive Directors, board members, officers, employees, or agents is to be construed as accepting Work done or material furnished in the performance of this Contract, which Work or materials are not in accordance with those specified and required by the Contract. The issuance of notice of Final Completion or the final payment does not affect the rights of the Commission against the Contractor (and the surety or sureties on the Performance and Payment Bond given by the Contractor) to enforce the complete performance of this Contract or to sue for the recovery of damages for failure to do so, nor affect the terms of Contractor’s guarantee in connection therewith.
Final Completion and Acceptance of the Work a. Punch List Completion (1) The Design-Builder understands and agrees that time is of the essence in closing out the Work of this Contract. Upon Substantial Completion of the Work, the Punch List will be transmitted to the Design-Builder from the Commission. The Design-Builder agrees to begin performance of Punch List Work immediately after receipt of the Punch List. (2) Failure of the Design-Builder or its Subcontractors to begin the Punch List Work within 3 business Days after receipt of the Punch List will be construed as failure to prosecute the Work of the Contract. This document is provided as a DRAFT and is not intended to be considered FINAL. The Commission explicitly reserves the right to modify this document and provide a revised Sample to Phase II Proposers. (3) Punch List Work will be continuously prosecuted once begun and completed within the period set forth in the Punch List by the Commission Representative. The Commission Representative shall establish the period for completion of the Punch List Work after consultation with the Design-Builder. The period established by the Commission Representative will be based on the Commission Representative’s reasonable, good faith estimate of the time necessary for the Design-Builder to complete the Punch List Work.
Final Completion and Acceptance of the Work. When Contractor deems the Work to be complete, Contractor must notify SCC, in writing that the Work will be ready for an inspection and/or test on a date specified by Contractor. Such notice is given at least 15 calendar days in advance of said date. If SCC concurs that the Work will be ready for inspection or testing on the date given, SCC will make such inspection within a reasonable period of time. The scheduling of the inspection to determine whether the Work is complete does not relieve Contractor of its responsibilities under the Contract Documents. Contractor must cooperate in all respects in the scheduling and performance of the inspection. Once the inspection is complete and all outstanding issues have been Contractor must submit a sworn affidavit stating the following: 1. All payrolls, invoices for materials and equipment, and all other indebtedness connected with the Work for which SCC might in any way be responsible, have been paid or otherwise satisfied; 2. All waivers of lien required by the Contract have been provided to SCC; 3. As of the date the affidavit is signed, all known claims made by Subcontractors of any tier, and others against the Contractor or SCC, pertaining to the Work required under this Contract, were provided, in writing, to SCC; 4. All claims made by Subcontractors of any tier, and others against the Contractor or SCC pertaining to the Work required under this Contract have been resolved; 5. The warranties and guarantees required by the Contract have been provided to SCC; 6. All warranties and guarantees are in full force and effect; 7. The surety’s written consent, signed by its authorized representative, to final payment being made directly to the Contractor is attached to the affidavit; 8. The Contractor agrees that acceptance of final payment will constitute a general release to SCC, its agents, representatives, officials and employees of all other claims of liability for anything done or furnished or relating to the Work or for any act or neglect of SCC or its agents, representatives, officials and employees relating to or connected with this Contract; 9. Record documents, including but not limited to As-Built Drawings, record shop drawings and Operation and Maintenance manuals have been provided to SCC; 10. All other documents requested by SCC have been provided; and 11. A Final Certificate verifying wages and classifications for laborers and mechanics, including apprentices and trainees employed on the Project, in t...
Final Completion and Acceptance of the Work a. Punch List Completion (1) The Contractor understands and agrees that time is of the essence in closing out the Work of this Contract. Upon Substantial Completion of the Work, the Punch List will be transmitted to the Contractor from the Commission. (2) Failure of the Contractor or its Subcontractors to begin the Punch List Work within three (3) business days after receipt of the Punch List will be construed as failure to prosecute the Work of the Contract. (3) Punch List Work will be continuously prosecuted once begun and completed within the period set forth in the Punch List by the Commission Representative. The Commission Representative shall establish the period for completion of the Punch List Work after consultation with the Contractor. The period established by the Commission Representative will be based on the Commission Representative’s reasonable, good faith estimate of the time necessary for the Contractor to complete the Punch List Work.

