PAYMENTS TO CONTRACTOR AND COMPLETION Clause Samples

PAYMENTS TO CONTRACTOR AND COMPLETION. 14.01 Schedule of Values
PAYMENTS TO CONTRACTOR AND COMPLETION. Schedules: 13.1 At least ten (10) days prior to submitting the first Application for a progress payment, CONTRACTOR shall (except as otherwise specified in the General Requirements) submit to PROJECT MANAGER a progress schedule, a final schedule of Shop Drawing submission and where applicable a schedule of values of the Work. These schedules shall be satisfactory in form and substance to PROJECT MANAGER. The schedule of values shall include quantities and unit prices aggregating the Contract Price, and shall subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during construction. Upon acceptance of the schedule of values by PROJECT MANAGER, it shall be incorporated into a form of Application for Payment acceptable to PROJECT MANAGER. Application for Progress Payment: 13.2 On or before the seventh day of each month (but not more often than once a month), CONTRACTOR shall submit to PROJECT MANAGER for review an Application for Payment filled out and signed by CONTRACTOR covering the Work completed for the previous month, updated progress schedule, updated CONTRACTOR red lines (as built) and accompanied by such supporting documentation as is required by the Contract Documents and also as PROJECT MANAGER may reasonably require. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the site or at another location, as agreed to in writing by the PROJECT MANAGER, the Application for Payment shall also be accompanied by such data, satisfactory to OWNER, as will establish OWNERS title to the material and equipment and protect OWNERS interest therein, including applicable insurance. All costs associated with the PROJECT MANAGERS verification that materials and equipment are suitably stored must be borne by the CONTRACTOR. Materials such as base, aggregate, bedding material, reinforcing steel, etc. that may be readily incorporated into construction will not be considered for payment as materials on hand. Each subsequent Application for Payment shall include an affidavit of CONTRACTOR stating that all previous progress payments received on account of the Work have been applied to discharge in full all of CONTRACTORS obligations reflected in prior Applications for Payment. Where the CONTRACTOR is withholding from the payment due to an assigned subcontractor for labor, materials or equipment, which is either complete or partially complete, the...
PAYMENTS TO CONTRACTOR AND COMPLETION. Applications for Payment will be processed by TOWN as provided in the General Conditions.
PAYMENTS TO CONTRACTOR AND COMPLETION. PAYMENTS SHALL BE MADE IN ACCORDANCE WITH APPROVED PAY APPLICATION(S). AUGUSTA shall compensate the CONTRACTOR for services, which have been authorized by AUGUSTA under the terms of this Agreement. DRAFT The CONTRACTOR may submit to AUGUSTA an application for payment, in a form acceptable to AUGUSTA and accompanied by all support documentation requested by AUGUSTA, for payment for the services, which were completed during the billing period. AUGUSTA shall review for approval said invoices. AUGUSTA shall have the right to reject payment of any invoice or part thereof if not properly supported, or if the costs requested or a part thereof, as determined solely by AUGUSTA, are unreasonably in excess of the actual work completed. AUGUSTA shall pay each such invoice or portion thereof as approved, provided that the approval or payment of any such invoice shall not considered to be evidence of performance by the CONTRACTOR to the point indicted by such invoice, or of receipt of acceptance by AUGUSTA of the service covered by such invoice. AUGUSTA shall pay any undisputed items contained in such invoices. Partial payments will be considered, but shall be decided on a case by case basis depending on the scope, duration, and total amount of specific project. Each invoice shall be accompanied by a letter progress report describing the total work accomplished for each phase and any problems, which have been encountered, which may inhibit execution of the work. The CONTRACTOR shall also submit an accurate updated schedule, and an itemized description of the percentage of total work completed for each phase during the billing period. When AUGUSTA authorizes the CONTRACTOR to proceed with the work authorized in a Task Order, it agrees to pay the CONTRACTOR for work completed, on the basis of Task Order Bid Schedule.
PAYMENTS TO CONTRACTOR AND COMPLETION. SC-15.01 Progress Payments
PAYMENTS TO CONTRACTOR AND COMPLETION. Schedule of Values: 14.1. The schedule of values established as provided in paragraph 2.9 will serve as the basis for progress payments and will be incorporated into a form of Application for Payment acceptable to ENGINEER. Progress payments on account of Unit Price Work will be based on the number of units completed.
PAYMENTS TO CONTRACTOR AND COMPLETION amount thereof, Owner may make a Claim therefor as provided in Paragraph 10.05. If the acceptance occurs after such recommendation, an appropriate amount will be paid by Contractor to Owner.
PAYMENTS TO CONTRACTOR AND COMPLETION. 13.1 Schedule of Values The Schedule of Values established as provided in paragraph 2.4.A.3 will serve as the basis for progress payments. Progress payments on account of Unit Price Work will be based on the number of units completed.
PAYMENTS TO CONTRACTOR AND COMPLETION. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated above, but, in each case, less the aggregate of payments previously made and less such amounts as CITY’S REPRESENTATIVE shall determine, or CITY may withhold, in accordance with the General Conditions.
PAYMENTS TO CONTRACTOR AND COMPLETION. SC-14.02.A.1 Add the following as the last sentence of subparagraph 14.02.A.1: Payment for materials and equipment not incorporated in the Work, but delivered and suitably stored, shall be based only upon the actual cost of such materials to Contractor, and shall not include any overhead or profit to Contractor.