SCHEDULE OF THE WORK Clause Samples
The "Schedule of the Work" clause defines the timeline and sequence for completing the various tasks and milestones within a project. It typically outlines key dates, deadlines, and the order in which work activities must occur, often referencing a detailed project schedule or Gantt chart. This clause ensures that all parties are aware of their time-related obligations and helps coordinate efforts, ultimately providing a clear framework to manage progress and avoid delays.
POPULAR SAMPLE Copied 2 times
SCHEDULE OF THE WORK. 6.2.1 Before submitting the first application for payment, the Construction Manager shall submit to the Owner and, if directed, the Design Professional a Schedule of the Work showing the dates on which the Construction Manager plans to commence and complete various parts of the Work, including dates on which information and approvals, self-performed work, selection of allowance items, and other known Owner services, tasks and work are required from the Owner. The Construction Manager shall comply with the approved Schedule of the Work, unless directed by the Owner to do otherwise or the Construction Manager is otherwise entitled to an adjustment in the Contract Time. The Construction Manager shall update the Schedule of the Work on a monthly basis or at appropriate intervals as required by the conditions of the Work and the Project.
6.2.2 The Owner may determine the sequence in which the Work shall be performed, provided it does not unreasonably interfere with the approved project schedule. The Owner may require the Construction Manager to make reasonable changes in the sequence at any time during the performance of the Work in order to facilitate the performance of work by the Owner or Others. To the extent such changes directly increase the Construction Manager's costs or time, the GMP or the dates of Substantial or Final Completion shall be equitably adjusted.
SCHEDULE OF THE WORK. The Design-Builder shall prepare and submit a Schedule of Work for the Owner’s acceptance and written approval as to milestone dates. This schedule shall indicate the dates for the start and completion of the various stages of the Work, including the dates when information and approvals are required from the Owner. The Schedule shall be revised as required by the conditions of the Work.
SCHEDULE OF THE WORK. 7.2.1 Before submitting the first application for payment, the Construction Manager shall submit to the Owner and, if directed, the Design Professional a Schedule of the Work showing the dates on which the Construction Manager plans to commence and complete various parts of the Work, including dates on which information and approvals are required from the Owner. The Construction Manager shall comply with the approved Schedule of the Work, unless directed by the Owner to do otherwise or the Construction Manager is otherwise entitled to an adjustment in the Contract Time. The Construction Manager shall update the Schedule of the Work on a monthly basis or at appropriate intervals as required by the conditions of the Work and the Project.
7.2.2 The Owner may determine the sequence in which the Work shall be performed, provided it does not unreasonably interfere with the approved project schedule. The Owner may require the Construction Manager to make reasonable changes in the sequence at any time during the performance of the Work in order to facilitate the performance of work by the Owner or Others. To the extent such changes increase the Construction Manager's costs or time, the GMP or the Dates of Substantial or Final Completion shall be equitably adjusted.
SCHEDULE OF THE WORK. Schedule of the Work" is a statement and timeline that shows when each distinct portion of the Work will be completed during the Construction Time. Each Schedule of the Work must, at minimum, (a) contain details required by the Design-Build Documents,
SCHEDULE OF THE WORK. 6.2.1 Before submitting the first application for payment, the Constructor shall submit to the Owner a Schedule of the Work showing the dates on which the Constructor plans to commence and complete various parts of the Work, including dates on which information and approvals are required from the Owner. The Constructor shall comply with the approved Schedule of the Work, unless directed by the Owner to do otherwise or the Constructor is otherwise entitled to an adjustment in the Contract Time. The Constructor shall update the Schedule of the Work on a monthly basis or at appropriate intervals as required by the conditions of the Work and the Project.
6.2.2 The Owner may determine the sequence in which the Work shall be performed, provided it does not unreasonably interfere with the Schedule of the Work. The Owner may require the Constructor to make reasonable changes in the sequence at any time during the performance of the Work in order to facilitate the performance of work by the Owner or Others. To the extent such changes increase the Constructor’s costs or time, the Contract Time shall be equitably adjusted, and the Constructor shall be paid its additional costs plus Constructor’s Fee.