Related to Final Completion and Acceptance of the Work

  • Acceptance of the Work 19.1 No act of, or failure to act by, the Owner or the OWNER'S REPRESENTATIVE during the course of the Work, nor any extension of time for the completion of the Work, shall be regarded as an acceptance of such Work or any part thereof, or of materials used therein, either wholly or in part. Acceptance shall be evidenced only by the Final Payment by the Owner to Contractor. Before any final certificate shall issue, Contractor shall execute an affidavit on the certificate that it accepts the same in full payment and settlement of all claims on account of Work done and materials furnished under this Contract, and that all claims for materials provided or labor performed have been paid or set aside in full. No waiver of any breach of this Contract by the Owner or anyone acting on Owner's behalf shall be held as a waiver of any other subsequent breach thereof. 19.2 Contractor agrees to guarantee all work under this Contract for a period of one year from the date of Final Payment by the Owner or within such longer period of time as may be prescribed by law or by the terms of any applicable special guarantee required under terms of Owner’s conditional acceptance of elements of the Work the Owner deems marginally substandard. If any unsatisfactory condition or damage develops within the time of this guarantee period due to materials or workmanship that are defective, inferior, or not in accordance with the Contract, as reasonably determined by the Owner or the OWNER’S REPRESENTATIVE, then the Contractor shall, when notified by the Owner or OWNER’S REPRESENTATIVE, immediately place such guaranteed Work in a condition satisfactory to the Owner or OWNER’S REPRESENTATIVE. Such guarantee shall be in addition to any implied warranty under law or other manufacturer’s or product supplier’s warranty. The provisions of this Article apply to Work done by Subcontractors as well as to Work done by direct employees of the Contractor, and are in addition to any other remedies or warranties provided by law.

  • Inspection and Acceptance Where the Master Agreement, a Participating Addendum, or an Order does not otherwise specify a process for inspection and Acceptance, this section governs. This section is not intended to limit rights and remedies under the applicable commercial code. Contractor shall provide right of access to the Lead State, or to any other authorized agent or official of the Lead State or other Participating or Purchasing Entity, at reasonable times, in order to monitor and evaluate performance, compliance, and quality assurance requirements under this Master Agreement. Upon delivery, the Purchasing Entity shall have 30 days to inspect. Products that do not meet specifications may be rejected. Failure to reject upon receipt, however, does not relieve the contractor of liability for material (nonconformity that substantially impairs value) latent or hidden defects subsequently revealed when goods are put to use. Acceptance of such goods may be revoked in accordance with the provisions of the applicable commercial code, and the Contractor is liable for any resulting expense incurred by the Purchasing Entity related to the preparation and shipping of Product rejected and returned, or for which Acceptance is revoked. If any services do not conform to contract requirements, the Purchasing Entity may require the Contractor to perform the services again in conformity with contract requirements, at no increase in Order amount. When defects cannot be corrected by re-performance, the Purchasing Entity may require the Contractor to take necessary action to ensure that future performance conforms to contract requirements; and reduce the contract price to reflect the reduced value of services performed. The warranty period shall begin upon Acceptance. The Purchasing Entity will make every effort to notify the Contractor, within thirty (30) calendar days following delivery, of non-acceptance of a Product or completion of Service. In the event that the Contractor has not been notified within 30 calendar days from delivery of Product or completion of Service, the Product and Services will be deemed accepted on the 31st day after delivery of Product or completion of Services. This clause shall not be applicable, if acceptance testing and corresponding terms have been mutually agreed to by both parties in writing. Acceptance Testing may be explicitly set out in a Master Agreement to ensure conformance to an explicit standard of performance. Acceptance Testing means the process set forth in the Master Agreement for ascertaining that the Product meets the standard of performance prior to Acceptance by the Purchasing Entity. If Acceptance Testing is prescribed, this subsection applies to applicable Products purchased under this Master Agreement, including any additional, replacement, or substitute Product(s) and any Product(s) which are modified by or with the written approval of Contractor after Acceptance by the Purchasing Entity. The Acceptance Testing period shall be thirty (30) calendar days or other time period identified in this Master Agreement or the Participating Addendum, starting from the day after the Product is delivered or, if installed, the day after the Product is installed and Contractor certifies that the Product is ready for Acceptance Testing. If the Product does not meet the standard of performance during the initial period of Acceptance Testing, Purchasing Entity may, at its discretion, continue Acceptance Testing on a day-to-day basis until the standard of performance is met. Upon rejection, the Contractor will have fifteen (15) calendar days to cure the standard of performance issue(s). If after the cure period, the Product still has not met the standard of performance, the Purchasing Entity may, at its option: (a) declare Contractor to be in breach and terminate the Order; (b) demand replacement Product from Contractor at no additional cost to Purchasing Entity; or, (c) continue the cure period for an additional time period agreed upon by the Purchasing Entity and the Contractor. Contractor shall pay all costs related to the preparation and shipping of Product returned pursuant to the section. No Product shall be deemed Accepted and no charges shall be paid until the standard of performance is met. The warranty period shall begin upon Acceptance.

