Requests for Change Orders Clause Samples

The "Requests for Change Orders" clause defines the process by which one party can formally propose modifications to the original terms, scope, or deliverables of a contract. Typically, this clause outlines the steps required to submit a change request, such as providing written notice, detailing the nature and justification for the change, and specifying any impacts on cost or schedule. For example, if a contractor encounters unforeseen site conditions, they would use this process to request additional time or compensation. The core function of this clause is to provide a structured and documented method for managing changes, thereby reducing disputes and ensuring that all parties agree to and understand any alterations to the contract.
Requests for Change Orders. Within ten (10) days of submitting its Notice of Claim, the Construction Manager shall submit to the Owner its Request for Change Order, which shall include a written statement of all details of the claim, including a description of the Work affected, the time extension requested (if any), and the amount sought for the claim. Waiver - The Construction Manager agrees that the Owner shall not be liable for any claim that the Construction Manager fails to submit as a Notice of Claim and Request for Change Order as provided in this paragraph. Any claim not so submitted shall be deemed waived.
Requests for Change Orders. ‌ 12.6.1 Subject to the terms of the Contract Documents, if Contractor believes that any act, error or omission of Owner constitutes a change in the Work entitling it to additional compensation, it shall within twenty (20) Days after the date on which Contractor discovers, or should have discovered with the exercise of appropriate diligence, the relevant act, error or omission of Owner (provided that the necessity of extra cost and/or time is already determinable, even if such extra cost and/or time has not yet been incurred), submit a Request for Change Order to the Contracting Officer stating the amount of the additional compensation and/or additional time to which it is entitled and the justification for the request. The Contracting Officer shall evaluate the Request for Change Order within a reasonable time and advise Contractor whether Owner will grant in whole, grant in part, or deny the Request for Change Order. Any additional compensation granted shall be recorded in the form of a Change Order. Failure of Contractor to timely submit a Request for Change Order in strict, not substantial, accordance with the requirements of this Section 12.6.1 shall constitute a waiver of and shall forever bar any recovery arising out of the pertinent act, error, or omission of Owner, even if Owner was not prejudiced thereby. 12.6.2 No proposal or claim by Contractor on account of changes to the Work shall be allowed for any costs or delay incurred more than twenty (20) Days before Contractor gives written notice as required.
Requests for Change Orders. The provisions of this Section 11.6 shall apply only if the Prompt Pay Act is applicable to a Project, and shall be null and void and of no force or effect for Projects to which the Prompt Pay Act does not apply. 11.6.1 If Contractor believes that it is entitled to an increase in the Stipulated Sum or the GMP for reasons including: (i) a written interpretation from the A/E, (ii) a written order for a minor change in the Work issued by the A/E, (iii) termination by Owner, or (iv) other reasonable grounds, then Contractor shall submit a written request for a for a Change Order seeking an increase to the Stipulated Sum or GMP to Owner and the A/E in the form to be provided by Owner prior to the commencement of the Work hereunder executed by Contractor’s Designated Representative, which satisfies all of the following requirements: .1 The request for a Change Order shall be accompanied by a written report by Contractor setting forth the facts and reasons for proceeding under this Section, including, without limitation, reasonable supporting backup documentation from all affected Subcontractors. .2 The request for a Change Order shall include a clear and precise description of any proposed change in the Work, together with a detailed breakdown of the cost of labor and materials for all trades involved, including, without limitations, rates and unit prices (if applicable), and the impact on the Schedule relating to any proposed change in the Work. 11.6.2 No request for a Change Order shall be valid or considered to have been "submitted" unless the same has been delivered to Owner in accordance with the provisions of Section 16.2, with simultaneous delivery to the A/E. The date of "submission" of any request for a Change Order shall be determined in accordance with the provisions of Section 16.2. 11.6.3 Owner will, within thirty (30) days after the later of: (i) the date of commencement of performance of the Work on which the request for a Change Order is based; or (ii) the date of submission of any request for a Change Order; either approve or reject (in whole or in part) the request for a Change Order by delivering to Contractor a written notice of approval or rejection of the request for a Change Order. A request for a Change Order which is neither approved nor rejected (in whole or in part) by Owner within such thirty
Requests for Change Orders. (i) Any SCA request for a Change Order shall be submitted to Developer in writing. SCA requests for Change Orders shall be subject to Developer’s approval, not to be unreasonably withheld, provided, that it shall not be deemed unreasonable for Developer to withhold its approval for any Change Order which: (A) Intentionally Omitted.
Requests for Change Orders. (RFCO) 1. The OR shall ensure that all RFCOs, including any and all requested modifications to the contract documents, are in writing from the GC including supplemental drawings, specifications, supporting documentations and proposed/allowable costs to fully describe the change and why it is justified as a change to the current CDs prior to forwarding the RFCO to the Village. 2. The OR shall review RFCOs, assist in negotiating GC’s proposals, submit recommendations to the Village, and, if they are accepted, prepare change orders that incorporate the approved modifications to the CDs. 3. Prior to forwarding the RFCO to the Village the OR shall include a cover memo evaluating the RFCO. The evaluation shall include a preliminary recommendation as to whether the RFCO is justified given the current CDs and if proposed work, quantities, prices and other data in the GC’s proposal are found to be reasonable and in conformance with the CDs. 4. The OR shall maintain an RFCO log documenting, at a minimum, when a properly submitted RFCO was received, its reference number and title, a very brief description of the request, the requested amount, its current status, and an approved amount (positive or negative/increase or decrease) if applicable. 5. The OR may be requested from time to time to attend a Village Council meeting in support of Village staff to help explain any contract modifications necessary as a result of an RFCOs.
Requests for Change Orders 

Related to Requests for Change Orders

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • Change Order The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.