SCHEDULE OF THE WORK. 5.2.1 Before submitting the first application for payment, the Contractor shall have submitted to the Owner a Schedule of the Work, attached as Attachment D, that shall show the dates on which the Contractor plans to commence and complete various parts of the Work, including dates on which information and approvals are required from the Owner. On the Owner's written approval of the Schedule of the Work, the Contractor shall comply with it unless directed by the Owner to do otherwise. The Contractor shall update the Schedule of the Work on a monthly basis or at appropriate intervals as required by the conditions of the Work and the Project.
SCHEDULE OF THE WORK. The Subcontractor is responsible for the sequencing, scheduling and coordinating of the Work, for monitoring the progress of the Work, and for taking appropriate action to keep the Work on schedule. Within two weeks after signing the Subcontract, unless otherwise extended by the Contractor at the time of the signing of the Subcontract, the Subcontractor shall prepare and submit to the Contractor a preliminary schedule for accomplishing the Work based upon the completion time stated in the Subcontract. A fully complete progress schedule for accomplishing the work must be submitted in like manner no later than 60 days after signing the Subcontract. No progress payments will be payable to the Subcontractor until after it has submitted a preliminary schedule which is acceptable to the Contractor. Neither the second progress payment nor any subsequent payment shall be payable to the Subcontractor until it has submitted a fully complete progress schedule.
SCHEDULE OF THE WORK. 6.2.1 Before submitting its first application for payment, Construction Manager shall submit to Owner and, if directed, Design Professional a Schedule of the Work showing the dates on which Construction Manager plans to begin and complete various parts of the Work, including dates on which information and approvals are required from Owner. Except as otherwise directed by Owner, Construction Manager shall comply with the approved Schedule of the Work . Unless otherwise agreed, the Schedule of the Work shall be formatted in a detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work. Construction Manager shall update the Schedule of the Work on a monthly basis or as mutually agreed by the Parties.
6.2.2 Owner may determine the sequence in which the Work shall be performed, provided it does not unreasonably interfere with the approved Schedule of Work. Owner may require Construction Manager to make reasonable changes in the sequence at any time during the performance of the Work in order to facilitate the performance of work by Owner or Others. If Construction Manager consequently incurs costs or is delayed, the GMP or the Dates of Substantial or Final Completion, or both, Construction Manager may seek equitable adjustment under ARTICLE 9.
SCHEDULE OF THE WORK. When Project requirements have been sufficiently identified, at a minimum at the completion of schematic design, design development, 50% construction drawings, and 100% construction drawings, the Construction Manager shall prepare a preliminary Schedule of the Work for the Design Professional's review and the Owner's approval. The Construction Manager shall coordinate and integrate the Schedule of the Work with the services and activities of the Owner, Construction Manager, Design Professional, and the requirements of governmental entities. As design proceeds, the Construction Manager shall update the Schedule of the Work to indicate proposed activity sequences, durations, or milestone dates for such activities as receipt and approval of pertinent information, issuance of the drawings and specifications, the preparation and processing of shop drawings and samples, delivery of materials or equipment requiring long-lead-time procurement, Owner's occupancy requirements and estimated date of Substantial Completion of the Project. If Schedule of the Work updates indicates that milestone dates contained in prior Schedules of the Work will not be met, the Construction Manager shall notify and make recommendations to the Owner. If the Project is to be completed in phases, the Construction Manager shall make recommendations to the Owner and Design Professional regarding the phased issuance of the drawings and specifications.PRELIMINARY EVALUATION Construction Manager shall provide a preliminary evaluation of Owner's Program and report such findings to Owner and Design Professional.
SCHEDULE OF THE WORK. Contractor shall perform the Work within the time frame established on the Statement of Work.