  • Inspection; Acceptance If defective or incorrect material is delivered, Region 4 ESC may make the determination to return the material to the Contractor at no cost to Region 4 ESC. The Contractor agrees to pay all shipping costs for the return shipment. Contractor shall be responsible for arranging the return of the defective or incorrect material.

  • Inspection and Acceptance of Commodities The services provided by Contractor are not anticipated to include the provision of commodities. In the event commodities are offered under this contract, these provisions shall apply.

  • INSPECTION, ACCEPTANCE AND REJECTION a. All shipments of Goods and performance of Services shall be subject to Buyer’s right of inspection. Buyer shall have ninety (90) days (the “Inspection Period“) following the delivery of the Goods at the Delivery Point or performance of the Services to undertake such inspection, and upon such inspection Buyer shall either accept the Goods or Services (“Acceptance“) or reject them. Buyer shall have the right to reject any Goods that are delivered in excess of the quantity ordered or are damaged or defective. In addition, Buyer shall have the right to reject any Goods or Services that are not in conformance with the Specifications or any term of this Agreement. Transfer of title to Buyer of Goods shall not constitute Buyer’s Acceptance of those Goods. Buyer shall provide Supplier within the Inspection Period notice of any Goods or Services that are rejected, together with the reasons for such rejection. If Buyer does not provide Supplier with any notice of rejection within the Inspection Period, then Buyer will be deemed to have provided Acceptance of such Goods or Services. Buyer’s inspection, testing, or Acceptance or use of the Goods or Services hereunder shall not limit or otherwise affect Supplier’s warranty obligations hereunder with respect to the Goods or Services, and such warranties shall survive inspection, test, Acceptance and use of the Goods or Services. b. Buyer shall be entitled to return rejected Goods to Supplier at Supplier’s expense and risk of loss for, at Buyer’s option, either: (i) full credit or refund of all amounts paid by Buyer to Supplier for the rejected Goods; or (ii) replacement Goods to be received within the time period specified by Buyer. Title to rejected Goods that are returned to Supplier shall transfer to Supplier upon such delivery and such Goods shall not be replaced by Supplier except upon written instructions from Buyer. Supplier shall not deliver Goods that were previously rejected on grounds of non-compliance with this Agreement, unless delivery of such Goods is approved in advance by Buyer, and is accompanied by a written disclosure of Buyer’s prior rejection(s).